Statistical outliers and inconsistencies in our own data, each with the rule that flagged it, the numbers and the source. A list for review, never a verdict about a project or developer.

Updated 19 Nov 2026

Each line is a number that does not fit a rule. It can be a typo in a source, a reading error on our side, a special unit type or a real change. We check each one; if you know which, tell us.

140lines to review
1,997projects read

Asking price per m2 far from the market (5) · Handover date moved 12 months or more (106) · Register date differs from the advertised date (26) · Register progress does not fit the stage (1) · Sizes or prices that do not add up (2) · No units on an active register entry (0)

Asking price per m2 far from the market 5

Lowest asking price divided by the smallest unit size, compared with the other projects of the same market and currency (11 groups with 10 or more projects). Robust z-score on the logarithm (median and median absolute deviation); listed when it is 3.5 or more either way.

ProjectMarketNumbersSourceRead
Armani Beach Residences at Palm JumeirahDubai94,262 AED/m2 (price 23,000,000, 244 m2); market median 21,528 from 370 projects; z = 4.1foundgroup.ae18 Nov 2026
ORLA, Dorchester CollectionDubai220,116 AED/m2 (price 57,230,250, 260 m2); market median 21,528 from 370 projects; z = 6.5jre.ae18 Nov 2026
The Alba Residences by OmniyatDubai116,312 AED/m2 (price 16,400,000, 141 m2); market median 21,528 from 370 projects; z = 4.7dubairealestateiq.com18 Nov 2026
Azure by LapisRas Al Khaimah15,192 AED/m2 (price 790,000, 52 m2); market median 31,475 from 16 projects; z = -4.6propertyfinder.ae31 Oct 2026
Shoreline by DAMACRas Al Khaimah66,397 AED/m2 (price 4,515,000, 68 m2); market median 31,475 from 16 projects; z = 4.8damacproperties.com13 Nov 2026

Handover date moved 12 months or more 106

The handover date on record now is 12 months or more later than the first handover date we recorded for the project.

ProjectMarketNumbersSourceRead
Al Sidr (Saadiyat Lagoons)Abu Dhabi2026-Q2 (community start of handovers at 2022 launch) → 2027-Q3 (15 months)propertyfinder.ae13 Nov 2026
BashayerAbu Dhabi2029-Q1 → 2030-Q1 (12 months)modon.com30 Oct 2026
23 SquareAlanya2026-04 (portal listing) → 2027-Q3 (17 months)idealandpartners.com31 Oct 2026
Signature Apartments IIAlgarve2025-Q1 → 2026-Q2 (15 months)palmaresliving.com28 Oct 2026
TerracotaAlgarve2026-05 → 2027-Q2 (13 months)vilamouraworld.com13 Nov 2026
LuviyaAntalya2027-2028 (partner, May 2025) → 2028-Q4 (12 months)antalyamoydom.com.tr13 Nov 2026
Ritz-Carlton Reserve Residences at Cotton BayBahamas2027 → 2028 (12 months)brandedresi.com31 Oct 2026
The Ocean Club, Four Seasons ResidencesBahamas2027 → 2028 (12 months)theoceanclubresidences.com4 Nov 2026
XO ParqBalearics2025-Q4 → 2027 (24 months)xo-jay.com31 Oct 2026
ADDRESSBALIBali2026-Q2 (Alnair) → 2027-Q3 (15 months)addressbali.com28 Oct 2026
Buddha Club HouseBali2026-Q4 → 2028 (24 months)avalonbali.com13 Nov 2026
Magnum Resort SanurBali2026-Q1 → 2027 (21 months)magnumestate.com31 Oct 2026
Parq UbudBali2024-Q3 (portals) → 2025-Q3 (12 months)parqdevelopment.com13 Nov 2026
Temple HeightsBali2025-Q4 (developer quoted in Estonian press, Apr 2025) → 2027-Q1 (15 months)investlandbali.com13 Nov 2026
Umah UbudBali2025 (12-month build from July 2024 launch, implied) → 2027-Q2 (18 months)balitecture.com13 Nov 2026
Pendry Residences BarbadosBarbados2026 → 2027 (12 months)barbadostoday.bb31 Oct 2026
Belize Marriott Residences of Ambergris CayeBelize2023-12 → 2028-Q4 (60 months)ndrbelize.com31 Oct 2026
Boulevard (Phase 2, Blocks A1 to A6)Birmingham2025-Q3 → 2026-Q4 (15 months)investinplc.com31 Oct 2026
Bvlgari Resort & Mansions BodrumBodrum2026 → 2027 (12 months)bulgarimansionsbodrum.com13 Nov 2026
QUEENS DistrictBucharestQ1 2027 → Q1 2028 (12 months)queensdistrict.ro4 Nov 2026
Odom LivingCambodia2024-Q4 → 2027-Q4 (36 months)odomphnompenh.com31 Oct 2026
UC88 Wyndham Garden BKK1Cambodia2024-Q4 → 2026-Q4 (24 months)realestate.com.kh31 Oct 2026
Lacovia (redevelopment)Cayman Islands2023-Q4 → 2028 (60 months)lacovia.com31 Oct 2026
Mandarin Oriental Residences, Grand CaymanCayman Islands2021 (pre-pandemic), then Q2 2022 → 2028-Q1 (75 months)ralcompanies.com31 Oct 2026
Solea Jaco Beach (Tower 1)Costa Rica2026-Q4 → 2027-Q4 (12 months)realtyonegroup.cr31 Oct 2026
Armani Beach Residences at Palm JumeirahDubai2026-Q4 → 2027-Q4 (12 months)foundgroup.ae18 Nov 2026
Aykon City 3Dubai2022-Q3 (registered completion 20 Sep 2022 per earlier DLD data on binayah.com) → 2027-Q4 (63 months)a1properties.ae18 Nov 2026
Azizi GrandDubai2024-Q4 → 2026-Q3 (21 months)propsearch.ae18 Nov 2026
Mar CasaDubai2026-Q4 → 2027-Q4 (12 months)propertyfinder.ae18 Nov 2026
Nuba El Gouna (serviced apartments)Egypt2027 (one-year delivery claim, May 2026) → 2028 (12 months)touch-realestate.com31 Oct 2026
Ogami (Nobu)Egypt2029-Q3 → 2030-Q3 (12 months)sodic.com30 Oct 2026
Alliance CentropolisGeorgia2028 → 2029-Q4 (12 months)korter.ge31 Oct 2026
Ramada Batumi by ArchiGeorgia2026-Q2 (June 2026 on some agency listings, per batumiverified) → 2027-Q4 (18 months)archi.ge13 Nov 2026
The Landmark, Mermaid BeachGold Coast2027 → 2028 (12 months)apartments.com.au13 Nov 2026
The La Sagesse Collection ResidencesGrenada2026 → 2027 (12 months)rangedevelopmentsgroup.com31 Oct 2026
KalaeHawaii2027 → 2028 (12 months)kalaewardvillage.com13 Nov 2026
The St. Regis Residences, HoustonHouston2027-Q4 → 2029-Q1 (15 months)elliman.com31 Oct 2026
Avrupa Konutları GüneşliIstanbul2026-Q1 (2023 EIA file, 1,312-unit version) → 2027-Q3 (18 months)emlakplatform.com.tr31 Oct 2026
Ebruli BaşakşehirIstanbul2025-Q4 → 2027-Q4 (24 months)ebrulibasaksehir.com30 Oct 2026
Piyalepaşa İstanbul PremiumIstanbul2025-Q4 → 2026-Q4 (12 months)piyalepasa.com.tr31 Oct 2026
The UnitsItaly2024-Q3 → 2026-Q4 (27 months)abitarein.com31 Oct 2026
Two Senopati (Tower 1)Jakarta2026-Q1 → 2027 (21 months)twosenopati.co.id31 Oct 2026
MawatuLabuan Bajo2023-Q1 → 2026-Q4 (45 months)mawatu.co.id13 Nov 2026
Cello TowerLas Vegas2027 → 2028 (12 months)nevadarealestategroup.com31 Oct 2026
Four Seasons Private Residences Las VegasLas Vegas2026-Q1 → 2027-Q4 (21 months)resident.com31 Oct 2026
Westminster TowerLondon2026 → 2027-Q4 (12 months)londonsquare.co.uk31 Oct 2026
Hideaways Los Cabos (Trademark Collection by Wyndham)Los Cabos2026 → 2028 (24 months)pincali.com31 Oct 2026
The Residences at The St. Regis Los Cabos (Quivira)Los Cabos2022-Q4 → 2026 (48 months)srresidencesloscabos.com31 Oct 2026
The HillsMadeira2025-Q4 → 2027-Q3 (21 months)interpatium.pt31 Oct 2026
Varino 09 ('Dubai' Madeira)Madeira2028 → 2029 | 2030 (12 months)varino.pt13 Nov 2026
111 Menerung (One Eleven Menerung)Malaysia2025-Q1 → 2027-Q1 (24 months)111menerung.com31 Oct 2026
Aethera ResidencesMalaysia2029-Q1 → 2030-Q2 (15 months)aetheraresidences.com31 Oct 2026
Amiba Bukit Bintang (formerly IBN Bukit Bintang)Malaysia2022-Q4 → 2029-Q4 (84 months)amibabukitbintang.com.my31 Oct 2026
Armani Hallson KLCC (Residensi Armani Hallson KLCC)Malaysia2028-Q2 → 2030-Q2 (24 months)armanigroup.com.my31 Oct 2026
Branniganz Suites @ Bukit BintangMalaysia2027-Q3 → 2028-Q4 (15 months)branniganz.com.my31 Oct 2026
Crown PenangMalaysia2027 (2023 announcement; first SPA VP date 20 Aug 2027) → 2029-Q1 (15 months)crownpenang.com13 Nov 2026
Divine KLCCMalaysia2029-Q3 → 2032-Q4 (39 months)malaysiaproperty4u.com31 Oct 2026
KL360 @ Menara GDMalaysia2029-Q2 (26 Jun 2029, 36 months from first SPA) → 2030-Q4 (18 months)register.kl360.my30 Oct 2026
One Seputeh ResidencesMalaysia2029-Q1 (26 Mar 2029 per first SPA) → 2030-Q3 (18 months)asiabina.com30 Oct 2026
Pavilion Damansara Heights Phase 2 (Royal Suites and Imperial Residences)Malaysia2029-Q2 → 2030-Q2 (12 months)theedgemalaysia.com31 Oct 2026
Pavilion Square Kuala Lumpur (Luxury Residences)Malaysia2027-Q3 → 2029-Q3 (24 months)pavilionsquarekl.com31 Oct 2026
R&F Princess Cove Phase 3, New Casa Suites (Mercu 3)Malaysia2028-Q3 → 2029-Q4 (15 months)theedgemalaysia.com13 Nov 2026
Residensi M TerraMalaysiaAugust 2027 → 2028 (16 months)mahsing.com.my13 Nov 2026
Sunway Velocity 3 (Towers A and B)Malaysia2027-Q2 → 2028-Q2 (12 months)sunwayproperty.com13 Nov 2026
The Westin Residences PenangMalaysia2028-Q2 → 2030-Q2 (24 months)edgeprop.my31 Oct 2026
The Coral Residences, KandimaMaldives2025-Q3 → 2026 (15 months)coralresidencesmaldives.com31 Oct 2026
Kingfisher, Red Bank RiversideManchester2028-Q2 → 2030-Q4 (30 months)crowncontinental.com31 Oct 2026
Pendry Residences Mexico CityMexico City2026 → 2027 (12 months)pendrymexicocityresidences.com31 Oct 2026
Bentley Residences MiamiMiami2027 → 2028 (12 months)joshsteinrealtor.com13 Nov 2026
Edition Residences MiamiMiami2028-Q2 (buyer contracts) → 2029-Q4 (18 months)therealdeal.com13 Nov 2026
ORA by Casa TuaMiami2028 → 2030-Q4 (24 months)orabycasatuavip.com13 Nov 2026
Okan TowerMiami2026 (2022 groundbreaking release) → 2028 (24 months)southfloridaagentmagazine.com13 Nov 2026
Waldorf Astoria Hotel & Residences MiamiMiami2027 → 2028 (12 months)joshsteinrealtor.com13 Nov 2026
Living Club pre-sale development, C. 52 x 69 Temozón Norte (project name not published)Mérida2025-Q2 (Palmer, per Goodlers; link to this listing not confirmed) → 2027-Q3 (27 months)pincali.com30 Oct 2026
Ozalia TemozónMérida2028-Q2 (stage 1, Sep 2025 listing) → 2029-Q4 (18 months)ozalia.mx31 Oct 2026
The KubrickNew Zealand2028-Q4 → 2029 (12 months)ockham.co.nz31 Oct 2026
Aman Residences, NisekoNiseko2023 → 2030 (84 months)aman.com31 Oct 2026
HOSHINOYA Hutte Niseko (provisional name)Niseko2026-Q4 → 2029-Q1 (27 months)hoshinoresorts.com13 Nov 2026
The Sustainable City - YitiOman2025 (stated at the March 2022 launch) → 2027-12 (The Plaza) (24 months)thesustainablecity-yiti.com31 Oct 2026
Uptown Muscat (Ivy Town phase 1)Oman2027-Q1 → 2029-Q2 (27 months)metropolitan.realestate30 Oct 2026
Guayacan Santa MariaPanama City2027 → 2028 (12 months)santamariapanama.com31 Oct 2026
Wellness & Longevity Concept tower, Costa del Este (42 floors, name not published)Panama City2022 (older agent listing) → 2027-Q2 (54 months)encuentra24.com30 Oct 2026
Once WongamatPattaya2028-01 (portal, Apr 2026) → 2029 (23 months)wongamatgroup.com31 Oct 2026
Soondri WongamatPattayaQ4 2029-2030 (agent) → 2031 (24 months)embarkestate.com31 Oct 2026
Mandtra Residences Tower 3 (Phase 2)Philippines2025 (Tower 1, per 2021 launch) → 2027-Q2 (18 months)cebulandmasters.com30 Oct 2026
AURA CondominiumPhuket2026-2027 (older listings) → 2028-Q2 (18 months)novasia.estate31 Oct 2026
Layan VerdePhuket2027 (Dusit press release, Jun 2024) → 2028-Q4 (12 months)layanre.com31 Oct 2026
Vega CondominiumPhuket2026-08 (Georid record of developer page, Aug 2026) / 2027 (Sun Hills Lakeside) → 2028-Q1 (19 months)vegacondominium.com28 Oct 2026
Ferreiros ResidencesPortugal2026-Q4 to 2027-Q1 (Diário Imobiliário, Nov 2024) → 2027 (12 months)yardproperties.pt31 Oct 2026
Spatia MelidesPortugal2024-Q4 → 2026-Q3 (21 months)eurosuez.com31 Oct 2026
City Place Luxury Condos & Shops (Phase 1)Punta Cana2025-Q4 → 2027-Q2 (18 months)axiainversiones.com13 Nov 2026
Nobu Hotel and Residences Al Marjan IslandRas Al Khaimah2026-Q4 → 2028-Q1 (15 months)rakcompare.ae31 Oct 2026
Sora Beach ResidencesRas Al Khaimah2026-Q4 (portal listings) → 2027-Q4 (12 months)directdxb.com31 Oct 2026
Bodhi TulumRiviera Maya2024-Q4 (phase 2) / 2024-Q1 (phase 1), per Aug 2023 price list → 2026 (24 months)bodhitulum.com28 Oct 2026
Tulum Country Club, Apartamento HélicesRiviera Maya2024-Q4 (phase 1, per agent) → 2026-Q4 (24 months)tulumcountryclub.com13 Nov 2026
Four Seasons Private Residences Red Sea at Shura IslandSaudi Arabia2025-Q4 (RSG, Jan 2025) → 2026 (12 months)fourseasons.com31 Oct 2026
Empathia VillageSeychelles2027 → 2030 (36 months)empathia-seychelles.com31 Oct 2026
Hayyan (current phases Samr and Deem)Sharjah2026-Q4 → 2030-Q2 (42 months)propertyfinder.ae31 Oct 2026
Fairway LatitudeSri Lanka2019-Q4 → 2028-Q1 (99 months)latitude.fairwayproperties.lk31 Oct 2026
Harbourside ResidencesSydney2026 → 2027-Q4 (12 months)harbourside.mirvac.com13 Nov 2026
Cielo CondosToronto2026 (portals) → 2027 (ConstructConnect, June 2026) (12 months)collecdevmarkee.com4 Nov 2026
Sobha Siniya Island Villas (Phase 1)Umm Al Quwain2027-12 (phase one, Khaleej Times Nov 2024) → 2028-Q4 (12 months)propertyfinder.ae31 Oct 2026
Nobu Residences DanangVietnam2026-Q1 → 2027-Q3 (18 months)savills.com.vn31 Oct 2026
Paramount Signature Nha Trang by Melia (Libera Nha Trang tower CT10)Vietnam2025-Q4 → 2026-Q4 (12 months)liberanhatrang.vn31 Oct 2026
The Residences at Mandarin Oriental Da NangVietnam2024 (resort opening per Feb 2021 announcement) → 2026-Q2 (18 months)rumavi.com31 Oct 2026
AZURE Michamvi (The House Residence Azure Zanzibar)Zanzibar2026-Q4 → 2027-Q4 (12 months)azuremichamvi.com31 Oct 2026

Register date differs from the advertised date 26

The completion date on the Dubai Land Department register and the handover date the developer advertises are more than 6 months apart.

ProjectMarketNumbersSourceRead
Azizi GrandDubaiadvertised 2026-Q3, register 2025-02-02 (-19 months)dubairealestateiq.com24 Jun 2026
Binghatti HillviewsDubaiadvertised 2026-Q4, register 2026-04-01 (-8 months)dubairealestateiq.com25 Jun 2026
Binghatti StarfallDubaiadvertised 2027-Q4, register 2028-09-30 (9 months)dubairealestateiq.com20 May 2026
Canal Crown de GRISOGONODubaiadvertised 2027-Q4, register 2027-02-28 (-10 months)dubairealestateiq.com15 Jul 2026
City Walk CrestlaneDubaiadvertised 2028-Q4, register 2029-09-30 (9 months)dubairealestateiq.com9 Nov 2026
Couture by CavalliDubaiadvertised 2027-Q2, register 2025-05-31 (-25 months)dubairealestateiq.com4 Nov 2026
DAMAC Riverside ViewsDubaiadvertised March 2029, register 2028-05-31 (-10 months)dubairealestateiq.com30 Sept 2026
Kanyon by BeyondDubaiadvertised 2029-Q2, register 2028-09-30 (-9 months)dubairealestateiq.com9 Nov 2026
Mar CasaDubaiadvertised 2027-Q4, register 2026-10-31 (-14 months)dubairealestateiq.com29 Oct 2026
Nad Al Sheba Gardens Phase 7Dubaiadvertised 2028-Q3, register 2028-02-15 (-7 months)dubairealestateiq.com12 Aug 2026
One by BinghattiDubaiadvertised 2026-Q4, register 2026-05-30 (-7 months)dubairealestateiq.com14 May 2026
SAMANA Barari ViewsDubaiadvertised 2028-Q2, register 2027-03-31 (-15 months)dubairealestateiq.com28 Oct 2026
SAMANA Ivy Gardens 2Dubaiadvertised 2028-Q4, register 2027-12-31 (-12 months)dubairealestateiq.com21 Oct 2026
SAMANA Manhattan 2Dubaiadvertised 2027-Q4, register 2026-11-01 (-13 months)dubairealestateiq.com17 Sept 2026
SAMANA Mykonos SignatureDubaiadvertised 2027-Q1, register 2026-04-30 (-11 months)dubairealestateiq.com12 Oct 2026
SAMANA Ocean PearlDubaiadvertised 2027-Q4, register 2026-12-31 (-12 months)dubairealestateiq.com17 Sept 2026
SAMANA Ocean Pearl 2Dubaiadvertised 2027-Q4, register 2027-03-31 (-9 months)dubairealestateiq.com17 Sept 2026
SAMANA Park MeadowsDubaiadvertised 2028-Q1, register 2027-08-31 (-7 months)dubairealestateiq.com1 Oct 2026
SAMANA SkyrosDubaiadvertised 2027-Q2, register 2026-04-30 (-14 months)dubairealestateiq.com29 Sept 2026
SAMANA WavesDubaiadvertised 2027-Q1, register 2026-04-15 (-11 months)dubairealestateiq.com16 Oct 2026
SAMANA Waves 2Dubaiadvertised 2027-Q3, register 2026-03-20 (-18 months)dubairealestateiq.com2 Oct 2026
Skyscape (Sobha Hartland II)Dubaiadvertised 2028-Q4, register 2029-12-31 (12 months)dubairealestateiq.com21 Sept 2026
The Brooks at Sobha SanctuaryDubaiadvertised 2029-Q3, register 2030-08-31 (11 months)dubairealestateiq.com15 Jul 2026
The HighgroveDubaiadvertised 2027-Q4, register 2028-12-31 (12 months)dubairealestateiq.com6 Aug 2026
The Meriva Collection (Meriva Gardens / Meriva Signature)Dubaiadvertised 2030-Q2, register 2031-12-31 (18 months)dubairealestateiq.com15 Oct 2026
Valencia (DAMAC Lagoons District)Dubaiadvertised 2029-Q3, register 2028-02-28 (-19 months)dubairealestateiq.com20 May 2026

Register progress does not fit the stage 1

The register reports 95% built or more while our stage says off-plan, or 0% built while our stage says under construction and the register start date is 12 months or more ago.

ProjectMarketNumbersSourceRead
Vision Iconic (Mercedes-Benz Places, Binghatti City)Dubai0% built at inspection of 2026-07-28, register start 2023-12-15, stage on record: under constructiondubairealestateiq.com28 Jul 2026

Sizes or prices that do not add up 2

Smallest size above the largest, smallest unit under 12 m2, largest unit more than 40 times the smallest, or lowest price above the highest.

ProjectMarketNumbersSourceRead
BayviewDubaismallest unit 3 m2dubairealestateiq.com18 Nov 2026
The MuralDubaismallest unit 4 m2dubairealestateiq.com18 Nov 2026

No units on an active register entry 0

An active Dubai register entry with zero units.

Nothing flagged by this rule today.

Method

Computed from the published dataset each time it is rebuilt, with fixed thresholds written above; no model and no manual selection. Outliers depend on the comparison group: a market with few projects or one luxury tower can make normal projects look unusual.

Rules that need data we do not hold (for example built area per unit) are not run.

Input: /data/named.json published 19 Nov 2026 (SHA-256 5b0bfe5efa566cf5…).