Nov 1DATAAll 646 projects re-verified: 6,419 developer claims tested against registers, courts and pressNov 1DATAMalaysia TEDUH and Philippines DHSUD licence checks: expired licences and approved delays foundNov 1DATAThailand ONEP register: 2 condos found selling before environmental approvalNov 1DATAMexico PROFECO contract register checks: one sales registration belonged to a laundryNov 1DATAAbu Dhabi ADREC inspections and RAK RERA permit list added: % built straight from the regulatorNov 1SHIPPEDNew stage filter: completed but still sellingNov 1SHIPPEDPublic database page: verification levels, disclosure distribution, every marketNov 1DATA+212 projects in one day, round 3: USA, Caribbean, Gulf, Africa, Japan, AustraliaNov 1SHIPPEDStage on every case: off-plan or under constructionOct 31SHIPPEDVerification level per check on every case card: registry, independent, developer, contradicted
Changelog →

Kolaboro / Countries / USA

Off-plan projects in USA

Facts from 36 tracked projects: what developers publish, what registers confirm, and how late handovers are.

In USA, Kolaboro has reviewed 36 off-plan projects in 12 markets (3 more added, not yet reviewed) (13 off-plan, 23 under construction). On average 3.0 of 6 buyer checks are public and 1.9 are confirmed by an official register or independent source.

3 projects are past the first handover date we have on record; 1 is past the date currently advertised. Data of 5 November 2026.

36projects tracked
12markets
56%publish a permit or licence number
11%state deposit protection
3past the first handover date on record
51developer claims contradicted by another source

Markets in USA#

Off-plan projects tracked in USA#

Sorted by the number of buyer checks the developer makes public. Facts as advertised, checked against registers where we could; "not published" means we found no public source.

ProjectWhereStageHandover year advertisedChecks publicConfirmed by register or independent sourcePast first handover date on record
Andare Residences by Pininfarina FLL-001Fort Lauderdaleunder construction20275/63/6not past
The Launiu Ward Village HNL-001Hawaiiunder construction20275/63/6not past
Millenia Park ORL-002Orlandounder constructionnot published5/63/6no date
ONE Tampa TPA-001Tampaunder construction20275/63/6not past
Kalae HNL-002Hawaiiunder construction20284/64/6not past
Edition Residences Miami MIA-001Miamioff-plan20294/63/6not past
ORA by Casa Tua MIA-004Miamioff-plan20304/62/6not past
Mercedes-Benz Places Miami MIA-006Miamiunder construction20274/62/6not past
Bentley Residences Miami MIA-008Miamiunder construction20284/63/6not past
The Windsor NYC-002New Yorkunder construction20264/62/6not past
Viceroy Residences Austin AUS-001Austinunder construction20273/63/6not past
One Lady Bird Lake AUS-002Austinunder construction20283/62/6not past
Four Seasons Private Residences Las Vegas LAS-001Las Vegasunder construction20273/61/68 months
Okan Tower MIA-002Miamiunder construction20273/62/611 months
Cipriani Residences Miami MIA-003Miamiunder construction20273/62/6not past
Waldorf Astoria Hotel & Residences Miami MIA-005Miamiunder construction20283/63/6not past
888 Brickell by Dolce&Gabbana MIA-010Miamioff-plan20293/62/6not past
Baccarat Residences Miami MIA-011Miamiunder construction20283/62/6not past
The St. Regis Residences, Miami (1809 Brickell) MIA-013Miamiunder construction20273/61/6not past
3300 Gulf Shore NAP-001Naplesunder construction20273/62/6not past
175 East 82nd Street NYC-001New Yorkunder construction20273/62/6not past
Enchanted Garden Resort, Phase 2 ORL-003Orlandooff-plannot published3/61/6no date
Mandarin Oriental Residences Boca Raton PAL-001Palm Beach Countyunder construction20253/61/6119 months
Pendry Residences Nashville BNA-001Nashvilleunder construction20272/61/6not past
The Residences at The Nashville EDITION BNA-002Nashvilleoff-plan20282/61/6not past
Sereno Fort Lauderdale FLL-002Fort Lauderdaleoff-plannot published2/61/6no date
Gaia Residences FLL-003Fort Lauderdaleoff-plannot published2/61/6no date
The St. Regis Residences, Houston HOU-001Houstonoff-plan20292/60/6not past
Cello Tower LAS-002Las Vegasunder construction20282/61/6not past
Colette Residences MIA-007Miamioff-plan20282/62/6not past
Avenia Aventura, Interiors by FENDI Casa MIA-009Miamioff-plan20272/62/6not past
The Residences at 1428 Brickell MIA-012Miamiunder construction20282/61/6not past
Beekman (401 East 51st Street) NYC-003New Yorkunder construction20272/62/6not past
Ambar Residences Orlando (Apartments by Marriott Bonvoy) ORL-001Orlandooff-plan20282/60/6not past
Luna at Marina Pointe (Tower Two) TPA-003Tampaoff-plan20282/61/6not past
Hotel ORA + Private Residences TPA-002Tampaoff-plan20291/62/6not past

Added, not yet reviewed#

3 projects were added to tracking and have not been read by our research agent yet. We show no score or check results for them until we have.

ProjectWhereStatus
Rivage Bal HarbourMiamiNot yet reviewed by Kolaboro
Casa Bella Residences by B&B ItaliaMiamiNot yet reviewed by Kolaboro
ELLE Residences MiamiMiamiNot yet reviewed by Kolaboro

Furthest past the first handover date#

  1. Mandarin Oriental Residences Boca Raton (Palm Beach County): first handover on record December 2016, 119 months ago; date moved 108 months in total
  2. Okan Tower (Miami): first handover on record December 2025, 11 months ago; date moved 24 months in total
  3. Four Seasons Private Residences Las Vegas (Las Vegas): first handover on record March 2026, 8 months ago; date moved 21 months in total

Source: /data/on-time.json (as of 2026-11). All markets

Delivery-delay index#

MarketTrackedWith a datePast first dateShare past first dateMedian months late
Miami161317.7%too few
New York330null%too few
Tampa330null%too few
Austin220null%too few
Hawaii220null%too few
Las Vegas221null%too few
Nashville220null%too few
Fort Lauderdale310null%too few
Houston110null%too few
Naples110null%too few
Orlando310null%too few
Palm Beach County111null%too few

Source: delivery-delay index, /data/delay-index.json.

Dated promises: kept, broken, moved#

MarketPromisesKeptBrokenMovedPending
Miami2010711
Tampa50122
Nashville41003
Hawaii30011
New York30003
Las Vegas31020
Orlando20002
Austin20002
Fort Lauderdale20002
Palm Beach County10100
Houston10010
Naples10001

Each promise is an exact quote from the developer page or research record: promise tracker, /data/promises.json.

Official registers for USA#

County and city permit portals (United States)

What it proves
Building permits, inspections and certificates of occupancy for the address.
What it does not prove
Ownership or the developer’s finances.
How to search
Find the building department of the city or county and search by address or parcel number. There is no single national site.

No public online search; ask the authority directly.

From our register guide.

Florida DBPR condominium filings (United States)

What it proves
Condominium projects filed with the Division of Florida Condominiums, Timeshares and Mobile Homes, with status. Florida law (Chapter 718) requires buyer deposits on new condos to be held in escrow.
What it does not prove
That the escrow agent named in your contract holds your money: confirm with the agent directly.
How to search
Download the condominium files for the county from DBPR public records and search for the project name.

Open the official register (opens in a new tab) www2.myfloridalicense.com

From our register guide.

County recorder and Secretary of State (United States)

What it proves
Recorded deeds and mortgages (county recorder or clerk), and that the developer company exists and is active (Secretary of State; in Florida, Sunbiz).
What it does not prove
Permits or progress.
How to search
Search the county official records by owner or parcel, and the state business register by company name.

No public online search; ask the authority directly.

From our register guide.

Questions and answers#

How many off-plan projects does Kolaboro track in USA?

36 projects in 12 markets (Miami, Fort Lauderdale, New York, Orlando, Tampa), data of 5 November 2026.

How many off-plan projects in USA publish a permit or licence number?

20 of 36 (56%). 23 are confirmed in an official register or by an independent source.

How many off-plan projects in USA state deposit protection such as escrow?

4 of 36 (11%).

Are off-plan projects in USA delivered late?

3 of 36 tracked projects are past the first handover date on record, the furthest by 119 months. 1 are past the date they currently advertise.

Which official registers can I use to check a project in USA?

County and city permit portals; Florida DBPR condominium filings; County recorder and Secretary of State.

Are you the developer, or did we get something wrong? Send documents and we add your reply or correct the record: right of reply · corrections. Every figure here is computed from the open dataset (/data/bali-cases.json, CC BY 4.0) and changes when the data changes.