Nov 1DATAAll 646 projects re-verified: 6,419 developer claims tested against registers, courts and pressNov 1DATAMalaysia TEDUH and Philippines DHSUD licence checks: expired licences and approved delays foundNov 1DATAThailand ONEP register: 2 condos found selling before environmental approvalNov 1DATAMexico PROFECO contract register checks: one sales registration belonged to a laundryNov 1DATAAbu Dhabi ADREC inspections and RAK RERA permit list added: % built straight from the regulatorNov 1SHIPPEDNew stage filter: completed but still sellingNov 1SHIPPEDPublic database page: verification levels, disclosure distribution, every marketNov 1DATA+212 projects in one day, round 3: USA, Caribbean, Gulf, Africa, Japan, AustraliaNov 1SHIPPEDStage on every case: off-plan or under constructionOct 31SHIPPEDVerification level per check on every case card: registry, independent, developer, contradicted
Changelog →

Kolaboro / Tools / Late handover

The keys are late. What does the contract say, and what does the law say?

Two answers side by side. First, what the delay clause in your contract pays, from the figures you type. Second, what the law where the property is gives you, quoted article by article from the official text, with the amounts worked out where the law sets a formula.

Where and how much

Dates

Payments made

Needed for the law side: Spanish legal interest runs from each payment date, and a Portuguese deposit doubles. Example payments are filled in.

The delay clause in your contract

What the contract pays for delay

What the contract clause pays

0

Months are calendar months; a part month counts by its days (30.44 days a month). Every figure here comes from the numbers you typed.

The law

What the law says

Before you accept a new date

What to do, in order

  1. Find the clause and the date.Read the exact delay clause, the grace period, force majeure wording and how notices must be sent. The promised date is the one in the contract, not in the brochure.
  2. Ask for the reason and the new date in writing.Keep every message. A new date you agree to in writing can replace the old one and restart the grace period.
  3. Do not sign an extension before advice.In Spain the law treats an extension as your choice instead of cancelling. Elsewhere, an addendum can waive the penalty.
  4. Check where your money is.Escrow, a bank guarantee or insurance decides whether a refund is real. See the deposit protection finder.
  5. Get a local lawyer to read the contract.Bring this page, the contract and your payment receipts.