In Malaysia, Kolaboro has reviewed 22 off-plan projects in 2 markets (8 off-plan, 14 under construction). On average 4.2 of 6 buyer checks are public and 2.6 are confirmed by an official register or independent source.
1 project is past the first handover date we have on record; 0 are past the date currently advertised. Data of 5 November 2026.
Markets in Malaysia#
Off-plan projects tracked in Malaysia#
Sorted by the number of buyer checks the developer makes public. Facts as advertised, checked against registers where we could; "not published" means we found no public source.
| Project | Where | Stage | Handover year advertised | Checks public | Confirmed by register or independent source | Past first handover date on record |
|---|---|---|---|---|---|---|
| Sunway Velocity 3 (Towers A and B) MYS-013 | Malaysia | under construction | 2028 | 6/6 | 4/6 | not past |
| Branniganz Suites @ Bukit Bintang MYS-014 | Malaysia | under construction | 2028 | 6/6 | 3/6 | not past |
| The Westin Residences Penang MYS-016 | Malaysia | under construction | 2028 | 6/6 | 4/6 | not past |
| Pavilion Damansara Heights Phase 2 (Royal Suites and Imperial Residences) MYS-017 | Malaysia | under construction | 2030 | 6/6 | 4/6 | not past |
| R&F Princess Cove Phase 3, New Casa Suites (Mercu 3) MYS-018 | Malaysia | under construction | 2029 | 6/6 | 4/6 | not past |
| Armani Hallson KLCC (Residensi Armani Hallson KLCC) MYS-019 | Malaysia | under construction | 2030 | 6/6 | 4/6 | not past |
| One Seputeh Residences MYS-002 | Malaysia | off-plan | 2030 | 5/6 | 3/6 | not past |
| KL360 @ Menara GD MYS-003 | Malaysia | off-plan | 2030 | 5/6 | 3/6 | not past |
| Crown Penang MYS-004 | Malaysia | under construction | 2028 | 5/6 | 4/6 | not past |
| Amiba Bukit Bintang (formerly IBN Bukit Bintang) MYS-015 | Malaysia | off-plan | 2029 | 5/6 | 4/6 | not past |
| The Ashwood KUA-001 | Kuala Lumpur | under construction | 2028 | 4/6 | 0/6 | not past |
| Pavilion Damansara Heights Phase 2 (Imperial Residences and Royal Suites) KUA-003 | Kuala Lumpur | off-plan | 2030 | 4/6 | 0/6 | not past |
| Pavilion Square Kuala Lumpur (Luxury Residences) MYS-009 | Malaysia | under construction | 2029 | 4/6 | 4/6 | not past |
| 111 Menerung (One Eleven Menerung) MYS-010 | Malaysia | under construction | 2027 | 4/6 | 4/6 | 11 months |
| Aethera Residences MYS-012 | Malaysia | off-plan | 2030 | 4/6 | 4/6 | not past |
| Papyrus North Kiara KUA-002 | Kuala Lumpur | under construction | 2028 | 3/6 | 0/6 | not past |
| AVÉA @ Andaman Island MYS-005 | Malaysia | off-plan | 2030 | 3/6 | 0/6 | not past |
| CloutHaus Residences MYS-007 | Malaysia | under construction | 2029 | 3/6 | 1/6 | not past |
| Skypark Kepler @ Lido Waterfront MYS-008 | Malaysia | under construction | 2029 | 3/6 | 2/6 | not past |
| Forest City MYS-001 | Malaysia | under construction | not published | 2/6 | 2/6 | no date |
| Divine KLCC MYS-011 | Malaysia | off-plan | 2032 | 2/6 | 3/6 | not past |
| Lumina Residence MYS-006 | Malaysia | off-plan | 2028 | 1/6 | 0/6 | not past |
Furthest past the first handover date#
- 111 Menerung (One Eleven Menerung) (Malaysia): first handover on record December 2025, 11 months ago; date moved 24 months in total
Source: /data/on-time.json (as of 2026-11). All markets
Delivery-delay index#
| Market | Tracked | With a date | Past first date | Share past first date | Median months late |
|---|---|---|---|---|---|
| Malaysia | 19 | 18 | 1 | 5.6% | too few |
| Kuala Lumpur | 3 | 3 | 0 | null% | too few |
Source: delivery-delay index, /data/delay-index.json.
Dated promises: kept, broken, moved#
| Market | Promises | Kept | Broken | Moved | Pending |
|---|---|---|---|---|---|
| Malaysia | 20 | 0 | 0 | 14 | 6 |
| Kuala Lumpur | 3 | 0 | 0 | 0 | 3 |
Each promise is an exact quote from the developer page or research record: promise tracker, /data/promises.json.
Official registers for Malaysia#
KPKT TEDUH (Malaysia)
- What it proves
- The developer’s licence, the project’s Advertising Permit and Developer’s Licence (APDL) and its status, reported progress, whether an extension of time was granted, and whether the project is listed as sick or abandoned.
- What it does not prove
- Build quality, or land title.
- How to search
- Search TEDUH by project or developer name and check the APDL is valid for the phase you are buying.
Open the official register (opens in a new tab) teduh.kpkt.gov.my
From our register guide.
Housing Development Account (HDA) (Malaysia)
- What it proves
- Under the Housing Development Act (Act 118) a licensed developer must pay buyers’ money into a Housing Development Account for the project, and withdrawals are restricted.
- What it does not prove
- There is no public search for the account: it does not show the balance or that your payment went in.
- How to search
- Check that your sale and purchase agreement names the HDA, and pay only into that account, never to a person or sales agent.
No public online search; ask the authority directly.
From our register guide.
Questions and answers#
How many off-plan projects does Kolaboro track in Malaysia?
22 projects in 2 markets (Malaysia, Kuala Lumpur), data of 5 November 2026.
How many off-plan projects in Malaysia publish a permit or licence number?
16 of 22 (73%). 14 are confirmed in an official register or by an independent source.
How many off-plan projects in Malaysia state deposit protection such as escrow?
8 of 22 (36%).
Are off-plan projects in Malaysia delivered late?
1 of 22 tracked projects are past the first handover date on record, the furthest by 11 months. 0 are past the date they currently advertise.
Which official registers can I use to check a project in Malaysia?
KPKT TEDUH; Housing Development Account (HDA).
Related#
Are you the developer, or did we get something wrong? Send documents and we add your reply or correct the record: right of reply · corrections. Every figure here is computed from the open dataset (/data/bali-cases.json, CC BY 4.0) and changes when the data changes.