Construction pace against the registered date

For Dubai projects with DLD inspection readings: % built against the share of time elapsed to the completion date on the register, and the completion range the observed pace points to. A projection, not a promise.

Updated 23 Nov 2026

A projection from the pace on the register, not a promise, and not a finding about the developer.

860projects compared (DLD % built and dates on the register)
82.7%more than 10 points behind the time elapsed (95% interval 80 to 85.1%)
-27median gap in points, % built minus % of time elapsed (95% interval -29.1 to -26)
452projects with a projected range (10% to 99% built)
86.7%of them projected after the registered date (95% interval 83.3 to 89.5%)
≤-6098-50119-40168-30186-20140-10940291013209303401
Projects by gap between % built and % of time elapsed, in 10-point bins
Show as a table
Gap (points)Projects
-60 … -5098
-50 … -40119
-40 … -30168
-30 … -20186
-20 … -10140
-10 … 094
0 … 1029
10 … 2013
20 … 309
30 … 403
40 … 501

Projects

985 projects, page 15
Project% built (inspection)Time elapsedGap (points)PaceRegistered completionProjected rangeRegister
Creek Waters 2
Emaar Properties · Dubai Creek Harbour
81.8%
31 Jul 2026
68%14.4on pace or ahead31 Dec 2027Mar 2027 – Apr 2027dubairealestateiq.com
Azizi Riviera 68
Azizi Developments · Al Merkadh
74.6%
7 Aug 2026
60%14.7on pace or ahead30 May 2027Dec 2026 – Jan 2027dubairealestateiq.com
Greenville
Emaar Properties · Madinat Al Mataar
46%
14 May 2026
31%15.2on pace or ahead31 Mar 2029Nov 2027 – Apr 2028dubairealestateiq.com
Parkside Hills
Emaar Properties · Dubai Hills Estate
68.3%
7 May 2026
53%15.6on pace or ahead30 Jun 2028Jun 2027 – Aug 2027dubairealestateiq.com
Kingdom Gate
Kingdom Gate · Jabal Ali First
55.5%
18 Jun 2026
38%17.4on pace or ahead31 Mar 2027Nov 2026dubairealestateiq.com
11 Hills Park
Townx · Dubai Science Park
80.1%
30 Apr 2026
62%18.4on pace or ahead31 Mar 2027Sept 2026dubairealestateiq.com
Azizi Riviera 64
Azizi Developments · Al Merkadh
83.8%
7 Sept 2026
64%19.8on pace or ahead30 May 2027Nov 2026 – Dec 2026dubairealestateiq.com
Sartoria
Pinnacle A K S · Dubai Sports City
51.2%
15 Oct 2026
30%20.9on pace or ahead9 Oct 2027Mar 2027dubairealestateiq.com
Azizi Riviera 60
Azizi Developments · Al Merkadh
97.1%
15 Sept 2026
76%21.6on pace or ahead13 Mar 2027Sept 2026 – Oct 2026dubairealestateiq.com
Ahs Tower
DAMAC Properties · Trade Center Second
67.4%
19 May 2026
46%21.8on pace or ahead31 Jan 2027Jul 2026 – Aug 2026dubairealestateiq.com
Azizi Riviera 62
Azizi Developments · Al Merkadh
90.8%
30 Jul 2026
69%21.8on pace or ahead13 Mar 2027Aug 2026 – Sept 2026dubairealestateiq.com
Aryam Tower by Abu Alnaga
Abualnaga · Jabal Ali First
33.2%
29 Sept 2026
11%21.8on pace or ahead30 Jun 2028Mar 2027dubairealestateiq.com
Golf Hillside
Emaar Properties · Hadaeq Sheikh Mohammed Bin Rashid
65.8%
11 Aug 2026
43%22.6on pace or ahead31 Dec 2028Jul 2027 – Aug 2027dubairealestateiq.com
Ashley Hills
Townx · Arjan
74.1%
10 Jun 2026
48%26.5on pace or ahead31 Mar 2027Sept 2026dubairealestateiq.com
Club Place
Emaar Properties · Dubai Hills Estate
68.8%
16 Jun 2026
41%27.9on pace or ahead31 Dec 2028Apr 2027 – Apr 2027dubairealestateiq.com
The Oasis - Palmiera 3
Emaar Properties · Me'Aisem Second
72.6%
9 Jun 2026
43%29.8on pace or ahead31 Oct 2028Feb 2027 – Feb 2027dubairealestateiq.com
Azizi Riviera 66
Azizi Developments · Al Merkadh
91%
7 Aug 2026
61%30on pace or ahead30 May 2027Sept 2026 – Sept 2026dubairealestateiq.com
Paradise One
Danat Aldunia · Jumeirah Village Triangle
69.7%
23 Apr 2026
35%35on pace or ahead15 Apr 2027Jul 2026dubairealestateiq.com
Oasis Tower 2
P A L · Dubai Sports City
73.9%
8 Sept 2026
34%39.7on pace or ahead30 Jun 2027Nov 2026dubairealestateiq.com
Altus
Emaar Properties · Al Khairan First
86.5%
10 Nov 2026
47%40on pace or ahead31 Jan 2029Feb 2027 – Mar 2027dubairealestateiq.com
Azizi Venice 14
Azizi Developments · Azizi Venice, Dubai South (DWC)
30.3%
22 Jun 2026
100%-registered date passed30 May 2026Nov 2030 – May 2031dubairealestateiq.com
Viewz 2 by Danube
Danube Properties Development L.L.C · Jumeirah Lake Towers (Al Thanyah Fifth)
65%
20 Oct 2026
100%-registered date passed30 Jun 2026Jul 2028 – Sept 2028dubairealestateiq.com
Expo Valley (villas and townhouses)
Expo City Dubai · Expo City Dubai (Madinat Al Mataar)
66%
19 Aug 2026
100%-registered date passed31 Jan 2026May 2028 – May 2028dubairealestateiq.com
Azizi Grand
Azizi Developments L.L.C · Dubai Sports City
82.1%
24 Jun 2026
100%-registered date passed2 Feb 2025Apr 2028 – Apr 2028dubairealestateiq.com
Burj Binghatti Jacob & Co Residences
Binghatti Developers · Business Bay
52.1%
31 Aug 2026
100%-registered date passed30 Jun 2026Mar 2030 – Apr 2030dubairealestateiq.com
Binghatti Hillviews
Binghatti Developers · Dubai Science Park
32.6%
25 Jun 2026
100%-registered date passed1 Apr 2026Nov 2029 – Jan 2030dubairealestateiq.com
Couture by Cavalli
DAMAC Properties · Dubai Canal, Safa Park
27.6%
4 Nov 2026
100%-registered date passed31 May 2025Apr 2036 – Jul 2037dubairealestateiq.com
Cove Edition 2 by Imtiaz
Imtiaz Developments · Dubailand (DLRC)
60.1%
20 Oct 2026
100%-registered date passed15 Oct 2026Feb 2028dubairealestateiq.com
Cove Edition by Imtiaz
Imtiaz Developments · Dubailand (DLRC)
90.2%
12 Oct 2026
100%-registered date passed25 Aug 2026Jan 2027dubairealestateiq.com
SAMANA Mykonos Signature
SAMANA Developers · Arjan
86%
12 Oct 2026
100%-registered date passed30 Apr 2026Apr 2027dubairealestateiq.com
SAMANA Skyros
SAMANA Developers · Arjan
71.3%
29 Sept 2026
100%-registered date passed30 Apr 2026Jan 2028dubairealestateiq.com
SAMANA Waves
SAMANA Developers · Jumeirah Village Circle (JVC)
90.6%
16 Oct 2026
100%-registered date passed15 Apr 2026Apr 2027dubairealestateiq.com
SAMANA Waves 2
SAMANA Developers · Jumeirah Village Circle (JVC)
52.1%
2 Oct 2026
100%-registered date passed20 Mar 2026Dec 2029dubairealestateiq.com
Eltiera Views
Ellington Properties · Jumeirah Islands
0%
5 Dec 2025
--not comparable31 Dec 2029under 10% built: too early to projectdubairealestateiq.com
The Brooks at Sobha Sanctuary
Sobha Realty · The Valley
0%
15 Jul 2026
--not comparable31 Aug 2030under 10% built: too early to projectdubairealestateiq.com
Golf Vale
Emaar Properties · Emaar South / Expo City
0%
24 Feb 2026
--not comparable31 Mar 2030under 10% built: too early to projectdubairealestateiq.com
Bayz 101 by Danube
Danube Properties · Business Bay
10%
12 Aug 2026
--not comparable-no projectiondubairealestateiq.com
Club Drive
Emaar Properties · Dubai Hills Estate
100%
19 Oct 2026
--not comparable-no projectiondubairealestateiq.com
Kensington Gardens (Greenwood)
LEOS Developments · Greenwood, International City Phase 2 (Al Warsan 4)
0%
17 Feb 2025
--not comparable27 Sept 2027under 10% built: too early to projectdubairealestateiq.com
Artistry One Residences
Select Group · Dubai Design District (d3)
0%
14 Jan 2026
--not comparable9 Feb 2029under 10% built: too early to projectdubairealestateiq.com
Nine Collective
Wasl · Wasl 1, Al Kifaf (Zabeel Park)
-
-
--not comparable-no projectiondubairealestateiq.com
Karl Lagerfeld Villas by Taraf
Taraf Development L.L.C · Majan / Wadi Al Safa 3 (marketed as Meydan, Nad Al Sheba)
10.5%
23 Sept 2026
--not comparable-no projectiondubairealestateiq.com
Arancia Yards by Beyond
Beyond Developments · The Yards, City of Arabia (Wadi Al Safa 4, Dubailand)
0%
18 May 2026
--not comparable30 Oct 2028under 10% built: too early to projectdubairealestateiq.com
Cello Residences
Taraf · Jumeirah Village Circle (JVC)
39%
4 Sept 2026
--not comparable-no projectiondubairealestateiq.com
Lagoon Views (DAMAC Lagoons)
DAMAC Properties · DAMAC Lagoons
63.9%
3 Nov 2026
--not comparable-no projectiondubairealestateiq.com
Six Senses Residences Dubai Marina
Select Group · Dubai Marina
26.7%
25 Sept 2026
--not comparable-no projectiondubairealestateiq.com
Binghatti Wraith
Binghatti Developers · Al Jaddaf
0%
20 May 2026
--not comparable30 Dec 2027under 10% built: too early to projectdubairealestateiq.com
Binghatti Starfall
Binghatti Developers · Al Jaddaf
0%
20 May 2026
--not comparable30 Sept 2028under 10% built: too early to projectdubairealestateiq.com
Route 66
Deerfields · Saih Shuaib 1
0%
4 Nov 2025
--not comparable12 Dec 2027under 10% built: too early to projectdubairealestateiq.com
La Crystal
Al Madar Properties · Palm Deira
0%
1 Oct 2025
--not comparable30 Sept 2028under 10% built: too early to projectdubairealestateiq.com
Portside Square
Ellington Properties · Mina Rashid
0%
12 Jan 2026
--not comparable31 Dec 2029under 10% built: too early to projectdubairealestateiq.com
Raw District
Imtiaz Developments · Downtown Jebel Ali, Sheikh Zayed Road
0%
9 Jun 2026
--not comparable15 Dec 2029under 10% built: too early to projectdubairealestateiq.com
Oceanz by Danube
Danube Properties · Dubai Maritime City
50%
25 Aug 2026
--not comparable-no projectiondubairealestateiq.com
Fashionz by Danube
Danube Properties · Jumeirah Village Triangle
40%
10 Sept 2026
--not comparable-no projectiondubairealestateiq.com
Diamondz by Danube
Danube Properties · Jumeirah Lake Towers
18.5%
27 Oct 2026
--not comparable-no projectiondubairealestateiq.com
Samana Portside
Samana Developers · Downtown Jebel Ali
0%
7 Jul 2026
--not comparable30 Jun 2029under 10% built: too early to projectdubairealestateiq.com
SAMANA Lake Views 2
SAMANA Developers · Dubai Production City
12%
28 Oct 2026
--not comparable-no projectiondubairealestateiq.com
Beach Walk III by Imtiaz
Imtiaz Developments · Dubai Islands
100%
4 Nov 2026
--not comparable14 Jun 2026no projectiondubairealestateiq.com
Binghatti Spectre
Binghatti Developers · Al Jaddaf, near DEWA headquarters
0%
9 Feb 2026
--not comparable31 Dec 2028under 10% built: too early to projectdubairealestateiq.com
ELO (DAMAC Hills 2)
DAMAC Properties · DAMAC Hills 2
31.5%
30 Oct 2026
--not comparable-no projectiondubairealestateiq.com

Next page

Method

Time elapsed = (inspection date minus construction start on the register) divided by (registered completion date minus construction start). When no start date is printed, the registration date is used.

Gap = % built at the inspection minus % of time elapsed at the same date, in percentage points. Behind = a gap below -10 points. Registered date passed = the inspection is after the completion date on the register and the project is not at 100%.

Projection, only for 10% to 99% built: the remaining % divided by the observed pace, where the pace is % built per day since the start date, since the registration date and between the last two inspections we hold (when it rose). The range runs from the earliest to the latest of these estimates.

Limits: Construction does not move in a straight line (a slow start, faster structure, slow finishing), so a straight line from an early reading tends to give later dates than the work will need, and a late reading can give earlier ones. The % built is the DLD inspection figure, not ours.

Source: the Dubai Land Department project register as mirrored per project with its inspection history, read by our register job; 985 DLD records, 28 with two or more dated inspections.

Files: /data/n35a/pace.json · /open/n35a-build.py · /registers/changes/