Construction pace against the registered date
For Dubai projects with DLD inspection readings: % built against the share of time elapsed to the completion date on the register, and the completion range the observed pace points to. A projection, not a promise.
Updated 23 Nov 2026
A projection from the pace on the register, not a promise, and not a finding about the developer.
Show as a table
| Gap (points) | Projects |
|---|---|
| -60 … -50 | 90 |
| -50 … -40 | 115 |
| -40 … -30 | 162 |
| -30 … -20 | 178 |
| -20 … -10 | 130 |
| -10 … 0 | 90 |
| 0 … 10 | 29 |
| 10 … 20 | 12 |
| 20 … 30 | 7 |
| 30 … 40 | 1 |
| 40 … 50 | 1 |
Projects
Developer: imtiaz-developments · All
| Project | % built (inspection) | Time elapsed | Gap (points) | Pace | Registered completion | Projected range | Register |
|---|---|---|---|---|---|---|---|
| Cotier House 2 by Imtiaz Imtiaz Developments · Dubai Islands | 20.2% 23 Oct 2026 | 76% | -56 | behind | 15 Apr 2027 | Sept 2032 – Oct 2032 | dubairealestateiq.com |
| Cove Edition 4 by Imtiaz Imtiaz Developments · Dubailand (DLRC) | 40% 6 Nov 2026 | 90% | -49.5 | behind | 21 Jan 2027 | Jul 2029 | dubairealestateiq.com |
| Cove Edition III by Imtiaz Imtiaz Developments · Dubailand (DLRC) | 44% 26 Oct 2026 | 92% | -47.5 | behind | 25 Dec 2026 | Jan 2029 | dubairealestateiq.com |
| Cove Grand by Imtiaz Imtiaz Developments · Dubailand Residence Complex | 13.4% 8 Oct 2026 | 53% | -40 | behind | 15 Dec 2027 | May 2031 – Jul 2035 | dubairealestateiq.com |
| Cotier House by Imtiaz Imtiaz Developments · Dubai Islands Marina | 51.7% 10 Nov 2026 | 91% | -38.9 | behind | 15 Jan 2027 | Jun 2028 | dubairealestateiq.com |
| Cove Edition 5 by Imtiaz Imtiaz Developments · Dubailand (Dubai Land Residence Complex) | 26.3% 18 Aug 2026 | 62% | -36 | behind | 20 May 2027 | Feb 2030 – Feb 2030 | dubairealestateiq.com |
| Cove Edition 6 Imtiaz Developments · Dubailand Residence Complex | 25.9% 13 Oct 2026 | 60% | -33.8 | behind | 10 Sept 2027 | Jun 2030 – Aug 2030 | dubairealestateiq.com |
| Cove Living Residence by Imtiaz Imtiaz Developments · Dubai Land Residence Complex | 47.2% 11 Aug 2026 | 77% | -30.2 | behind | 15 Apr 2027 | Feb 2029 – Mar 2029 | dubairealestateiq.com |
| Wynwood by Imtiaz Imtiaz Developments · Dubai Islands | 26.3% 6 Oct 2026 | 56% | -30 | behind | 30 Sept 2027 | Apr 2030 | dubairealestateiq.com |
| Cove Boulevard by Imtiaz Imtiaz Developments · Dubailand (Dubai Land Residence Complex) | 10.5% 30 Sept 2026 | 39% | -28.9 | behind | 30 Oct 2028 | Mar 2038 – Apr 2038 | dubairealestateiq.com |
| Beach Walk Grand by Imtiaz Imtiaz Developments · Dubai Islands | 68% 9 Nov 2026 | 94% | -25.7 | behind | 25 Dec 2026 | Sept 2027 – Sept 2027 | dubairealestateiq.com |
| Beach Walk Grand 2 by Imtiaz Imtiaz Developments · Dubai Islands | 23.5% 14 Sept 2026 | 49% | -25.5 | behind | 15 Dec 2027 | Jul 2030 – Aug 2030 | dubairealestateiq.com |
| Beach Walk Residences 4 by Imtiaz Imtiaz Developments · Dubai Islands | 54.1% 5 Nov 2026 | 77% | -23.2 | behind | 20 Apr 2027 | Oct 2027 – Feb 2028 | dubairealestateiq.com |
| Sunset Bay Grand by Imtiaz Imtiaz Developments · Dubai Islands | 23.1% 9 Nov 2026 | 46% | -22.6 | behind | 15 Feb 2028 | May 2030 – Jul 2030 | dubairealestateiq.com |
| Pearl House 4 by Imtiaz Imtiaz Developments · Jumeirah Village Circle (JVC) | 17.9% 7 Oct 2026 | 40% | -22.2 | behind | 29 Feb 2028 | Jan 2031 – Apr 2031 | dubairealestateiq.com |
| Le Blanc by Imtiaz Imtiaz Developments · Dubailand Residence Complex | 6% 8 Oct 2026 | 27% | -20.5 | behind | 15 Oct 2028 | under 10% built: too early to project | dubairealestateiq.com |
| Wynwood Horizon Imtiaz Developments · Meydan Horizon, MBR City | 9.6% 16 Sept 2026 | 28% | -18.7 | behind | 30 Oct 2028 | under 10% built: too early to project | dubairealestateiq.com |
| Sea Cliff by Imtiaz Imtiaz Developments · Dubai Islands | 7.7% 13 Oct 2026 | 26% | -18.6 | behind | 15 Aug 2028 | under 10% built: too early to project | dubairealestateiq.com |
| Sunset Bay 4 by Imtiaz Imtiaz Developments · Dubai Islands | 53% 29 Sept 2026 | 69% | -15.8 | behind | 15 May 2027 | Dec 2027 – Dec 2027 | dubairealestateiq.com |
| The Symphony by Imtiaz Imtiaz Developments · Mohammed Bin Rashid City | 6.3% 16 Sept 2026 | 22% | -15.2 | behind | 15 Jun 2029 | under 10% built: too early to project | dubairealestateiq.com |
| Sunset Bay 3 by Imtiaz Imtiaz Developments · Dubai Islands | 60% 17 Sept 2026 | 75% | -14.8 | behind | 20 Mar 2027 | Aug 2027 – Sept 2027 | dubairealestateiq.com |
| Sunset Bay 5 by Imtiaz Imtiaz Developments · Dubai Islands | 44.5% 5 Oct 2026 | 56% | -11.5 | behind | 15 Oct 2027 | Apr 2028 – May 2028 | dubairealestateiq.com |
| Sunset Bay 2 by Imtiaz Imtiaz Developments · Dubai Islands | 80.9% 4 Nov 2026 | 85% | -4.3 | on pace or ahead | 20 Feb 2027 | Mar 2027 – Mar 2027 | dubairealestateiq.com |
| Enre Residence Imtiaz Developments · Dubai South | 24.2% 30 Oct 2026 | 28% | -3.9 | on pace or ahead | 15 Aug 2028 | Dec 2028 – Jan 2029 | dubairealestateiq.com |
| Luxor by Imtiaz Imtiaz Developments · Jumeirah Village Circle (JVC) | 90% 17 Sept 2026 | 92% | -2.3 | on pace or ahead | 15 Dec 2026 | Jan 2027 | dubairealestateiq.com |
| Sunset Bay One by Imtiaz Imtiaz Developments · Palm Deira | 93.5% 2 Nov 2026 | 93% | 0.8 | on pace or ahead | 25 Dec 2026 | Dec 2026 – Dec 2026 | dubairealestateiq.com |
| Cove Edition 2 by Imtiaz Imtiaz Developments · Dubailand (DLRC) | 60.1% 20 Oct 2026 | 100% | - | registered date passed | 15 Oct 2026 | Feb 2028 | dubairealestateiq.com |
| Cove Edition by Imtiaz Imtiaz Developments · Dubailand (DLRC) | 90.2% 12 Oct 2026 | 100% | - | registered date passed | 25 Aug 2026 | Jan 2027 | dubairealestateiq.com |
| Raw District Imtiaz Developments · Downtown Jebel Ali, Sheikh Zayed Road | 0% 9 Jun 2026 | - | - | not comparable | 15 Dec 2029 | under 10% built: too early to project | dubairealestateiq.com |
| Beach Walk III by Imtiaz Imtiaz Developments · Dubai Islands | 100% 4 Nov 2026 | - | - | not comparable | 14 Jun 2026 | no projection | dubairealestateiq.com |
| Raw District 2 by Imtiaz Imtiaz Developments · Jabal Ali Industrial Second | 0% 8 Jul 2026 | - | - | not comparable | 1 Dec 2029 | under 10% built: too early to project | dubairealestateiq.com |
Method
Time elapsed = (inspection date minus construction start on the register) divided by (registered completion date minus construction start). When no start date is printed, the registration date is used.
Gap = % built at the inspection minus % of time elapsed at the same date, in percentage points. Behind = a gap below -10 points. Registered date passed = the inspection is after the completion date on the register and the project is not at 100%.
Projection, only for 10% to 99% built: the remaining % divided by the observed pace, where the pace is % built per day since the start date, since the registration date and between the last two inspections we hold (when it rose). The range runs from the earliest to the latest of these estimates.
Limits: Construction does not move in a straight line (a slow start, faster structure, slow finishing), so a straight line from an early reading tends to give later dates than the work will need, and a late reading can give earlier ones. The % built is the DLD inspection figure, not ours.
Source: the Dubai Land Department project register as mirrored per project with its inspection history, read by our register job; 929 DLD records, 28 with two or more dated inspections.
Files: /data/n35a/pace.json · /open/n35a-build.py · /registers/changes/