Home / Dubai / Construction pace against the registered date
Construction pace against the registered date
For Dubai projects with DLD inspection readings: % built against the share of time elapsed to the completion date on the register, and the completion range the observed pace points to. A projection, not a promise.
Updated 23 Nov 2026
A projection from the pace on the register, not a promise, and not a finding about the developer.
Show as a table
| Gap (points) | Projects |
|---|---|
| -60 … -50 | 98 |
| -50 … -40 | 119 |
| -40 … -30 | 168 |
| -30 … -20 | 186 |
| -20 … -10 | 140 |
| -10 … 0 | 94 |
| 0 … 10 | 29 |
| 10 … 20 | 13 |
| 20 … 30 | 9 |
| 30 … 40 | 3 |
| 40 … 50 | 1 |
Projects
| Project | % built (inspection) | Time elapsed | Gap (points) | Pace | Registered completion | Projected range | Register |
|---|---|---|---|---|---|---|---|
| Azizi Venice 14 Azizi Developments · Azizi Venice, Dubai South (DWC) | 30.3% 22 Jun 2026 | 100% | - | registered date passed | 30 May 2026 | Nov 2030 – May 2031 | dubairealestateiq.com |
| Viewz 2 by Danube Danube Properties Development L.L.C · Jumeirah Lake Towers (Al Thanyah Fifth) | 65% 20 Oct 2026 | 100% | - | registered date passed | 30 Jun 2026 | Jul 2028 – Sept 2028 | dubairealestateiq.com |
| Expo Valley (villas and townhouses) Expo City Dubai · Expo City Dubai (Madinat Al Mataar) | 66% 19 Aug 2026 | 100% | - | registered date passed | 31 Jan 2026 | May 2028 – May 2028 | dubairealestateiq.com |
| Azizi Grand Azizi Developments L.L.C · Dubai Sports City | 82.1% 24 Jun 2026 | 100% | - | registered date passed | 2 Feb 2025 | Apr 2028 – Apr 2028 | dubairealestateiq.com |
| Burj Binghatti Jacob & Co Residences Binghatti Developers · Business Bay | 52.1% 31 Aug 2026 | 100% | - | registered date passed | 30 Jun 2026 | Mar 2030 – Apr 2030 | dubairealestateiq.com |
| Binghatti Hillviews Binghatti Developers · Dubai Science Park | 32.6% 25 Jun 2026 | 100% | - | registered date passed | 1 Apr 2026 | Nov 2029 – Jan 2030 | dubairealestateiq.com |
| Couture by Cavalli DAMAC Properties · Dubai Canal, Safa Park | 27.6% 4 Nov 2026 | 100% | - | registered date passed | 31 May 2025 | Apr 2036 – Jul 2037 | dubairealestateiq.com |
| Cove Edition 2 by Imtiaz Imtiaz Developments · Dubailand (DLRC) | 60.1% 20 Oct 2026 | 100% | - | registered date passed | 15 Oct 2026 | Feb 2028 | dubairealestateiq.com |
| Cove Edition by Imtiaz Imtiaz Developments · Dubailand (DLRC) | 90.2% 12 Oct 2026 | 100% | - | registered date passed | 25 Aug 2026 | Jan 2027 | dubairealestateiq.com |
| SAMANA Mykonos Signature SAMANA Developers · Arjan | 86% 12 Oct 2026 | 100% | - | registered date passed | 30 Apr 2026 | Apr 2027 | dubairealestateiq.com |
| SAMANA Skyros SAMANA Developers · Arjan | 71.3% 29 Sept 2026 | 100% | - | registered date passed | 30 Apr 2026 | Jan 2028 | dubairealestateiq.com |
| SAMANA Waves SAMANA Developers · Jumeirah Village Circle (JVC) | 90.6% 16 Oct 2026 | 100% | - | registered date passed | 15 Apr 2026 | Apr 2027 | dubairealestateiq.com |
| SAMANA Waves 2 SAMANA Developers · Jumeirah Village Circle (JVC) | 52.1% 2 Oct 2026 | 100% | - | registered date passed | 20 Mar 2026 | Dec 2029 | dubairealestateiq.com |
Method
Time elapsed = (inspection date minus construction start on the register) divided by (registered completion date minus construction start). When no start date is printed, the registration date is used.
Gap = % built at the inspection minus % of time elapsed at the same date, in percentage points. Behind = a gap below -10 points. Registered date passed = the inspection is after the completion date on the register and the project is not at 100%.
Projection, only for 10% to 99% built: the remaining % divided by the observed pace, where the pace is % built per day since the start date, since the registration date and between the last two inspections we hold (when it rose). The range runs from the earliest to the latest of these estimates.
Limits: Construction does not move in a straight line (a slow start, faster structure, slow finishing), so a straight line from an early reading tends to give later dates than the work will need, and a late reading can give earlier ones. The % built is the DLD inspection figure, not ours.
Source: the Dubai Land Department project register as mirrored per project with its inspection history, read by our register job; 985 DLD records, 28 with two or more dated inspections.
Files: /data/n35a/pace.json · /open/n35a-build.py · /registers/changes/