Construction pace against the registered date

For Dubai projects with DLD inspection readings: % built against the share of time elapsed to the completion date on the register, and the completion range the observed pace points to. A projection, not a promise.

Updated 23 Nov 2026

A projection from the pace on the register, not a promise, and not a finding about the developer.

860projects compared (DLD % built and dates on the register)
82.7%more than 10 points behind the time elapsed (95% interval 80 to 85.1%)
-27median gap in points, % built minus % of time elapsed (95% interval -29.1 to -26)
452projects with a projected range (10% to 99% built)
86.7%of them projected after the registered date (95% interval 83.3 to 89.5%)
≤-6098-50119-40168-30186-20140-10940291013209303401
Projects by gap between % built and % of time elapsed, in 10-point bins
Show as a table
Gap (points)Projects
-60 … -5098
-50 … -40119
-40 … -30168
-30 … -20186
-20 … -10140
-10 … 094
0 … 1029
10 … 2013
20 … 309
30 … 403
40 … 501

Projects

13 projects, page 1
Project% built (inspection)Time elapsedGap (points)PaceRegistered completionProjected rangeRegister
Azizi Venice 14
Azizi Developments · Azizi Venice, Dubai South (DWC)
30.3%
22 Jun 2026
100%-registered date passed30 May 2026Nov 2030 – May 2031dubairealestateiq.com
Viewz 2 by Danube
Danube Properties Development L.L.C · Jumeirah Lake Towers (Al Thanyah Fifth)
65%
20 Oct 2026
100%-registered date passed30 Jun 2026Jul 2028 – Sept 2028dubairealestateiq.com
Expo Valley (villas and townhouses)
Expo City Dubai · Expo City Dubai (Madinat Al Mataar)
66%
19 Aug 2026
100%-registered date passed31 Jan 2026May 2028 – May 2028dubairealestateiq.com
Azizi Grand
Azizi Developments L.L.C · Dubai Sports City
82.1%
24 Jun 2026
100%-registered date passed2 Feb 2025Apr 2028 – Apr 2028dubairealestateiq.com
Burj Binghatti Jacob & Co Residences
Binghatti Developers · Business Bay
52.1%
31 Aug 2026
100%-registered date passed30 Jun 2026Mar 2030 – Apr 2030dubairealestateiq.com
Binghatti Hillviews
Binghatti Developers · Dubai Science Park
32.6%
25 Jun 2026
100%-registered date passed1 Apr 2026Nov 2029 – Jan 2030dubairealestateiq.com
Couture by Cavalli
DAMAC Properties · Dubai Canal, Safa Park
27.6%
4 Nov 2026
100%-registered date passed31 May 2025Apr 2036 – Jul 2037dubairealestateiq.com
Cove Edition 2 by Imtiaz
Imtiaz Developments · Dubailand (DLRC)
60.1%
20 Oct 2026
100%-registered date passed15 Oct 2026Feb 2028dubairealestateiq.com
Cove Edition by Imtiaz
Imtiaz Developments · Dubailand (DLRC)
90.2%
12 Oct 2026
100%-registered date passed25 Aug 2026Jan 2027dubairealestateiq.com
SAMANA Mykonos Signature
SAMANA Developers · Arjan
86%
12 Oct 2026
100%-registered date passed30 Apr 2026Apr 2027dubairealestateiq.com
SAMANA Skyros
SAMANA Developers · Arjan
71.3%
29 Sept 2026
100%-registered date passed30 Apr 2026Jan 2028dubairealestateiq.com
SAMANA Waves
SAMANA Developers · Jumeirah Village Circle (JVC)
90.6%
16 Oct 2026
100%-registered date passed15 Apr 2026Apr 2027dubairealestateiq.com
SAMANA Waves 2
SAMANA Developers · Jumeirah Village Circle (JVC)
52.1%
2 Oct 2026
100%-registered date passed20 Mar 2026Dec 2029dubairealestateiq.com

Method

Time elapsed = (inspection date minus construction start on the register) divided by (registered completion date minus construction start). When no start date is printed, the registration date is used.

Gap = % built at the inspection minus % of time elapsed at the same date, in percentage points. Behind = a gap below -10 points. Registered date passed = the inspection is after the completion date on the register and the project is not at 100%.

Projection, only for 10% to 99% built: the remaining % divided by the observed pace, where the pace is % built per day since the start date, since the registration date and between the last two inspections we hold (when it rose). The range runs from the earliest to the latest of these estimates.

Limits: Construction does not move in a straight line (a slow start, faster structure, slow finishing), so a straight line from an early reading tends to give later dates than the work will need, and a late reading can give earlier ones. The % built is the DLD inspection figure, not ours.

Source: the Dubai Land Department project register as mirrored per project with its inspection history, read by our register job; 985 DLD records, 28 with two or more dated inspections.

Files: /data/n35a/pace.json · /open/n35a-build.py · /registers/changes/