Construction pace against the registered date
For Dubai projects with DLD inspection readings: % built against the share of time elapsed to the completion date on the register, and the completion range the observed pace points to. A projection, not a promise.
Updated 23 Nov 2026
A projection from the pace on the register, not a promise, and not a finding about the developer.
Show as a table
| Gap (points) | Projects |
|---|---|
| -60 … -50 | 90 |
| -50 … -40 | 115 |
| -40 … -30 | 162 |
| -30 … -20 | 178 |
| -20 … -10 | 130 |
| -10 … 0 | 90 |
| 0 … 10 | 29 |
| 10 … 20 | 12 |
| 20 … 30 | 7 |
| 30 … 40 | 1 |
| 40 … 50 | 1 |
Projects
Developer: binghatti-developers · All
| Project | % built (inspection) | Time elapsed | Gap (points) | Pace | Registered completion | Projected range | Register |
|---|---|---|---|---|---|---|---|
| Vision Iconic (Mercedes-Benz Places, Binghatti City) Binghatti Developers · Mercedes-Benz Places | Binghatti City, Meydan | 0% 28 Jul 2026 | 86% | -86 | behind | 31 Dec 2026 | under 10% built: too early to project | dubairealestateiq.com |
| Binghatti Aquarise Binghatti Developers · Business Bay | 28% 22 Oct 2026 | 99% | -70.5 | behind | 31 Oct 2026 | Sept 2030 – Dec 2030 | dubairealestateiq.com |
| Binghatti Titania Binghatti Developers · Majan | 14.7% 28 Oct 2026 | 76% | -61.4 | behind | 28 Feb 2027 | Apr 2032 – Jan 2033 | dubairealestateiq.com |
| Binghatti Vintage Binghatti Developers · Majan | 10.6% 28 Oct 2026 | 72% | -61.2 | behind | 31 Mar 2027 | May 2034 – Nov 2035 | dubairealestateiq.com |
| Binghatti Skyrise Binghatti Developers · Business Bay | 35.9% 22 Oct 2026 | 91% | -55.4 | behind | 31 Dec 2026 | May 2030 – May 2030 | dubairealestateiq.com |
| Binghatti Circle Binghatti Developers · Jumeirah Village Circle (JVC) | 22.1% 26 Oct 2026 | 70% | -48.1 | behind | 31 May 2027 | Apr 2031 – Oct 2031 | dubairealestateiq.com |
| One by Binghatti Binghatti Developers · Business Bay | 50.2% 14 May 2026 | 98% | -47.8 | behind | 30 May 2026 | Mar 2028 – Jul 2028 | dubairealestateiq.com |
| Binghatti Cullinan Binghatti Developers · Al Jaddaf | 18.3% 28 Oct 2026 | 58% | -39.2 | behind | 30 Jun 2027 | Jul 2030 – Nov 2030 | dubairealestateiq.com |
| Binghatti Luxuria Binghatti Developers · Jumeirah Village Triangle | 7% 17 Sept 2026 | 45% | -38 | behind | 30 Jul 2027 | under 10% built: too early to project | dubairealestateiq.com |
| Project Maybach Binghatti Developers · Nad Al Shiba First | 19.1% 3 Nov 2026 | 55% | -36 | behind | 30 Jun 2027 | Mar 2030 – Apr 2030 | dubairealestateiq.com |
| Maybach Six Binghatti Developers · Nad Al Shiba First | 17.5% 3 Nov 2026 | 49% | -31.9 | behind | 31 Aug 2027 | Aug 2030 | dubairealestateiq.com |
| Maybach Ultimate Luxury Binghatti Developers · Nad Al Shiba First | 17.7% 3 Nov 2026 | 49% | -31.6 | behind | 31 Aug 2027 | Jul 2030 | dubairealestateiq.com |
| Binghatti Flare 02 Binghatti Developers · Jumeirah Village Triangle | 17.8% 19 Jun 2026 | 48% | -30.6 | behind | 15 Jun 2027 | Feb 2030 – Sept 2030 | dubairealestateiq.com |
| Binghatti Etherea Binghatti Developers · Jumeirah Village Circle | 7.2% 15 Sept 2026 | 35% | -28 | behind | 31 Dec 2027 | under 10% built: too early to project | dubairealestateiq.com |
| Binghatti Flare Binghatti Developers · Jumeirah Village Triangle | 20% 19 Jun 2026 | 47% | -26.5 | behind | 14 Jul 2027 | Oct 2029 – Mar 2030 | dubairealestateiq.com |
| Binghatti Skyflame 2 Binghatti Developers · Majan | 12.2% 28 Oct 2026 | 39% | -26.3 | behind | 31 Dec 2027 | Feb 2031 – Feb 2032 | dubairealestateiq.com |
| Binghatti Skyblade Binghatti Developers · Downtown Dubai | 17.1% 21 Apr 2026 | 43% | -26 | behind | 30 Nov 2027 | Jul 2029 – Mar 2032 | dubairealestateiq.com |
| Binghatti Skyflame 1 Binghatti Developers · Majan | 15.3% 28 Oct 2026 | 39% | -23.3 | behind | 31 Dec 2027 | Feb 2030 – Nov 2030 | dubairealestateiq.com |
| Binghatti Hillcrest Binghatti Developers · Arjan | 60% 17 Sept 2026 | 77% | -17 | behind | 31 Dec 2026 | Mar 2027 – May 2027 | dubairealestateiq.com |
| Binghatti SkyTerraces Binghatti Developers · Motor City | 0% 7 Jan 2026 | 1% | -0.9 | on pace or ahead | 31 Oct 2027 | under 10% built: too early to project | dubairealestateiq.com |
| Burj Binghatti Jacob & Co Residences Binghatti Developers · Business Bay | 52.1% 31 Aug 2026 | 100% | - | registered date passed | 30 Jun 2026 | Mar 2030 – Apr 2030 | dubairealestateiq.com |
| Binghatti Hillviews Binghatti Developers · Dubai Science Park | 32.6% 25 Jun 2026 | 100% | - | registered date passed | 1 Apr 2026 | Nov 2029 – Jan 2030 | dubairealestateiq.com |
| Binghatti Wraith Binghatti Developers · Al Jaddaf | 0% 20 May 2026 | - | - | not comparable | 30 Dec 2027 | under 10% built: too early to project | dubairealestateiq.com |
| Binghatti Starfall Binghatti Developers · Al Jaddaf | 0% 20 May 2026 | - | - | not comparable | 30 Sept 2028 | under 10% built: too early to project | dubairealestateiq.com |
| Binghatti Spectre Binghatti Developers · Al Jaddaf, near DEWA headquarters | 0% 9 Feb 2026 | - | - | not comparable | 31 Dec 2028 | under 10% built: too early to project | dubairealestateiq.com |
Method
Time elapsed = (inspection date minus construction start on the register) divided by (registered completion date minus construction start). When no start date is printed, the registration date is used.
Gap = % built at the inspection minus % of time elapsed at the same date, in percentage points. Behind = a gap below -10 points. Registered date passed = the inspection is after the completion date on the register and the project is not at 100%.
Projection, only for 10% to 99% built: the remaining % divided by the observed pace, where the pace is % built per day since the start date, since the registration date and between the last two inspections we hold (when it rose). The range runs from the earliest to the latest of these estimates.
Limits: Construction does not move in a straight line (a slow start, faster structure, slow finishing), so a straight line from an early reading tends to give later dates than the work will need, and a late reading can give earlier ones. The % built is the DLD inspection figure, not ours.
Source: the Dubai Land Department project register as mirrored per project with its inspection history, read by our register job; 929 DLD records, 28 with two or more dated inspections.
Files: /data/n35a/pace.json · /open/n35a-build.py · /registers/changes/