Home / Dubai / Construction pace against the registered date
Construction pace against the registered date
For Dubai projects with DLD inspection readings: % built against the share of time elapsed to the completion date on the register, and the completion range the observed pace points to. A projection, not a promise.
Updated 23 Nov 2026
A projection from the pace on the register, not a promise, and not a finding about the developer.
Show as a table
| Gap (points) | Projects |
|---|---|
| -60 … -50 | 90 |
| -50 … -40 | 115 |
| -40 … -30 | 162 |
| -30 … -20 | 178 |
| -20 … -10 | 130 |
| -10 … 0 | 90 |
| 0 … 10 | 29 |
| 10 … 20 | 12 |
| 20 … 30 | 7 |
| 30 … 40 | 1 |
| 40 … 50 | 1 |
Projects
| Project | % built (inspection) | Time elapsed | Gap (points) | Pace | Registered completion | Projected range | Register |
|---|---|---|---|---|---|---|---|
| Vision Iconic (Mercedes-Benz Places, Binghatti City) Binghatti Developers · Mercedes-Benz Places | Binghatti City, Meydan | 0% 28 Jul 2026 | 86% | -86 | behind | 31 Dec 2026 | under 10% built: too early to project | dubairealestateiq.com |
| Eden Hills Eden Hills · Hadaeq Sheikh Mohammed Bin Rashid | 3.5% 22 Sept 2026 | 87% | -83.1 | behind | 25 Dec 2026 | under 10% built: too early to project | dubairealestateiq.com |
| Celeste HRE Development · Al Jadaf | 3.4% 9 Nov 2026 | 85% | -81.6 | behind | 28 Feb 2027 | under 10% built: too early to project | dubairealestateiq.com |
| Azizi Milan 51 Azizi Developments · City of Arabia | 0% 5 Nov 2026 | 81% | -80.7 | behind | 26 Mar 2027 | under 10% built: too early to project | dubairealestateiq.com |
| Azizi Milan 30 Azizi Developments · City of Arabia | 0% 5 Nov 2026 | 80% | -79.5 | behind | 4 Apr 2027 | under 10% built: too early to project | dubairealestateiq.com |
| Azizi Milan 18 Azizi Developments · City of Arabia | 0% 5 Nov 2026 | 78% | -77.8 | behind | 16 Apr 2027 | under 10% built: too early to project | dubairealestateiq.com |
| Azizi Milan 20 Azizi Developments · City of Arabia | 0% 5 Nov 2026 | 77% | -76.6 | behind | 30 Apr 2027 | under 10% built: too early to project | dubairealestateiq.com |
| Moonsa Residences 2 Dugasta · International City Ph 2 & 3 | 1% 20 Jul 2026 | 78% | -76.5 | behind | 31 Dec 2026 | under 10% built: too early to project | dubairealestateiq.com |
| Azizi Milan 53 Azizi Developments · City of Arabia | 0% 5 Nov 2026 | 76% | -76.3 | behind | 30 Apr 2027 | under 10% built: too early to project | dubairealestateiq.com |
| Azizi Milan 55 Azizi Developments · City of Arabia | 0% 5 Nov 2026 | 76% | -76.3 | behind | 30 Apr 2027 | under 10% built: too early to project | dubairealestateiq.com |
| SAMANA Manhattan 2 SAMANA Developers · Jumeirah Village Circle | 21.2% 17 Sept 2026 | 95% | -74 | behind | 1 Nov 2026 | Nov 2035 – Jun 2036 | dubairealestateiq.com |
| Numa Reserve Mirfa · Majan | 10.3% 5 Oct 2026 | 84% | -74 | behind | 31 Dec 2026 | Nov 2037 | dubairealestateiq.com |
| Vistara House Object 1 · Jabal Ali First | 10.5% 12 Nov 2026 | 83% | -72.9 | behind | 30 Mar 2027 | Aug 2042 – Jan 2043 | dubairealestateiq.com |
| Azizi Milan 9 Azizi Developments · City of Arabia | 0% 5 Nov 2026 | 73% | -72.9 | behind | 30 May 2027 | under 10% built: too early to project | dubairealestateiq.com |
| 105 Residences by Kamdar Kamdar · Jumeirah Village Circle | 12.5% 15 Oct 2026 | 84% | -72 | behind | 28 Feb 2027 | Dec 2040 | dubairealestateiq.com |
| Jade Tower Tiger Properties · Majan | 11% 2 Oct 2026 | 83% | -71.5 | behind | 31 Mar 2027 | Jul 2045 | dubairealestateiq.com |
| Azizi Milan 28 Azizi Developments · City of Arabia | 0% 5 Nov 2026 | 71% | -71.2 | behind | 3 Jun 2027 | under 10% built: too early to project | dubairealestateiq.com |
| Binghatti Aquarise Binghatti Developers · Business Bay | 28% 22 Oct 2026 | 99% | -70.5 | behind | 31 Oct 2026 | Sept 2030 – Dec 2030 | dubairealestateiq.com |
| Keturah Reserve MAG · MBR City District 7, Meydan | 10% 3 Aug 2026 | 80% | -70.2 | behind | 30 Jun 2027 | Feb 2035 | dubairealestateiq.com |
| Bonds Avenue Residences Amirah Living · Palm Deira | 6.9% 1 Jul 2026 | 76% | -69.5 | behind | 31 Dec 2026 | under 10% built: too early to project | dubairealestateiq.com |
| Azizi Venice 16 Azizi Developments · Madinat Al Mataar | 3.7% 16 Nov 2026 | 73% | -69.2 | behind | 2 Jun 2027 | under 10% built: too early to project | dubairealestateiq.com |
| Baccarat Hotel and Residences, Dubai Shamal · Burj Khalifa | 21.2% 3 Sept 2026 | 90% | -69.1 | behind | 29 Dec 2026 | Sept 2037 | dubairealestateiq.com |
| One Residence Ginco · Burj Khalifa | 6.3% 27 Jul 2026 | 75% | -68.8 | behind | 31 Mar 2027 | under 10% built: too early to project | dubairealestateiq.com |
| Forest City 2 HZ Development · Dubailand Residence Complex (Wadi Al Safa 5) | 1.2% 15 Oct 2026 | 69% | -67.5 | behind | 1 Jun 2027 | under 10% built: too early to project | dubairealestateiq.com |
| West 5 Residences West F 5 Development L.L.C · Al Satwa | 8.2% 19 Oct 2026 | 76% | -67.3 | behind | 14 Apr 2027 | under 10% built: too early to project | dubairealestateiq.com |
| Selora Residences Swank · Majan | 3.5% 22 Sept 2026 | 71% | -67.3 | behind | 30 Apr 2027 | under 10% built: too early to project | dubairealestateiq.com |
| Chelsea Gardens Alaia · Al Satwa | 10.3% 23 Sept 2026 | 77% | -67 | behind | 28 Feb 2027 | Jul 2039 | dubairealestateiq.com |
| Treppan Tower Fakhruddin · Jumeirah Village Triangle | 16.1% 10 Nov 2026 | 83% | -66.8 | behind | 1 Apr 2027 | Sept 2036 | dubairealestateiq.com |
| Saas Hills SAAS Properties · Dubai Science Park | 17% 4 Nov 2026 | 83% | -66.2 | behind | 31 Mar 2027 | Jul 2036 | dubairealestateiq.com |
| Trussardi Residences 2 M I R A Developments L.L.C · Jabal Ali First | 6.6% 12 Nov 2026 | 73% | -66 | behind | 3 Jul 2027 | under 10% built: too early to project | dubairealestateiq.com |
| Amali Island DAMAC Properties · The World | 18.7% 27 Oct 2026 | 85% | -65.8 | behind | 31 Mar 2027 | Nov 2036 – Jun 2037 | dubairealestateiq.com |
| Capital One Royal Centurion · Al Hebiah First | 20% 8 Oct 2026 | 84% | -64.4 | behind | 9 Feb 2027 | Feb 2034 | dubairealestateiq.com |
| Havelock Residences HMB Homes · Jabal Ali First | 30% 9 Nov 2026 | 94% | -63.8 | behind | 31 Dec 2026 | Nov 2031 | dubairealestateiq.com |
| Como Residences Dubai Holding Real Estate · Palm Jumeirah | 24.8% 9 Oct 2026 | 88% | -63.5 | behind | 27 Mar 2027 | May 2037 | dubairealestateiq.com |
| Milos by Karma Karma · Dubai Land Residence Complex | 0.4% 22 Apr 2026 | 64% | -63.5 | behind | 1 Apr 2027 | under 10% built: too early to project | dubairealestateiq.com |
| Luminar Tower 3 Object 1 · Jumeirah Village Triangle | 18.3% 28 Oct 2026 | 82% | -63.3 | behind | 30 Mar 2027 | Feb 2035 | dubairealestateiq.com |
| Woodland Terraces A M I S · Majan | 10.3% 2 Sept 2026 | 74% | -63.2 | behind | 30 Mar 2027 | Jun 2040 | dubairealestateiq.com |
| SAMANA Ocean Pearl SAMANA Developers · Dubai Islands | 25.1% 17 Sept 2026 | 88% | -62.9 | behind | 31 Dec 2026 | Jan 2033 | dubairealestateiq.com |
| Autograph Collection (DAMAC Hills) DAMAC Properties · DAMAC Hills | 17.9% 30 Oct 2026 | 80% | -62.1 | behind | 30 May 2027 | Jun 2037 – Aug 2037 | dubairealestateiq.com |
| Woodland Crest A M I S · Nad Al Shiba First | 1.4% 2 Sept 2026 | 64% | -62.1 | behind | 30 Jun 2027 | under 10% built: too early to project | dubairealestateiq.com |
| Vio Residences Modelux · International City Ph 2 & 3 | 6.4% 3 Aug 2026 | 69% | -62.1 | behind | 31 Dec 2026 | under 10% built: too early to project | dubairealestateiq.com |
| Al Haseen Residence Dugasta · Dubai Industrial City (Saih Shuaib 2) | 11.8% 14 Jul 2026 | 73% | -61.6 | behind | 30 Dec 2026 | Feb 2036 | dubairealestateiq.com |
| Binghatti Titania Binghatti Developers · Majan | 14.7% 28 Oct 2026 | 76% | -61.4 | behind | 28 Feb 2027 | Apr 2032 – Jan 2033 | dubairealestateiq.com |
| Binghatti Vintage Binghatti Developers · Majan | 10.6% 28 Oct 2026 | 72% | -61.2 | behind | 31 Mar 2027 | May 2034 – Nov 2035 | dubairealestateiq.com |
| Terra Tower Dugasta · Dubai Land Residence Complex | 7.4% 8 Jul 2026 | 68% | -60.8 | behind | 30 Apr 2027 | under 10% built: too early to project | dubairealestateiq.com |
| Coral Isle Residences Grovy Homes · Palm Deira | 7.2% 17 Aug 2026 | 68% | -60.5 | behind | 31 Mar 2027 | under 10% built: too early to project | dubairealestateiq.com |
| Isolana Residences Hayaat Ikhlaq · Palm Deira | 5.5% 23 Jul 2026 | 66% | -60.4 | behind | 20 Mar 2027 | under 10% built: too early to project | dubairealestateiq.com |
| Esme' Beach Residences Elysian · Palm Deira | 14.4% 3 Sept 2026 | 74% | -59.6 | behind | 1 Apr 2027 | May 2036 | dubairealestateiq.com |
| Zyra Vista Residences Laraix · International City Ph 2 & 3 | 2.1% 1 Jul 2026 | 61% | -59.2 | behind | 31 Mar 2027 | under 10% built: too early to project | dubairealestateiq.com |
| Lazord by Lapis Lapis Properties · Majan | 27.6% 3 Sept 2026 | 86% | -58.3 | behind | 31 Dec 2026 | Nov 2031 | dubairealestateiq.com |
| Alfal Residences Dubuild · Jumeirah Village Circle | 24.9% 25 Sept 2026 | 83% | -58 | behind | 28 Feb 2027 | Dec 2032 | dubairealestateiq.com |
| Gate Royale Residences Baron Prime · Jabal Ali First | 1.7% 3 Sept 2026 | 60% | -57.9 | behind | 2 Jun 2027 | under 10% built: too early to project | dubairealestateiq.com |
| Allegro Park by Mill Hill Riviera Development Mill Hill Riviera · Palm Deira | 4.2% 15 Oct 2026 | 61% | -57.1 | behind | 25 Apr 2027 | under 10% built: too early to project | dubairealestateiq.com |
| Hillmont Residences by Ellington Ellington Properties · Jumeirah Village Circle | 26.3% 22 Jul 2026 | 83% | -56.9 | behind | 31 Dec 2026 | Mar 2032 – Sept 2032 | dubairealestateiq.com |
| Norah Residence Al Tareq Star · Jumeirah Village Circle | 6.8% 29 Sept 2026 | 63% | -56.5 | behind | 30 Jun 2027 | under 10% built: too early to project | dubairealestateiq.com |
| Azizi Ruby Azizi Developments · Jumeirah Village Circle | 4.1% 17 Nov 2026 | 61% | -56.4 | behind | 23 Jan 2028 | under 10% built: too early to project | dubairealestateiq.com |
| Q Gardens Aliya AYS · Jumeirah Village Circle | 7.7% 5 Jul 2026 | 64% | -56.3 | behind | 30 Jun 2027 | under 10% built: too early to project | dubairealestateiq.com |
| The Collection by Naser N A S E R · Majan | 0.6% 1 Jul 2026 | 57% | -56.3 | behind | 30 Jun 2027 | under 10% built: too early to project | dubairealestateiq.com |
| Cotier House 2 by Imtiaz Imtiaz Developments · Dubai Islands | 20.2% 23 Oct 2026 | 76% | -56 | behind | 15 Apr 2027 | Sept 2032 – Oct 2032 | dubairealestateiq.com |
| Lexington Nshama · Al Yelayiss 2 | 4.5% 13 Aug 2026 | 61% | -56 | behind | 30 Sept 2027 | under 10% built: too early to project | dubairealestateiq.com |
Method
Time elapsed = (inspection date minus construction start on the register) divided by (registered completion date minus construction start). When no start date is printed, the registration date is used.
Gap = % built at the inspection minus % of time elapsed at the same date, in percentage points. Behind = a gap below -10 points. Registered date passed = the inspection is after the completion date on the register and the project is not at 100%.
Projection, only for 10% to 99% built: the remaining % divided by the observed pace, where the pace is % built per day since the start date, since the registration date and between the last two inspections we hold (when it rose). The range runs from the earliest to the latest of these estimates.
Limits: Construction does not move in a straight line (a slow start, faster structure, slow finishing), so a straight line from an early reading tends to give later dates than the work will need, and a late reading can give earlier ones. The % built is the DLD inspection figure, not ours.
Source: the Dubai Land Department project register as mirrored per project with its inspection history, read by our register job; 929 DLD records, 28 with two or more dated inspections.