Home / Dubai / Construction pace against the registered date

Construction pace against the registered date

For Dubai projects with DLD inspection readings: % built against the share of time elapsed to the completion date on the register, and the completion range the observed pace points to. A projection, not a promise.

Updated 23 Nov 2026

A projection from the pace on the register, not a promise, and not a finding about the developer.

815projects compared (DLD % built and dates on the register)
82.8%more than 10 points behind the time elapsed (95% interval 80.1 to 85.3%)
-27.1median gap in points, % built minus % of time elapsed (95% interval -29.5 to -26)
426projects with a projected range (10% to 99% built)
87.1%of them projected after the registered date (95% interval 83.6 to 89.9%)
≤-6090-50115-40162-30178-20130-10900291012207301401
Projects by gap between % built and % of time elapsed, in 10-point bins
Show as a table
Gap (points)Projects
-60 … -5090
-50 … -40115
-40 … -30162
-30 … -20178
-20 … -10130
-10 … 090
0 … 1029
10 … 2012
20 … 307
30 … 401
40 … 501

Projects

Developer: object-1 · All

14 projects, page 1
Project% built (inspection)Time elapsedGap (points)PaceRegistered completionProjected rangeRegister
Vistara House
Object 1 · Jabal Ali First
10.5%
12 Nov 2026
83%-72.9behind30 Mar 2027Aug 2042 – Jan 2043dubairealestateiq.com
Luminar Tower 3
Object 1 · Jumeirah Village Triangle
18.3%
28 Oct 2026
82%-63.3behind30 Mar 2027Feb 2035dubairealestateiq.com
Silviana Park Living
Object 1 · Jumeirah Village Triangle
2.7%
13 Aug 2026
51%-48.6behind30 Mar 2027under 10% built: too early to projectdubairealestateiq.com
Verdania
Object 1 · Dubai Land Residence Complex
30.9%
28 Oct 2026
77%-46.1behind30 Mar 2027Dec 2029dubairealestateiq.com
Evergrin House
Object 1 · Al Satwa
23.6%
7 Aug 2026
67%-43.5behind30 Dec 2026Mar 2029dubairealestateiq.com
Aurelia Residence
Object 1 · Dubai Sports City
4.5%
28 Oct 2026
47%-42.7behind30 Mar 2028under 10% built: too early to projectdubairealestateiq.com
Essenlife Residence
Object 1 · Jumeirah Village Triangle
7.2%
16 Sept 2026
46%-38.6behind30 Mar 2028under 10% built: too early to projectdubairealestateiq.com
ELAR1S Sky (Elaris Sky)
Object 1 · Jumeirah Village Triangle (JVT District 3)
1.2%
29 Oct 2026
35%-33.8behind30 Sept 2028under 10% built: too early to projectdubairealestateiq.com
Elaris Rise
Object 1 · Jumeirah Village Triangle
3.6%
29 Oct 2026
35%-31.4behind30 Sept 2028under 10% built: too early to projectdubairealestateiq.com
Elaris Axis
Object 1 · Jumeirah Village Triangle
4.2%
9 Nov 2026
29%-24.6behind30 Nov 2028under 10% built: too early to projectdubairealestateiq.com
Alta View Skyhomes
Object 1 · Jumeirah Village Circle
5.8%
16 Sept 2026
29%-22.9behind30 Jun 2029under 10% built: too early to projectdubairealestateiq.com
Iridian Park 2
Object 1 · Jumeirah Village Circle
21.3%
31 Jul 2026
17%4.6on pace or ahead1 Feb 2027Dec 2026dubairealestateiq.com
1wood Residence 2
Object 1 · Jumeirah Village Circle
0%
3 Mar 2026
--not comparable20 Oct 2027under 10% built: too early to projectdubairealestateiq.com
Sky Level 1
Object 1 · Jumeirah Village Circle
0%
13 May 2026
--not comparable28 Feb 2029under 10% built: too early to projectdubairealestateiq.com

Method

Time elapsed = (inspection date minus construction start on the register) divided by (registered completion date minus construction start). When no start date is printed, the registration date is used.

Gap = % built at the inspection minus % of time elapsed at the same date, in percentage points. Behind = a gap below -10 points. Registered date passed = the inspection is after the completion date on the register and the project is not at 100%.

Projection, only for 10% to 99% built: the remaining % divided by the observed pace, where the pace is % built per day since the start date, since the registration date and between the last two inspections we hold (when it rose). The range runs from the earliest to the latest of these estimates.

Limits: Construction does not move in a straight line (a slow start, faster structure, slow finishing), so a straight line from an early reading tends to give later dates than the work will need, and a late reading can give earlier ones. The % built is the DLD inspection figure, not ours.

Source: the Dubai Land Department project register as mirrored per project with its inspection history, read by our register job; 929 DLD records, 28 with two or more dated inspections.

Files: /data/n35a/pace.json · /open/n35a-build.py · /registers/changes/