Dubai projects grouped by the escrow bank printed on the DLD register: projects, units, median % built, registered dates passed and dates moved. Facts from the register, not a rating.

Updated 23 Nov 2026

Facts from the DLD register about the projects each bank holds escrow for. The bank does not build the project; this is not a rating of any bank or developer.

23escrow banks named on the register
905projects with a registered escrow bank (of 929 DLD records)

By escrow bank

Pick a bank to list its projects.
Escrow bankProjectsDevelopersUnitsMedian % built100% builtRegistered date passedBehind pace / comparedHandover moved
Emirates NBD1738050,66910.3%03121 / 1461
First Abu Dhabi Bank1444148,60612.1%03110 / 1352
Abu Dhabi Commercial Bank1154739,85311.1%0275 / 1001
Dubai Islamic Bank973157,44114.1%0273 / 830
Mashreq Bank704221,3377.3%1147 / 621
Abu Dhabi Islamic Bank452113,0747.7%0132 / 370
Commercial Bank of Dubai442518,2225.9%0035 / 430
Emirates Islamic Bank44269,6736%0031 / 401
United Bank Limited38296,2056.3%1029 / 330
The National Bank of Fujairah32236,7057.5%0023 / 270
Ajman Bank24510,5712.4%0016 / 170
Sharjah Islamic Bank22159,3816%0218 / 210
National Bank of Ras Al- Khaimah15113,1664%0012 / 140
Al Ahli Bank of Kuwait K S C P Dubai Branch999032.4%008 / 80
Bank of Sharjah962,8123.5%009 / 90
Bank of Baroda5484531.6%005 / 50
Arab Bank For Investment & Foreign Trade Almasref433,62934%003 / 30
Arab Bank Plc431,72219.2%003 / 40
United Arab Bank422,3999.1%002 / 20
Zand Bank3331812.7%003 / 30
Commercial Bank International221,18431%002 / 20
Al Maryah Community Bank L.L.C - Dubai Branch111216.2%001 / 10
Mcb Bank Limited11440%000 / 10

Pick a bank in the table to list its projects.

Method

Bank: the escrow account bank printed on the DLD project register for the project, as read by our register job; case and spelling variants of one bank name are unified, legal suffixes removed.

Registered date passed: the completion date on the register is before the build date and the last DLD inspection is below 100%.

Handover moved: our record holds a promised handover later than the first one we recorded.

Behind pace: % built more than 10 points below the share of time elapsed (see the construction pace page).

Limits: A bank holds the buyers' money in escrow under the law; the figures describe the projects, not the bank.

Files: /data/n35a/escrow.json · /open/n35a-build.py