Facts from the DLD register about the projects each bank holds escrow for. The bank does not build the project; this is not a rating of any bank or developer.
By escrow bank
| Escrow bank | Projects | Developers | Units | Median % built | 100% built | Registered date passed | Behind pace / compared | Handover moved |
|---|---|---|---|---|---|---|---|---|
| Emirates NBD | 173 | 80 | 50,669 | 10.3% | 0 | 3 | 121 / 146 | 1 |
| First Abu Dhabi Bank | 144 | 41 | 48,606 | 12.1% | 0 | 3 | 110 / 135 | 2 |
| Abu Dhabi Commercial Bank | 115 | 47 | 39,853 | 11.1% | 0 | 2 | 75 / 100 | 1 |
| Dubai Islamic Bank | 97 | 31 | 57,441 | 14.1% | 0 | 2 | 73 / 83 | 0 |
| Mashreq Bank | 70 | 42 | 21,337 | 7.3% | 1 | 1 | 47 / 62 | 1 |
| Abu Dhabi Islamic Bank | 45 | 21 | 13,074 | 7.7% | 0 | 1 | 32 / 37 | 0 |
| Commercial Bank of Dubai | 44 | 25 | 18,222 | 5.9% | 0 | 0 | 35 / 43 | 0 |
| Emirates Islamic Bank | 44 | 26 | 9,673 | 6% | 0 | 0 | 31 / 40 | 1 |
| United Bank Limited | 38 | 29 | 6,205 | 6.3% | 1 | 0 | 29 / 33 | 0 |
| The National Bank of Fujairah | 32 | 23 | 6,705 | 7.5% | 0 | 0 | 23 / 27 | 0 |
| Ajman Bank | 24 | 5 | 10,571 | 2.4% | 0 | 0 | 16 / 17 | 0 |
| Sharjah Islamic Bank | 22 | 15 | 9,381 | 6% | 0 | 2 | 18 / 21 | 0 |
| National Bank of Ras Al- Khaimah | 15 | 11 | 3,166 | 4% | 0 | 0 | 12 / 14 | 0 |
| Al Ahli Bank of Kuwait K S C P Dubai Branch | 9 | 9 | 903 | 2.4% | 0 | 0 | 8 / 8 | 0 |
| Bank of Sharjah | 9 | 6 | 2,812 | 3.5% | 0 | 0 | 9 / 9 | 0 |
| Bank of Baroda | 5 | 4 | 845 | 31.6% | 0 | 0 | 5 / 5 | 0 |
| Arab Bank For Investment & Foreign Trade Almasref | 4 | 3 | 3,629 | 34% | 0 | 0 | 3 / 3 | 0 |
| Arab Bank Plc | 4 | 3 | 1,722 | 19.2% | 0 | 0 | 3 / 4 | 0 |
| United Arab Bank | 4 | 2 | 2,399 | 9.1% | 0 | 0 | 2 / 2 | 0 |
| Zand Bank | 3 | 3 | 318 | 12.7% | 0 | 0 | 3 / 3 | 0 |
| Commercial Bank International | 2 | 2 | 1,184 | 31% | 0 | 0 | 2 / 2 | 0 |
| Al Maryah Community Bank L.L.C - Dubai Branch | 1 | 1 | 121 | 6.2% | 0 | 0 | 1 / 1 | 0 |
| Mcb Bank Limited | 1 | 1 | 44 | 0% | 0 | 0 | 0 / 1 | 0 |
Pick a bank in the table to list its projects.
Method
Bank: the escrow account bank printed on the DLD project register for the project, as read by our register job; case and spelling variants of one bank name are unified, legal suffixes removed.
Registered date passed: the completion date on the register is before the build date and the last DLD inspection is below 100%.
Handover moved: our record holds a promised handover later than the first one we recorded.
Behind pace: % built more than 10 points below the share of time elapsed (see the construction pace page).
Limits: A bank holds the buyers' money in escrow under the law; the figures describe the projects, not the bank.