Home / Dubai / Construction pace against the registered date
Construction pace against the registered date
For Dubai projects with DLD inspection readings: % built against the share of time elapsed to the completion date on the register, and the completion range the observed pace points to. A projection, not a promise.
Updated 23 Nov 2026
A projection from the pace on the register, not a promise, and not a finding about the developer.
Show as a table
| Gap (points) | Projects |
|---|---|
| -60 … -50 | 90 |
| -50 … -40 | 115 |
| -40 … -30 | 162 |
| -30 … -20 | 178 |
| -20 … -10 | 130 |
| -10 … 0 | 90 |
| 0 … 10 | 29 |
| 10 … 20 | 12 |
| 20 … 30 | 7 |
| 30 … 40 | 1 |
| 40 … 50 | 1 |
Projects
| Project | % built (inspection) | Time elapsed | Gap (points) | Pace | Registered completion | Projected range | Register |
|---|---|---|---|---|---|---|---|
| Palm Beach Towers Dubai Holding Real Estate · Palm Jumeirah | 81.6% 12 Aug 2026 | 91% | -9.8 | on pace or ahead | 31 Dec 2026 | Jul 2027 | dubairealestateiq.com |
| Soul by Vision Vision Developments · Dubai Production City | 77% 12 Oct 2026 | 87% | -9.7 | on pace or ahead | 31 Dec 2026 | Mar 2027 | dubairealestateiq.com |
| South Lofts by Premier Choice P C I Real Estate Developers L.L.C · Dubai Industrial City (Saih Shuaib 2) | 0% 2 Jul 2026 | 10% | -9.5 | on pace or ahead | 30 Jan 2029 | under 10% built: too early to project | dubairealestateiq.com |
| Bulgari Lighthouse Dubai Dubai Holding Real Estate · Jumeira Bay | 80% 8 Oct 2026 | 89% | -9.3 | on pace or ahead | 27 Mar 2027 | Sept 2027 | dubairealestateiq.com |
| German Supreme Tower 2 Uniestate · Jumeirah Village Circle | 45% 28 Oct 2026 | 54% | -9.3 | on pace or ahead | 22 Jan 2029 | Jan 2030 | dubairealestateiq.com |
| The Meriva Collection (Meriva Gardens / Meriva Signature) Ellington Properties · Dubai Islands | 0.1% 15 Oct 2026 | 9% | -9.2 | on pace or ahead | 31 Dec 2031 | under 10% built: too early to project | dubairealestateiq.com |
| Palm Jebel Ali - Frond A Villas Nakheel · Palm Jebel Ali | 51.3% 10 Nov 2026 | 61% | -9.2 | on pace or ahead | 17 Jan 2028 | Jan 2027 – Sept 2028 | dubairealestateiq.com |
| Address Residences L Dubai Hills Estate Emaar Properties · Hadaeq Sheikh Mohammed Bin Rashid | 26.5% 10 Jun 2026 | 36% | -9.2 | on pace or ahead | 28 Feb 2029 | Aug 2030 – Jun 2031 | dubairealestateiq.com |
| Azizi Riviera 50 Azizi Developments · Al Merkadh | 60.9% 7 Aug 2026 | 70% | -9.2 | on pace or ahead | 13 Mar 2027 | Feb 2027 – Jul 2027 | dubairealestateiq.com |
| The Corner Arabian Gulf Properties · Dubai Land Residence Complex | 37.7% 1 Jun 2026 | 47% | -9.2 | on pace or ahead | 30 Jun 2027 | Dec 2027 | dubairealestateiq.com |
| Golf Hills Emaar Properties · Madinat Al Mataar | 3.7% 23 Jun 2026 | 13% | -9.1 | on pace or ahead | 30 Sept 2029 | under 10% built: too early to project | dubairealestateiq.com |
| Golf Fields Emaar Properties · Madinat Al Mataar | 0% 6 Aug 2026 | 9% | -8.6 | on pace or ahead | 28 Feb 2030 | under 10% built: too early to project | dubairealestateiq.com |
| Vita Grande by Meteora Meteora · Jumeirah Village Circle | 63.8% 25 Feb 2026 | 72% | -8.5 | on pace or ahead | 31 Dec 2026 | May 2027 | dubairealestateiq.com |
| Palace Residences Creek Blue Emaar Properties · Al Khairan First | 40.2% 5 Nov 2026 | 49% | -8.3 | on pace or ahead | 31 Mar 2029 | Mar 2030 – May 2030 | dubairealestateiq.com |
| Serenia District - East Palma Holding · Jumeirah Lakes Towers | 1.1% 23 Jun 2026 | 9% | -8.3 | on pace or ahead | 30 Jun 2030 | under 10% built: too early to project | dubairealestateiq.com |
| Celia Homes Abou Eid · Dubai Land Residence Complex | 40.7% 10 Nov 2026 | 49% | -8.2 | on pace or ahead | 1 Nov 2027 | Mar 2028 | dubairealestateiq.com |
| Greenz by Danube Danube Properties · Dubai Academic City | 0.1% 14 Oct 2026 | 8% | -8.1 | on pace or ahead | 31 Dec 2029 | under 10% built: too early to project | dubairealestateiq.com |
| Naya at District One Meydan / District One · Mohammed Bin Rashid City (District One) | 68.5% 27 Oct 2026 | 76% | -8 | on pace or ahead | 30 Sept 2027 | Mar 2028 – May 2028 | dubairealestateiq.com |
| Palace Residences Hillside A Emaar Properties · Hadaeq Sheikh Mohammed Bin Rashid | 7.9% 5 May 2026 | 16% | -8 | on pace or ahead | 30 Jun 2029 | under 10% built: too early to project | dubairealestateiq.com |
| Liv Lux LIV · Dubai Marina | 87.1% 15 Oct 2026 | 95% | -7.8 | on pace or ahead | 30 Dec 2026 | May 2027 | dubairealestateiq.com |
| Sera 1 Emaar Properties · Dubai Maritime City | 0% 2 Jun 2026 | 7% | -7 | on pace or ahead | 30 Nov 2029 | under 10% built: too early to project | dubairealestateiq.com |
| Sky Harmony by Peace Homes Peace Homes · Jumeirah Village Circle | 12.6% 10 Sept 2026 | 20% | -7 | on pace or ahead | 20 Jan 2029 | Sept 2030 | dubairealestateiq.com |
| Ayami Residence, by Ayat Development Ayat · International City Ph 1 | 0.1% 18 Jun 2026 | 7% | -6.9 | on pace or ahead | 31 Dec 2028 | under 10% built: too early to project | dubairealestateiq.com |
| The Valley - Avena 2 Emaar Properties · Al Yufrah 1 | 42.9% 20 Jul 2026 | 50% | -6.6 | on pace or ahead | 31 Jul 2028 | Mar 2029 – Mar 2029 | dubairealestateiq.com |
| Vibe Arsenal East · Al Satwa | 1.5% 9 Apr 2026 | 8% | -6.6 | on pace or ahead | 31 Aug 2028 | under 10% built: too early to project | dubairealestateiq.com |
| Ventana Residences Zedor Real Estate Development L.L.C · International City Ph 2 & 3 | 6.7% 8 Oct 2026 | 13% | -6.6 | on pace or ahead | 29 Feb 2028 | under 10% built: too early to project | dubairealestateiq.com |
| Grand Polo - Chevalia Estate 2 Emaar Properties · Grand Polo Club, Dubai Investment Park Second | 4.1% 25 Jun 2026 | 11% | -6.4 | on pace or ahead | 30 Jun 2029 | under 10% built: too early to project | dubairealestateiq.com |
| Montiva by Vida Emaar Properties · Dubai Creek Harbour | 5.9% 22 Apr 2026 | 12% | -6.3 | on pace or ahead | 30 Sept 2029 | under 10% built: too early to project | dubairealestateiq.com |
| Sobha Central Sobha Realty · Sheikh Zayed Road, Jebel Ali side | 2.4% 29 Sept 2026 | 9% | -6.3 | on pace or ahead | 31 Dec 2031 | under 10% built: too early to project | dubairealestateiq.com |
| The Valley - Ovelle Emaar Properties · Al Yufrah 1 | 2.4% 16 Jun 2026 | 9% | -6.3 | on pace or ahead | 31 Dec 2029 | under 10% built: too early to project | dubairealestateiq.com |
| Oasis Residences Al Helal Al Zahaby · Madinat Al Mataar | 58.5% 30 Oct 2026 | 65% | -6.3 | on pace or ahead | 1 Jul 2027 | Sept 2027 | dubairealestateiq.com |
| Lumena Alta by Omniyat OMNIYAT · Business Bay | 0% 23 Jul 2026 | 6% | -6.2 | on pace or ahead | 30 Apr 2031 | under 10% built: too early to project | dubairealestateiq.com |
| Courtyard One Golden Light · Madinat Al Mataar | 8.2% 8 May 2026 | 14% | -6.2 | on pace or ahead | 1 Sept 2027 | under 10% built: too early to project | dubairealestateiq.com |
| Mareva 2 the Oasis Emaar Properties · Me'Aisem Second | 1.3% 6 Jul 2026 | 7% | -6 | on pace or ahead | 28 Feb 2030 | under 10% built: too early to project | dubairealestateiq.com |
| The Valley - Avelia Emaar Properties · Al Yufrah 1 | 0.3% 9 Jun 2026 | 6% | -5.9 | on pace or ahead | 31 Dec 2029 | under 10% built: too early to project | dubairealestateiq.com |
| Azizi Riviera 53 Azizi Developments · Al Merkadh | 63.2% 30 Jul 2026 | 69% | -5.9 | on pace or ahead | 13 Mar 2027 | Jan 2027 – May 2027 | dubairealestateiq.com |
| Baystar by Vida Emaar Properties · Dubai Maritime City | 6.3% 16 Jun 2026 | 12% | -5.6 | on pace or ahead | 31 Dec 2029 | under 10% built: too early to project | dubairealestateiq.com |
| Grand Polo - Equiterra 2 Emaar Properties · Grand Polo Club, Dubai Investment Park Second | 1% 29 Apr 2026 | 6% | -5.2 | on pace or ahead | 31 Jul 2029 | under 10% built: too early to project | dubairealestateiq.com |
| Onda by Kasco Kasco · Business Bay | 61.1% 19 Aug 2026 | 66% | -5.2 | on pace or ahead | 31 Aug 2027 | Dec 2027 | dubairealestateiq.com |
| Serro the Heights Emaar Properties · Al Yelayiss 5 | 0.5% 9 Jun 2026 | 6% | -5.1 | on pace or ahead | 31 Mar 2030 | under 10% built: too early to project | dubairealestateiq.com |
| Creek Haven Emaar Properties · Al Khairan First | 0.9% 16 Jun 2026 | 6% | -5 | on pace or ahead | 31 Mar 2030 | under 10% built: too early to project | dubairealestateiq.com |
| Lyvia by Palace Emaar Properties · Al Khairan First | 4.8% 17 Mar 2026 | 10% | -4.8 | on pace or ahead | 31 Jul 2029 | under 10% built: too early to project | dubairealestateiq.com |
| Boulevard Park 2 Wasl · Jabal Ali First | 0% 29 Jun 2026 | 5% | -4.6 | on pace or ahead | 30 Nov 2029 | under 10% built: too early to project | dubairealestateiq.com |
| The Valley - Avena Emaar Properties · Al Yufrah 1 | 54.4% 5 Nov 2026 | 59% | -4.5 | on pace or ahead | 30 Jun 2028 | Oct 2028 – Oct 2028 | dubairealestateiq.com |
| Creek Bay Emaar Properties · Al Khairan First | 0.6% 16 Jun 2026 | 5% | -4.5 | on pace or ahead | 30 Apr 2030 | under 10% built: too early to project | dubairealestateiq.com |
| 31 Above by Beyond Beyond Developments · Dubai Maritime City | 0.5% 18 Jun 2026 | 5% | -4.5 | on pace or ahead | 30 Dec 2028 | under 10% built: too early to project | dubairealestateiq.com |
| Grand Polo - Equiterra Emaar Properties · Grand Polo Club, Dubai Investment Park Second | 0.8% 14 May 2026 | 5% | -4.4 | on pace or ahead | 31 Aug 2029 | under 10% built: too early to project | dubairealestateiq.com |
| Sunset Bay 2 by Imtiaz Imtiaz Developments · Dubai Islands | 80.9% 4 Nov 2026 | 85% | -4.3 | on pace or ahead | 20 Feb 2027 | Mar 2027 – Mar 2027 | dubairealestateiq.com |
| Boulevard Park 1 Wasl · Jabal Ali First | 0% 29 Jun 2026 | 4% | -4.1 | on pace or ahead | 30 Apr 2030 | under 10% built: too early to project | dubairealestateiq.com |
| Sports View Residence 2 by Al Helal Al Zahaby Al Helal Al Zahaby · International City Ph 2 & 3 | 13.4% 12 Aug 2026 | 18% | -4.1 | on pace or ahead | 10 Nov 2029 | Jan 2031 | dubairealestateiq.com |
| Valia Emaar Properties · Dubai Creek Harbour | 0% 6 Aug 2026 | 4% | -3.9 | on pace or ahead | 31 Aug 2030 | under 10% built: too early to project | dubairealestateiq.com |
| Enre Residence Imtiaz Developments · Dubai South | 24.2% 30 Oct 2026 | 28% | -3.9 | on pace or ahead | 15 Aug 2028 | Dec 2028 – Jan 2029 | dubairealestateiq.com |
| Mareva the Oasis Emaar Properties · Me'Aisem Second | 2.1% 16 Jun 2026 | 6% | -3.9 | on pace or ahead | 28 Feb 2030 | under 10% built: too early to project | dubairealestateiq.com |
| Lateral One Grand Signature · Dubai Land Residence Complex | 78.9% 28 Oct 2026 | 83% | -3.7 | on pace or ahead | 31 Dec 2026 | Jan 2027 | dubairealestateiq.com |
| The Valley - Velora 2 Emaar Properties · Al Yufrah 1 | 40.3% 6 Jul 2026 | 44% | -3.6 | on pace or ahead | 31 Jul 2028 | Nov 2028 – Jun 2029 | dubairealestateiq.com |
| Hillsedge Emaar Properties · Hadaeq Sheikh Mohammed Bin Rashid | 25.6% 6 Jun 2026 | 29% | -3.6 | on pace or ahead | 31 Jan 2029 | Aug 2029 – Nov 2030 | dubairealestateiq.com |
| DAMAC Islands 2 - Antigua 1 DAMAC Properties · Al Yelayiss 1 | 0.3% 16 Sept 2026 | 4% | -3.5 | on pace or ahead | 31 Dec 2030 | under 10% built: too early to project | dubairealestateiq.com |
| Palace Residences Dubai Hills Estate Emaar Properties · Dubai Hills Estate | 50.7% 16 Jun 2026 | 54% | -3.4 | on pace or ahead | 30 Apr 2028 | Aug 2028 – Nov 2028 | dubairealestateiq.com |
| Soma Residences Origami · Palm Deira | 0% 16 Jul 2026 | 3% | -3.4 | on pace or ahead | 1 Sept 2028 | under 10% built: too early to project | dubairealestateiq.com |
| Azizi David Azizi Developments · Al Jadaf | 2% 24 Mar 2026 | 5% | -3.1 | on pace or ahead | 30 Sept 2028 | under 10% built: too early to project | dubairealestateiq.com |
Method
Time elapsed = (inspection date minus construction start on the register) divided by (registered completion date minus construction start). When no start date is printed, the registration date is used.
Gap = % built at the inspection minus % of time elapsed at the same date, in percentage points. Behind = a gap below -10 points. Registered date passed = the inspection is after the completion date on the register and the project is not at 100%.
Projection, only for 10% to 99% built: the remaining % divided by the observed pace, where the pace is % built per day since the start date, since the registration date and between the last two inspections we hold (when it rose). The range runs from the earliest to the latest of these estimates.
Limits: Construction does not move in a straight line (a slow start, faster structure, slow finishing), so a straight line from an early reading tends to give later dates than the work will need, and a late reading can give earlier ones. The % built is the DLD inspection figure, not ours.
Source: the Dubai Land Department project register as mirrored per project with its inspection history, read by our register job; 929 DLD records, 28 with two or more dated inspections.