Home / Dubai / Construction pace against the registered date

Construction pace against the registered date

For Dubai projects with DLD inspection readings: % built against the share of time elapsed to the completion date on the register, and the completion range the observed pace points to. A projection, not a promise.

Updated 23 Nov 2026

A projection from the pace on the register, not a promise, and not a finding about the developer.

815projects compared (DLD % built and dates on the register)
82.8%more than 10 points behind the time elapsed (95% interval 80.1 to 85.3%)
-27.1median gap in points, % built minus % of time elapsed (95% interval -29.5 to -26)
426projects with a projected range (10% to 99% built)
87.1%of them projected after the registered date (95% interval 83.6 to 89.9%)
≤-6090-50115-40162-30178-20130-10900291012207301401
Projects by gap between % built and % of time elapsed, in 10-point bins
Show as a table
Gap (points)Projects
-60 … -5090
-50 … -40115
-40 … -30162
-30 … -20178
-20 … -10130
-10 … 090
0 … 1029
10 … 2012
20 … 307
30 … 401
40 … 501

Projects

Developer: vision-developments · All

5 projects, page 1
Project% built (inspection)Time elapsedGap (points)PaceRegistered completionProjected rangeRegister
Verde by Vision
Vision Developments · Dubai Sports City
12%
12 Oct 2026
51%-38.8behind30 Sept 2027Feb 2034dubairealestateiq.com
Vista by Vision
Vision Developments · Dubai Production City
12.2%
12 Oct 2026
50%-38.1behind1 Sept 2027Mar 2033dubairealestateiq.com
Reem by Vision
Vision Developments · Wadi Al Safa 2
70.4%
13 Oct 2026
87%-16.7behind31 Dec 2026May 2027dubairealestateiq.com
Soul by Vision
Vision Developments · Dubai Production City
77%
12 Oct 2026
87%-9.7on pace or ahead31 Dec 2026Mar 2027dubairealestateiq.com
Sera Gardens by Vision
Vision Developments · Dubai Production City
0%
7 Apr 2026
--not comparable1 Apr 2028under 10% built: too early to projectdubairealestateiq.com

Method

Time elapsed = (inspection date minus construction start on the register) divided by (registered completion date minus construction start). When no start date is printed, the registration date is used.

Gap = % built at the inspection minus % of time elapsed at the same date, in percentage points. Behind = a gap below -10 points. Registered date passed = the inspection is after the completion date on the register and the project is not at 100%.

Projection, only for 10% to 99% built: the remaining % divided by the observed pace, where the pace is % built per day since the start date, since the registration date and between the last two inspections we hold (when it rose). The range runs from the earliest to the latest of these estimates.

Limits: Construction does not move in a straight line (a slow start, faster structure, slow finishing), so a straight line from an early reading tends to give later dates than the work will need, and a late reading can give earlier ones. The % built is the DLD inspection figure, not ours.

Source: the Dubai Land Department project register as mirrored per project with its inspection history, read by our register job; 929 DLD records, 28 with two or more dated inspections.

Files: /data/n35a/pace.json · /open/n35a-build.py · /registers/changes/