Home / Dubai / Construction pace against the registered date

Construction pace against the registered date

For Dubai projects with DLD inspection readings: % built against the share of time elapsed to the completion date on the register, and the completion range the observed pace points to. A projection, not a promise.

Updated 23 Nov 2026

A projection from the pace on the register, not a promise, and not a finding about the developer.

815projects compared (DLD % built and dates on the register)
82.8%more than 10 points behind the time elapsed (95% interval 80.1 to 85.3%)
-27.1median gap in points, % built minus % of time elapsed (95% interval -29.5 to -26)
426projects with a projected range (10% to 99% built)
87.1%of them projected after the registered date (95% interval 83.6 to 89.9%)
≤-6090-50115-40162-30178-20130-10900291012207301401
Projects by gap between % built and % of time elapsed, in 10-point bins
Show as a table
Gap (points)Projects
-60 … -5090
-50 … -40115
-40 … -30162
-30 … -20178
-20 … -10130
-10 … 090
0 … 1029
10 … 2012
20 … 307
30 … 401
40 … 501

Projects

101 projects, page 1
Project% built (inspection)Time elapsedGap (points)PaceRegistered completionProjected rangeRegister
Eltiera Views
Ellington Properties · Jumeirah Islands
0%
5 Dec 2025
--not comparable31 Dec 2029under 10% built: too early to projectdubairealestateiq.com
The Brooks at Sobha Sanctuary
Sobha Realty · The Valley
0%
15 Jul 2026
--not comparable31 Aug 2030under 10% built: too early to projectdubairealestateiq.com
Golf Vale
Emaar Properties · Emaar South / Expo City
0%
24 Feb 2026
--not comparable31 Mar 2030under 10% built: too early to projectdubairealestateiq.com
Bayz 101 by Danube
Danube Properties · Business Bay
10%
12 Aug 2026
--not comparable-no projectiondubairealestateiq.com
Club Drive
Emaar Properties · Dubai Hills Estate
100%
19 Oct 2026
--not comparable-no projectiondubairealestateiq.com
Kensington Gardens (Greenwood)
LEOS Developments · Greenwood, International City Phase 2 (Al Warsan 4)
0%
17 Feb 2025
--not comparable27 Sept 2027under 10% built: too early to projectdubairealestateiq.com
Artistry One Residences
Select Group · Dubai Design District (d3)
0%
14 Jan 2026
--not comparable9 Feb 2029under 10% built: too early to projectdubairealestateiq.com
Nine Collective
Wasl · Wasl 1, Al Kifaf (Zabeel Park)
-
-
--not comparable-no projectiondubairealestateiq.com
Karl Lagerfeld Villas by Taraf
Taraf Development L.L.C · Majan / Wadi Al Safa 3 (marketed as Meydan, Nad Al Sheba)
10.5%
23 Sept 2026
--not comparable-no projectiondubairealestateiq.com
Arancia Yards by Beyond
Beyond Developments · The Yards, City of Arabia (Wadi Al Safa 4, Dubailand)
0%
18 May 2026
--not comparable30 Oct 2028under 10% built: too early to projectdubairealestateiq.com
Cello Residences
Taraf · Jumeirah Village Circle (JVC)
39%
4 Sept 2026
--not comparable-no projectiondubairealestateiq.com
Lagoon Views (DAMAC Lagoons)
DAMAC Properties · DAMAC Lagoons
63.9%
3 Nov 2026
--not comparable-no projectiondubairealestateiq.com
Six Senses Residences Dubai Marina
Select Group · Dubai Marina
26.7%
25 Sept 2026
--not comparable-no projectiondubairealestateiq.com
Binghatti Wraith
Binghatti Developers · Al Jaddaf
0%
20 May 2026
--not comparable30 Dec 2027under 10% built: too early to projectdubairealestateiq.com
Binghatti Starfall
Binghatti Developers · Al Jaddaf
0%
20 May 2026
--not comparable30 Sept 2028under 10% built: too early to projectdubairealestateiq.com
Portside Square
Ellington Properties · Mina Rashid
0%
12 Jan 2026
--not comparable31 Dec 2029under 10% built: too early to projectdubairealestateiq.com
Raw District
Imtiaz Developments · Downtown Jebel Ali, Sheikh Zayed Road
0%
9 Jun 2026
--not comparable15 Dec 2029under 10% built: too early to projectdubairealestateiq.com
Oceanz by Danube
Danube Properties · Dubai Maritime City
50%
25 Aug 2026
--not comparable-no projectiondubairealestateiq.com
Fashionz by Danube
Danube Properties · Jumeirah Village Triangle
40%
10 Sept 2026
--not comparable-no projectiondubairealestateiq.com
Diamondz by Danube
Danube Properties · Jumeirah Lake Towers
18.5%
27 Oct 2026
--not comparable-no projectiondubairealestateiq.com
Samana Portside
Samana Developers · Downtown Jebel Ali
0%
7 Jul 2026
--not comparable30 Jun 2029under 10% built: too early to projectdubairealestateiq.com
SAMANA Lake Views 2
SAMANA Developers · Dubai Production City
12%
28 Oct 2026
--not comparable-no projectiondubairealestateiq.com
Beach Walk III by Imtiaz
Imtiaz Developments · Dubai Islands
100%
4 Nov 2026
--not comparable14 Jun 2026no projectiondubairealestateiq.com
Binghatti Spectre
Binghatti Developers · Al Jaddaf, near DEWA headquarters
0%
9 Feb 2026
--not comparable31 Dec 2028under 10% built: too early to projectdubairealestateiq.com
ELO (DAMAC Hills 2)
DAMAC Properties · DAMAC Hills 2
31.5%
30 Oct 2026
--not comparable-no projectiondubairealestateiq.com
Evergreens (DAMAC Hills 2)
DAMAC Properties · DAMAC Hills 2
48.1%
30 Oct 2026
--not comparable-no projectiondubairealestateiq.com
Golf Gate 2 (DAMAC Hills)
DAMAC Properties · DAMAC Hills
80.4%
20 Jul 2026
--not comparable-no projectiondubairealestateiq.com
DAMAC Casa
DAMAC Properties · Al Sufouh
33.6%
18 Aug 2026
--not comparable-no projectiondubairealestateiq.com
DAMAC Bay 2 by Cavalli
DAMAC Properties · Dubai Harbour
30.3%
15 Jul 2026
--not comparable-no projectiondubairealestateiq.com
Sobha Skyparks
Sobha Realty · Business Bay
0%
23 Oct 2025
--not comparable31 Dec 2032under 10% built: too early to projectdubairealestateiq.com
Artistry Two Residences
Select Group · Zaabeel Second
0%
14 Jan 2026
--not comparable9 Feb 2029under 10% built: too early to projectdubairealestateiq.com
SAMANA Greenfield 2
SAMANA Developers · Al Warsan (International City Ph 2 & 3)
0%
18 May 2026
--not comparable31 Aug 2029under 10% built: too early to projectdubairealestateiq.com
SAMANA Ivy Gardens
SAMANA Developers · Dubai Land Residence Complex (DLRC)
40.7%
1 Oct 2026
--not comparable-no projectiondubairealestateiq.com
SAMANA South Haven
SAMANA Developers · Dubai South
0%
4 May 2026
--not comparable31 Dec 2028under 10% built: too early to projectdubairealestateiq.com
SAMANA South Haven 2
SAMANA Developers · Dubai South
0%
7 Jul 2026
--not comparable30 Jun 2029under 10% built: too early to projectdubairealestateiq.com
Golf Edge
Emaar Properties · Madinat Al Mataar
0%
5 Nov 2024
--not comparable28 Feb 2029under 10% built: too early to projectdubairealestateiq.com
Grand Polo - Equestra
Emaar Properties · Grand Polo Club, Dubai Investment Park Second
1%
4 May 2026
--not comparable31 Aug 2029under 10% built: too early to projectdubairealestateiq.com
Grove Ridge
Emaar Properties · Madinat Al Mataar
0%
4 Nov 2025
--not comparable30 Sept 2029under 10% built: too early to projectdubairealestateiq.com
Vista Ridge
Emaar Properties · Madinat Al Mataar
0%
4 Nov 2025
--not comparable30 Sept 2029under 10% built: too early to projectdubairealestateiq.com
Terra Woods
Emaar Properties · Madinat Al Mataar
0%
28 Jan 2026
--not comparable31 Mar 2030under 10% built: too early to projectdubairealestateiq.com
Fior 1
Emaar Properties · Dubai Maritime City
0%
11 Dec 2025
--not comparable31 Jul 2030under 10% built: too early to projectdubairealestateiq.com
Golf Trails
Emaar Properties · Madinat Al Mataar
0%
1 Jul 2026
--not comparable31 Oct 2030under 10% built: too early to projectdubairealestateiq.com
Palace by the Beach
Emaar Properties · Dubai Marina
0%
12 Jan 2026
--not comparable30 Nov 2031under 10% built: too early to projectdubairealestateiq.com
Azizi Abraham
Azizi Developments · Jabal Ali Industrial Second
2%
24 Mar 2026
--not comparable4 Aug 2027under 10% built: too early to projectdubairealestateiq.com
Azizi Gabriel
Azizi Developments · Jabal Ali Industrial Second
0%
17 Nov 2025
--not comparable4 Jul 2028under 10% built: too early to projectdubairealestateiq.com
Azizi Rose
Azizi Developments · Jabal Ali Industrial Second
0%
16 Feb 2026
--not comparable4 Jul 2028under 10% built: too early to projectdubairealestateiq.com
Raw District 2 by Imtiaz
Imtiaz Developments · Jabal Ali Industrial Second
0%
8 Jul 2026
--not comparable1 Dec 2029under 10% built: too early to projectdubairealestateiq.com
Bay Estate
Nakheel · Palm Deira
0%
20 Aug 2026
--not comparable15 Aug 2030under 10% built: too early to projectdubairealestateiq.com
Palm Central Private Residences - Frond N
Nakheel · Palm Jabal Ali
0%
27 Feb 2026
--not comparable13 Dec 2030under 10% built: too early to projectdubairealestateiq.com
The Greens at Sobha Sanctuary
Sobha Realty · Al Yufrah 1
0%
15 Jul 2026
--not comparable31 Aug 2030under 10% built: too early to projectdubairealestateiq.com
The Grove at Sobha Sanctuary
Sobha Realty · Al Yufrah 1
0%
20 May 2026
--not comparable31 Aug 2030under 10% built: too early to projectdubairealestateiq.com
The Woods
Sobha Realty · Al Yufrah 1
0%
21 May 2026
--not comparable30 Dec 2030under 10% built: too early to projectdubairealestateiq.com
Arancia Yards 2 by Beyond
Beyond Developments · City of Arabia
0%
9 Jul 2026
--not comparable30 Jan 2029under 10% built: too early to projectdubairealestateiq.com
Hado by Beyond
Beyond Developments · Palm Deira
0%
16 Jun 2026
--not comparable30 Jun 2029under 10% built: too early to projectdubairealestateiq.com
Cedarwood Estates
Wasl · Dubai Production City
0%
8 Jan 2026
--not comparable4 Oct 2028under 10% built: too early to projectdubairealestateiq.com
Pinewood Estate Homes
Wasl · Dubai Production City
0.3%
11 Mar 2026
--not comparable17 Nov 2028under 10% built: too early to projectdubairealestateiq.com
Cedarwood Estates-South
Wasl · Dubai Production City
0%
14 May 2026
--not comparable31 Jan 2029under 10% built: too early to projectdubairealestateiq.com
Avenue Park Towers II
Wasl · Al Kifaf
0%
8 Jun 2026
--not comparable6 Mar 2030under 10% built: too early to projectdubairealestateiq.com
1wood Residence 2
Object 1 · Jumeirah Village Circle
0%
3 Mar 2026
--not comparable20 Oct 2027under 10% built: too early to projectdubairealestateiq.com
Sky Level 1
Object 1 · Jumeirah Village Circle
0%
13 May 2026
--not comparable28 Feb 2029under 10% built: too early to projectdubairealestateiq.com

Next page

Method

Time elapsed = (inspection date minus construction start on the register) divided by (registered completion date minus construction start). When no start date is printed, the registration date is used.

Gap = % built at the inspection minus % of time elapsed at the same date, in percentage points. Behind = a gap below -10 points. Registered date passed = the inspection is after the completion date on the register and the project is not at 100%.

Projection, only for 10% to 99% built: the remaining % divided by the observed pace, where the pace is % built per day since the start date, since the registration date and between the last two inspections we hold (when it rose). The range runs from the earliest to the latest of these estimates.

Limits: Construction does not move in a straight line (a slow start, faster structure, slow finishing), so a straight line from an early reading tends to give later dates than the work will need, and a late reading can give earlier ones. The % built is the DLD inspection figure, not ours.

Source: the Dubai Land Department project register as mirrored per project with its inspection history, read by our register job; 929 DLD records, 28 with two or more dated inspections.

Files: /data/n35a/pace.json · /open/n35a-build.py · /registers/changes/