Construction pace against the registered date
For Dubai projects with DLD inspection readings: % built against the share of time elapsed to the completion date on the register, and the completion range the observed pace points to. A projection, not a promise.
Updated 23 Nov 2026
A projection from the pace on the register, not a promise, and not a finding about the developer.
Show as a table
| Gap (points) | Projects |
|---|---|
| -60 … -50 | 90 |
| -50 … -40 | 115 |
| -40 … -30 | 162 |
| -30 … -20 | 178 |
| -20 … -10 | 130 |
| -10 … 0 | 90 |
| 0 … 10 | 29 |
| 10 … 20 | 12 |
| 20 … 30 | 7 |
| 30 … 40 | 1 |
| 40 … 50 | 1 |
Projects
| Project | % built (inspection) | Time elapsed | Gap (points) | Pace | Registered completion | Projected range | Register |
|---|---|---|---|---|---|---|---|
| Eltiera Views Ellington Properties · Jumeirah Islands | 0% 5 Dec 2025 | - | - | not comparable | 31 Dec 2029 | under 10% built: too early to project | dubairealestateiq.com |
| The Brooks at Sobha Sanctuary Sobha Realty · The Valley | 0% 15 Jul 2026 | - | - | not comparable | 31 Aug 2030 | under 10% built: too early to project | dubairealestateiq.com |
| Golf Vale Emaar Properties · Emaar South / Expo City | 0% 24 Feb 2026 | - | - | not comparable | 31 Mar 2030 | under 10% built: too early to project | dubairealestateiq.com |
| Bayz 101 by Danube Danube Properties · Business Bay | 10% 12 Aug 2026 | - | - | not comparable | - | no projection | dubairealestateiq.com |
| Club Drive Emaar Properties · Dubai Hills Estate | 100% 19 Oct 2026 | - | - | not comparable | - | no projection | dubairealestateiq.com |
| Kensington Gardens (Greenwood) LEOS Developments · Greenwood, International City Phase 2 (Al Warsan 4) | 0% 17 Feb 2025 | - | - | not comparable | 27 Sept 2027 | under 10% built: too early to project | dubairealestateiq.com |
| Artistry One Residences Select Group · Dubai Design District (d3) | 0% 14 Jan 2026 | - | - | not comparable | 9 Feb 2029 | under 10% built: too early to project | dubairealestateiq.com |
| Nine Collective Wasl · Wasl 1, Al Kifaf (Zabeel Park) | - - | - | - | not comparable | - | no projection | dubairealestateiq.com |
| Karl Lagerfeld Villas by Taraf Taraf Development L.L.C · Majan / Wadi Al Safa 3 (marketed as Meydan, Nad Al Sheba) | 10.5% 23 Sept 2026 | - | - | not comparable | - | no projection | dubairealestateiq.com |
| Arancia Yards by Beyond Beyond Developments · The Yards, City of Arabia (Wadi Al Safa 4, Dubailand) | 0% 18 May 2026 | - | - | not comparable | 30 Oct 2028 | under 10% built: too early to project | dubairealestateiq.com |
| Cello Residences Taraf · Jumeirah Village Circle (JVC) | 39% 4 Sept 2026 | - | - | not comparable | - | no projection | dubairealestateiq.com |
| Lagoon Views (DAMAC Lagoons) DAMAC Properties · DAMAC Lagoons | 63.9% 3 Nov 2026 | - | - | not comparable | - | no projection | dubairealestateiq.com |
| Six Senses Residences Dubai Marina Select Group · Dubai Marina | 26.7% 25 Sept 2026 | - | - | not comparable | - | no projection | dubairealestateiq.com |
| Binghatti Wraith Binghatti Developers · Al Jaddaf | 0% 20 May 2026 | - | - | not comparable | 30 Dec 2027 | under 10% built: too early to project | dubairealestateiq.com |
| Binghatti Starfall Binghatti Developers · Al Jaddaf | 0% 20 May 2026 | - | - | not comparable | 30 Sept 2028 | under 10% built: too early to project | dubairealestateiq.com |
| Portside Square Ellington Properties · Mina Rashid | 0% 12 Jan 2026 | - | - | not comparable | 31 Dec 2029 | under 10% built: too early to project | dubairealestateiq.com |
| Raw District Imtiaz Developments · Downtown Jebel Ali, Sheikh Zayed Road | 0% 9 Jun 2026 | - | - | not comparable | 15 Dec 2029 | under 10% built: too early to project | dubairealestateiq.com |
| Oceanz by Danube Danube Properties · Dubai Maritime City | 50% 25 Aug 2026 | - | - | not comparable | - | no projection | dubairealestateiq.com |
| Fashionz by Danube Danube Properties · Jumeirah Village Triangle | 40% 10 Sept 2026 | - | - | not comparable | - | no projection | dubairealestateiq.com |
| Diamondz by Danube Danube Properties · Jumeirah Lake Towers | 18.5% 27 Oct 2026 | - | - | not comparable | - | no projection | dubairealestateiq.com |
| Samana Portside Samana Developers · Downtown Jebel Ali | 0% 7 Jul 2026 | - | - | not comparable | 30 Jun 2029 | under 10% built: too early to project | dubairealestateiq.com |
| SAMANA Lake Views 2 SAMANA Developers · Dubai Production City | 12% 28 Oct 2026 | - | - | not comparable | - | no projection | dubairealestateiq.com |
| Beach Walk III by Imtiaz Imtiaz Developments · Dubai Islands | 100% 4 Nov 2026 | - | - | not comparable | 14 Jun 2026 | no projection | dubairealestateiq.com |
| Binghatti Spectre Binghatti Developers · Al Jaddaf, near DEWA headquarters | 0% 9 Feb 2026 | - | - | not comparable | 31 Dec 2028 | under 10% built: too early to project | dubairealestateiq.com |
| ELO (DAMAC Hills 2) DAMAC Properties · DAMAC Hills 2 | 31.5% 30 Oct 2026 | - | - | not comparable | - | no projection | dubairealestateiq.com |
| Evergreens (DAMAC Hills 2) DAMAC Properties · DAMAC Hills 2 | 48.1% 30 Oct 2026 | - | - | not comparable | - | no projection | dubairealestateiq.com |
| Golf Gate 2 (DAMAC Hills) DAMAC Properties · DAMAC Hills | 80.4% 20 Jul 2026 | - | - | not comparable | - | no projection | dubairealestateiq.com |
| DAMAC Casa DAMAC Properties · Al Sufouh | 33.6% 18 Aug 2026 | - | - | not comparable | - | no projection | dubairealestateiq.com |
| DAMAC Bay 2 by Cavalli DAMAC Properties · Dubai Harbour | 30.3% 15 Jul 2026 | - | - | not comparable | - | no projection | dubairealestateiq.com |
| Sobha Skyparks Sobha Realty · Business Bay | 0% 23 Oct 2025 | - | - | not comparable | 31 Dec 2032 | under 10% built: too early to project | dubairealestateiq.com |
| Artistry Two Residences Select Group · Zaabeel Second | 0% 14 Jan 2026 | - | - | not comparable | 9 Feb 2029 | under 10% built: too early to project | dubairealestateiq.com |
| SAMANA Greenfield 2 SAMANA Developers · Al Warsan (International City Ph 2 & 3) | 0% 18 May 2026 | - | - | not comparable | 31 Aug 2029 | under 10% built: too early to project | dubairealestateiq.com |
| SAMANA Ivy Gardens SAMANA Developers · Dubai Land Residence Complex (DLRC) | 40.7% 1 Oct 2026 | - | - | not comparable | - | no projection | dubairealestateiq.com |
| SAMANA South Haven SAMANA Developers · Dubai South | 0% 4 May 2026 | - | - | not comparable | 31 Dec 2028 | under 10% built: too early to project | dubairealestateiq.com |
| SAMANA South Haven 2 SAMANA Developers · Dubai South | 0% 7 Jul 2026 | - | - | not comparable | 30 Jun 2029 | under 10% built: too early to project | dubairealestateiq.com |
| Golf Edge Emaar Properties · Madinat Al Mataar | 0% 5 Nov 2024 | - | - | not comparable | 28 Feb 2029 | under 10% built: too early to project | dubairealestateiq.com |
| Grand Polo - Equestra Emaar Properties · Grand Polo Club, Dubai Investment Park Second | 1% 4 May 2026 | - | - | not comparable | 31 Aug 2029 | under 10% built: too early to project | dubairealestateiq.com |
| Grove Ridge Emaar Properties · Madinat Al Mataar | 0% 4 Nov 2025 | - | - | not comparable | 30 Sept 2029 | under 10% built: too early to project | dubairealestateiq.com |
| Vista Ridge Emaar Properties · Madinat Al Mataar | 0% 4 Nov 2025 | - | - | not comparable | 30 Sept 2029 | under 10% built: too early to project | dubairealestateiq.com |
| Terra Woods Emaar Properties · Madinat Al Mataar | 0% 28 Jan 2026 | - | - | not comparable | 31 Mar 2030 | under 10% built: too early to project | dubairealestateiq.com |
| Fior 1 Emaar Properties · Dubai Maritime City | 0% 11 Dec 2025 | - | - | not comparable | 31 Jul 2030 | under 10% built: too early to project | dubairealestateiq.com |
| Golf Trails Emaar Properties · Madinat Al Mataar | 0% 1 Jul 2026 | - | - | not comparable | 31 Oct 2030 | under 10% built: too early to project | dubairealestateiq.com |
| Palace by the Beach Emaar Properties · Dubai Marina | 0% 12 Jan 2026 | - | - | not comparable | 30 Nov 2031 | under 10% built: too early to project | dubairealestateiq.com |
| Azizi Abraham Azizi Developments · Jabal Ali Industrial Second | 2% 24 Mar 2026 | - | - | not comparable | 4 Aug 2027 | under 10% built: too early to project | dubairealestateiq.com |
| Azizi Gabriel Azizi Developments · Jabal Ali Industrial Second | 0% 17 Nov 2025 | - | - | not comparable | 4 Jul 2028 | under 10% built: too early to project | dubairealestateiq.com |
| Azizi Rose Azizi Developments · Jabal Ali Industrial Second | 0% 16 Feb 2026 | - | - | not comparable | 4 Jul 2028 | under 10% built: too early to project | dubairealestateiq.com |
| Raw District 2 by Imtiaz Imtiaz Developments · Jabal Ali Industrial Second | 0% 8 Jul 2026 | - | - | not comparable | 1 Dec 2029 | under 10% built: too early to project | dubairealestateiq.com |
| Bay Estate Nakheel · Palm Deira | 0% 20 Aug 2026 | - | - | not comparable | 15 Aug 2030 | under 10% built: too early to project | dubairealestateiq.com |
| Palm Central Private Residences - Frond N Nakheel · Palm Jabal Ali | 0% 27 Feb 2026 | - | - | not comparable | 13 Dec 2030 | under 10% built: too early to project | dubairealestateiq.com |
| The Greens at Sobha Sanctuary Sobha Realty · Al Yufrah 1 | 0% 15 Jul 2026 | - | - | not comparable | 31 Aug 2030 | under 10% built: too early to project | dubairealestateiq.com |
| The Grove at Sobha Sanctuary Sobha Realty · Al Yufrah 1 | 0% 20 May 2026 | - | - | not comparable | 31 Aug 2030 | under 10% built: too early to project | dubairealestateiq.com |
| The Woods Sobha Realty · Al Yufrah 1 | 0% 21 May 2026 | - | - | not comparable | 30 Dec 2030 | under 10% built: too early to project | dubairealestateiq.com |
| Arancia Yards 2 by Beyond Beyond Developments · City of Arabia | 0% 9 Jul 2026 | - | - | not comparable | 30 Jan 2029 | under 10% built: too early to project | dubairealestateiq.com |
| Hado by Beyond Beyond Developments · Palm Deira | 0% 16 Jun 2026 | - | - | not comparable | 30 Jun 2029 | under 10% built: too early to project | dubairealestateiq.com |
| Cedarwood Estates Wasl · Dubai Production City | 0% 8 Jan 2026 | - | - | not comparable | 4 Oct 2028 | under 10% built: too early to project | dubairealestateiq.com |
| Pinewood Estate Homes Wasl · Dubai Production City | 0.3% 11 Mar 2026 | - | - | not comparable | 17 Nov 2028 | under 10% built: too early to project | dubairealestateiq.com |
| Cedarwood Estates-South Wasl · Dubai Production City | 0% 14 May 2026 | - | - | not comparable | 31 Jan 2029 | under 10% built: too early to project | dubairealestateiq.com |
| Avenue Park Towers II Wasl · Al Kifaf | 0% 8 Jun 2026 | - | - | not comparable | 6 Mar 2030 | under 10% built: too early to project | dubairealestateiq.com |
| 1wood Residence 2 Object 1 · Jumeirah Village Circle | 0% 3 Mar 2026 | - | - | not comparable | 20 Oct 2027 | under 10% built: too early to project | dubairealestateiq.com |
| Sky Level 1 Object 1 · Jumeirah Village Circle | 0% 13 May 2026 | - | - | not comparable | 28 Feb 2029 | under 10% built: too early to project | dubairealestateiq.com |
Method
Time elapsed = (inspection date minus construction start on the register) divided by (registered completion date minus construction start). When no start date is printed, the registration date is used.
Gap = % built at the inspection minus % of time elapsed at the same date, in percentage points. Behind = a gap below -10 points. Registered date passed = the inspection is after the completion date on the register and the project is not at 100%.
Projection, only for 10% to 99% built: the remaining % divided by the observed pace, where the pace is % built per day since the start date, since the registration date and between the last two inspections we hold (when it rose). The range runs from the earliest to the latest of these estimates.
Limits: Construction does not move in a straight line (a slow start, faster structure, slow finishing), so a straight line from an early reading tends to give later dates than the work will need, and a late reading can give earlier ones. The % built is the DLD inspection figure, not ours.
Source: the Dubai Land Department project register as mirrored per project with its inspection history, read by our register job; 929 DLD records, 28 with two or more dated inspections.