Home / Dubai / Construction pace against the registered date
Construction pace against the registered date
For Dubai projects with DLD inspection readings: % built against the share of time elapsed to the completion date on the register, and the completion range the observed pace points to. A projection, not a promise.
Updated 23 Nov 2026
A projection from the pace on the register, not a promise, and not a finding about the developer.
Show as a table
| Gap (points) | Projects |
|---|---|
| -60 … -50 | 90 |
| -50 … -40 | 115 |
| -40 … -30 | 162 |
| -30 … -20 | 178 |
| -20 … -10 | 130 |
| -10 … 0 | 90 |
| 0 … 10 | 29 |
| 10 … 20 | 12 |
| 20 … 30 | 7 |
| 30 … 40 | 1 |
| 40 … 50 | 1 |
Projects
Developer: ellington-properties · All
| Project | % built (inspection) | Time elapsed | Gap (points) | Pace | Registered completion | Projected range | Register |
|---|---|---|---|---|---|---|---|
| Hillmont Residences by Ellington Ellington Properties · Jumeirah Village Circle | 26.3% 22 Jul 2026 | 83% | -56.9 | behind | 31 Dec 2026 | Mar 2032 – Sept 2032 | dubairealestateiq.com |
| Mercer House Ellington Properties · Uptown Dubai, Jumeirah Lake Towers | 18.1% 7 Aug 2026 | 71% | -53.2 | behind | 31 Jul 2027 | Apr 2036 – Aug 2037 | dubairealestateiq.com |
| Claydon House by Ellington Ellington Properties · Bukadra | 15.7% 6 Aug 2026 | 61% | -45.6 | behind | 31 Dec 2027 | Dec 2035 – Jul 2038 | dubairealestateiq.com |
| The Watercrest Ellington Properties · Mohammed Bin Rashid City | 2.2% 24 Jul 2026 | 47% | -44.5 | behind | 31 Mar 2028 | under 10% built: too early to project | dubairealestateiq.com |
| One River Point Ellington Properties · Business Bay | 35.4% 21 Jul 2026 | 76% | -40.2 | behind | 9 Jun 2027 | Jan 2031 – Jul 2031 | dubairealestateiq.com |
| Belmore Residences Ellington Properties · Bukadra | 6.5% 6 Aug 2026 | 42% | -35 | behind | 31 Dec 2027 | under 10% built: too early to project | dubairealestateiq.com |
| The Hillgate Ellington Properties · Dubai Silicon Oasis | 3.1% 4 Jun 2026 | 38% | -34.6 | behind | 30 Jun 2028 | under 10% built: too early to project | dubairealestateiq.com |
| Belgravia Gardens Ellington Properties · Wadi Al Safa 2 | 3.1% 4 Jun 2026 | 37% | -33.5 | behind | 30 Sept 2028 | under 10% built: too early to project | dubairealestateiq.com |
| Eltiera Heights Ellington Properties · Jumeirah Islands | 3% 20 Jul 2026 | 31% | -27.7 | behind | 31 Dec 2028 | under 10% built: too early to project | dubairealestateiq.com |
| The Highgrove Ellington Properties · Mohammed Bin Rashid City | 7% 6 Aug 2026 | 28% | -20.9 | behind | 31 Dec 2028 | under 10% built: too early to project | dubairealestateiq.com |
| Ellington Sands I Ellington Properties · Dubai Islands (Island A) | 0.4% 5 Jun 2026 | 20% | -19.8 | behind | 31 Dec 2028 | under 10% built: too early to project | dubairealestateiq.com |
| Ellington Sands II Ellington Properties · Palm Deira | 0.4% 5 Jun 2026 | 20% | -19.8 | behind | 31 Dec 2028 | under 10% built: too early to project | dubairealestateiq.com |
| Eaton Square Ellington Properties · Bukadra | 5.4% 20 Jul 2026 | 25% | -19.1 | behind | 30 Jun 2028 | under 10% built: too early to project | dubairealestateiq.com |
| Windsor House II Ellington Properties · Madinat Al Mataar | 0.6% 20 Aug 2026 | 15% | -14.3 | behind | 31 Jul 2029 | under 10% built: too early to project | dubairealestateiq.com |
| Windsor House Ellington Properties · Dubai South (Residential District) | 3.1% 17 Jun 2026 | 15% | -11.7 | behind | 31 Jul 2029 | under 10% built: too early to project | dubairealestateiq.com |
| The Meriva Collection (Meriva Gardens / Meriva Signature) Ellington Properties · Dubai Islands | 0.1% 15 Oct 2026 | 9% | -9.2 | on pace or ahead | 31 Dec 2031 | under 10% built: too early to project | dubairealestateiq.com |
| Riverton House Ellington Properties · Bukadra | 0% 22 Dec 2025 | 3% | -2.8 | on pace or ahead | 31 Dec 2027 | under 10% built: too early to project | dubairealestateiq.com |
| Eltiera Views Ellington Properties · Jumeirah Islands | 0% 5 Dec 2025 | - | - | not comparable | 31 Dec 2029 | under 10% built: too early to project | dubairealestateiq.com |
| Portside Square Ellington Properties · Mina Rashid | 0% 12 Jan 2026 | - | - | not comparable | 31 Dec 2029 | under 10% built: too early to project | dubairealestateiq.com |
Method
Time elapsed = (inspection date minus construction start on the register) divided by (registered completion date minus construction start). When no start date is printed, the registration date is used.
Gap = % built at the inspection minus % of time elapsed at the same date, in percentage points. Behind = a gap below -10 points. Registered date passed = the inspection is after the completion date on the register and the project is not at 100%.
Projection, only for 10% to 99% built: the remaining % divided by the observed pace, where the pace is % built per day since the start date, since the registration date and between the last two inspections we hold (when it rose). The range runs from the earliest to the latest of these estimates.
Limits: Construction does not move in a straight line (a slow start, faster structure, slow finishing), so a straight line from an early reading tends to give later dates than the work will need, and a late reading can give earlier ones. The % built is the DLD inspection figure, not ours.
Source: the Dubai Land Department project register as mirrored per project with its inspection history, read by our register job; 929 DLD records, 28 with two or more dated inspections.
Files: /data/n35a/pace.json · /open/n35a-build.py · /registers/changes/