Construction pace against the registered date

For Dubai projects with DLD inspection readings: % built against the share of time elapsed to the completion date on the register, and the completion range the observed pace points to. A projection, not a promise.

Updated 23 Nov 2026

A projection from the pace on the register, not a promise, and not a finding about the developer.

815projects compared (DLD % built and dates on the register)
82.8%more than 10 points behind the time elapsed (95% interval 80.1 to 85.3%)
-27.1median gap in points, % built minus % of time elapsed (95% interval -29.5 to -26)
426projects with a projected range (10% to 99% built)
87.1%of them projected after the registered date (95% interval 83.6 to 89.9%)
≤-6090-50115-40162-30178-20130-10900291012207301401
Projects by gap between % built and % of time elapsed, in 10-point bins
Show as a table
Gap (points)Projects
-60 … -5090
-50 … -40115
-40 … -30162
-30 … -20178
-20 … -10130
-10 … 090
0 … 1029
10 … 2012
20 … 307
30 … 401
40 … 501

Projects

Developer: ellington-properties · All

19 projects, page 1
Project% built (inspection)Time elapsedGap (points)PaceRegistered completionProjected rangeRegister
Hillmont Residences by Ellington
Ellington Properties · Jumeirah Village Circle
26.3%
22 Jul 2026
83%-56.9behind31 Dec 2026Mar 2032 – Sept 2032dubairealestateiq.com
Mercer House
Ellington Properties · Uptown Dubai, Jumeirah Lake Towers
18.1%
7 Aug 2026
71%-53.2behind31 Jul 2027Apr 2036 – Aug 2037dubairealestateiq.com
Claydon House by Ellington
Ellington Properties · Bukadra
15.7%
6 Aug 2026
61%-45.6behind31 Dec 2027Dec 2035 – Jul 2038dubairealestateiq.com
The Watercrest
Ellington Properties · Mohammed Bin Rashid City
2.2%
24 Jul 2026
47%-44.5behind31 Mar 2028under 10% built: too early to projectdubairealestateiq.com
One River Point
Ellington Properties · Business Bay
35.4%
21 Jul 2026
76%-40.2behind9 Jun 2027Jan 2031 – Jul 2031dubairealestateiq.com
Belmore Residences
Ellington Properties · Bukadra
6.5%
6 Aug 2026
42%-35behind31 Dec 2027under 10% built: too early to projectdubairealestateiq.com
The Hillgate
Ellington Properties · Dubai Silicon Oasis
3.1%
4 Jun 2026
38%-34.6behind30 Jun 2028under 10% built: too early to projectdubairealestateiq.com
Belgravia Gardens
Ellington Properties · Wadi Al Safa 2
3.1%
4 Jun 2026
37%-33.5behind30 Sept 2028under 10% built: too early to projectdubairealestateiq.com
Eltiera Heights
Ellington Properties · Jumeirah Islands
3%
20 Jul 2026
31%-27.7behind31 Dec 2028under 10% built: too early to projectdubairealestateiq.com
The Highgrove
Ellington Properties · Mohammed Bin Rashid City
7%
6 Aug 2026
28%-20.9behind31 Dec 2028under 10% built: too early to projectdubairealestateiq.com
Ellington Sands I
Ellington Properties · Dubai Islands (Island A)
0.4%
5 Jun 2026
20%-19.8behind31 Dec 2028under 10% built: too early to projectdubairealestateiq.com
Ellington Sands II
Ellington Properties · Palm Deira
0.4%
5 Jun 2026
20%-19.8behind31 Dec 2028under 10% built: too early to projectdubairealestateiq.com
Eaton Square
Ellington Properties · Bukadra
5.4%
20 Jul 2026
25%-19.1behind30 Jun 2028under 10% built: too early to projectdubairealestateiq.com
Windsor House II
Ellington Properties · Madinat Al Mataar
0.6%
20 Aug 2026
15%-14.3behind31 Jul 2029under 10% built: too early to projectdubairealestateiq.com
Windsor House
Ellington Properties · Dubai South (Residential District)
3.1%
17 Jun 2026
15%-11.7behind31 Jul 2029under 10% built: too early to projectdubairealestateiq.com
The Meriva Collection (Meriva Gardens / Meriva Signature)
Ellington Properties · Dubai Islands
0.1%
15 Oct 2026
9%-9.2on pace or ahead31 Dec 2031under 10% built: too early to projectdubairealestateiq.com
Riverton House
Ellington Properties · Bukadra
0%
22 Dec 2025
3%-2.8on pace or ahead31 Dec 2027under 10% built: too early to projectdubairealestateiq.com
Eltiera Views
Ellington Properties · Jumeirah Islands
0%
5 Dec 2025
--not comparable31 Dec 2029under 10% built: too early to projectdubairealestateiq.com
Portside Square
Ellington Properties · Mina Rashid
0%
12 Jan 2026
--not comparable31 Dec 2029under 10% built: too early to projectdubairealestateiq.com

Method

Time elapsed = (inspection date minus construction start on the register) divided by (registered completion date minus construction start). When no start date is printed, the registration date is used.

Gap = % built at the inspection minus % of time elapsed at the same date, in percentage points. Behind = a gap below -10 points. Registered date passed = the inspection is after the completion date on the register and the project is not at 100%.

Projection, only for 10% to 99% built: the remaining % divided by the observed pace, where the pace is % built per day since the start date, since the registration date and between the last two inspections we hold (when it rose). The range runs from the earliest to the latest of these estimates.

Limits: Construction does not move in a straight line (a slow start, faster structure, slow finishing), so a straight line from an early reading tends to give later dates than the work will need, and a late reading can give earlier ones. The % built is the DLD inspection figure, not ours.

Source: the Dubai Land Department project register as mirrored per project with its inspection history, read by our register job; 929 DLD records, 28 with two or more dated inspections.