Home / Dubai / Construction pace against the registered date

Construction pace against the registered date

For Dubai projects with DLD inspection readings: % built against the share of time elapsed to the completion date on the register, and the completion range the observed pace points to. A projection, not a promise.

Updated 23 Nov 2026

A projection from the pace on the register, not a promise, and not a finding about the developer.

860projects compared (DLD % built and dates on the register)
82.7%more than 10 points behind the time elapsed (95% interval 80 to 85.1%)
-27median gap in points, % built minus % of time elapsed (95% interval -29.1 to -26)
452projects with a projected range (10% to 99% built)
86.7%of them projected after the registered date (95% interval 83.3 to 89.5%)
≤-6098-50119-40168-30186-20140-10940291013209303401
Projects by gap between % built and % of time elapsed, in 10-point bins
Show as a table
Gap (points)Projects
-60 … -5098
-50 … -40119
-40 … -30168
-30 … -20186
-20 … -10140
-10 … 094
0 … 1029
10 … 2013
20 … 309
30 … 403
40 … 501

Projects

Developer: sobha-realty · All

16 projects, page 1
Project% built (inspection)Time elapsedGap (points)PaceRegistered completionProjected rangeRegister
Sobha Solis
Sobha Realty · Motor City
17.9%
22 Oct 2026
48%-30.4behind31 Dec 2028Nov 2034 – Mar 2036dubairealestateiq.com
Sobha Orbis
Sobha Realty · Motor City
18.2%
13 Aug 2026
48%-29.8behind31 Dec 2028Jan 2036 – Jun 2036dubairealestateiq.com
Sobha Seahaven Tower A
Sobha Realty · Dubai Marina
45.2%
9 Nov 2026
70%-24.3behind30 Apr 2028Dec 2030 – Mar 2031dubairealestateiq.com
Elwood Estates
Sobha Realty · Al Yufrah 1
14.4%
20 Jul 2026
34%-19.9behind30 Jun 2028Aug 2032 – Nov 2033dubairealestateiq.com
Sobha Seahaven Tower B & C
Sobha Realty · Dubai Marina
40.2%
18 Sept 2026
58%-18.1behind31 Oct 2028Sept 2030 – Feb 2031dubairealestateiq.com
The Element at Sobha One
Sobha Realty · Ras Al Khor Industrial First
11.1%
11 Aug 2026
27%-16.3behind31 Dec 2029Oct 2036 – Oct 2037dubairealestateiq.com
Skyvue
Sobha Realty · Bukadra
16.1%
11 Nov 2026
32%-16.1behind31 Mar 2030Mar 2035 – Sept 2035dubairealestateiq.com
Sobha Central
Sobha Realty · Sheikh Zayed Road, Jebel Ali side
2.4%
29 Sept 2026
9%-6.3on pace or ahead31 Dec 2031under 10% built: too early to projectdubairealestateiq.com
Sobha Estates
Sobha Realty · Bukadra
68.5%
15 Sept 2026
69%-0.9on pace or ahead31 Dec 2027Dec 2027 – Jan 2028dubairealestateiq.com
Skyscape (Sobha Hartland II)
Sobha Realty · Mohammed Bin Rashid City
38.3%
21 Sept 2026
39%-0.8on pace or ahead31 Dec 2029Sept 2028 – Feb 2030dubairealestateiq.com
Verde by Sobha
Sobha Realty · Jumeirah Lakes Towers
85%
24 Aug 2026
80%5on pace or ahead30 Jun 2027Mar 2027 – Mar 2027dubairealestateiq.com
The Brooks at Sobha Sanctuary
Sobha Realty · The Valley
0%
15 Jul 2026
--not comparable31 Aug 2030under 10% built: too early to projectdubairealestateiq.com
Sobha Skyparks
Sobha Realty · Business Bay
0%
23 Oct 2025
--not comparable31 Dec 2032under 10% built: too early to projectdubairealestateiq.com
The Greens at Sobha Sanctuary
Sobha Realty · Al Yufrah 1
0%
15 Jul 2026
--not comparable31 Aug 2030under 10% built: too early to projectdubairealestateiq.com
The Grove at Sobha Sanctuary
Sobha Realty · Al Yufrah 1
0%
20 May 2026
--not comparable31 Aug 2030under 10% built: too early to projectdubairealestateiq.com
The Woods
Sobha Realty · Al Yufrah 1
0%
21 May 2026
--not comparable30 Dec 2030under 10% built: too early to projectdubairealestateiq.com

Method

Time elapsed = (inspection date minus construction start on the register) divided by (registered completion date minus construction start). When no start date is printed, the registration date is used.

Gap = % built at the inspection minus % of time elapsed at the same date, in percentage points. Behind = a gap below -10 points. Registered date passed = the inspection is after the completion date on the register and the project is not at 100%.

Projection, only for 10% to 99% built: the remaining % divided by the observed pace, where the pace is % built per day since the start date, since the registration date and between the last two inspections we hold (when it rose). The range runs from the earliest to the latest of these estimates.

Limits: Construction does not move in a straight line (a slow start, faster structure, slow finishing), so a straight line from an early reading tends to give later dates than the work will need, and a late reading can give earlier ones. The % built is the DLD inspection figure, not ours.

Source: the Dubai Land Department project register as mirrored per project with its inspection history, read by our register job; 985 DLD records, 28 with two or more dated inspections.

Files: /data/n35a/pace.json · /open/n35a-build.py · /registers/changes/