Home / Dubai / Construction pace against the registered date
Construction pace against the registered date
For Dubai projects with DLD inspection readings: % built against the share of time elapsed to the completion date on the register, and the completion range the observed pace points to. A projection, not a promise.
Updated 23 Nov 2026
A projection from the pace on the register, not a promise, and not a finding about the developer.
Show as a table
| Gap (points) | Projects |
|---|---|
| -60 … -50 | 98 |
| -50 … -40 | 119 |
| -40 … -30 | 168 |
| -30 … -20 | 186 |
| -20 … -10 | 140 |
| -10 … 0 | 94 |
| 0 … 10 | 29 |
| 10 … 20 | 13 |
| 20 … 30 | 9 |
| 30 … 40 | 3 |
| 40 … 50 | 1 |
Projects
Developer: sobha-realty · All
| Project | % built (inspection) | Time elapsed | Gap (points) | Pace | Registered completion | Projected range | Register |
|---|---|---|---|---|---|---|---|
| Sobha Solis Sobha Realty · Motor City | 17.9% 22 Oct 2026 | 48% | -30.4 | behind | 31 Dec 2028 | Nov 2034 – Mar 2036 | dubairealestateiq.com |
| Sobha Orbis Sobha Realty · Motor City | 18.2% 13 Aug 2026 | 48% | -29.8 | behind | 31 Dec 2028 | Jan 2036 – Jun 2036 | dubairealestateiq.com |
| Sobha Seahaven Tower A Sobha Realty · Dubai Marina | 45.2% 9 Nov 2026 | 70% | -24.3 | behind | 30 Apr 2028 | Dec 2030 – Mar 2031 | dubairealestateiq.com |
| Elwood Estates Sobha Realty · Al Yufrah 1 | 14.4% 20 Jul 2026 | 34% | -19.9 | behind | 30 Jun 2028 | Aug 2032 – Nov 2033 | dubairealestateiq.com |
| Sobha Seahaven Tower B & C Sobha Realty · Dubai Marina | 40.2% 18 Sept 2026 | 58% | -18.1 | behind | 31 Oct 2028 | Sept 2030 – Feb 2031 | dubairealestateiq.com |
| The Element at Sobha One Sobha Realty · Ras Al Khor Industrial First | 11.1% 11 Aug 2026 | 27% | -16.3 | behind | 31 Dec 2029 | Oct 2036 – Oct 2037 | dubairealestateiq.com |
| Skyvue Sobha Realty · Bukadra | 16.1% 11 Nov 2026 | 32% | -16.1 | behind | 31 Mar 2030 | Mar 2035 – Sept 2035 | dubairealestateiq.com |
| Sobha Central Sobha Realty · Sheikh Zayed Road, Jebel Ali side | 2.4% 29 Sept 2026 | 9% | -6.3 | on pace or ahead | 31 Dec 2031 | under 10% built: too early to project | dubairealestateiq.com |
| Sobha Estates Sobha Realty · Bukadra | 68.5% 15 Sept 2026 | 69% | -0.9 | on pace or ahead | 31 Dec 2027 | Dec 2027 – Jan 2028 | dubairealestateiq.com |
| Skyscape (Sobha Hartland II) Sobha Realty · Mohammed Bin Rashid City | 38.3% 21 Sept 2026 | 39% | -0.8 | on pace or ahead | 31 Dec 2029 | Sept 2028 – Feb 2030 | dubairealestateiq.com |
| Verde by Sobha Sobha Realty · Jumeirah Lakes Towers | 85% 24 Aug 2026 | 80% | 5 | on pace or ahead | 30 Jun 2027 | Mar 2027 – Mar 2027 | dubairealestateiq.com |
| The Brooks at Sobha Sanctuary Sobha Realty · The Valley | 0% 15 Jul 2026 | - | - | not comparable | 31 Aug 2030 | under 10% built: too early to project | dubairealestateiq.com |
| Sobha Skyparks Sobha Realty · Business Bay | 0% 23 Oct 2025 | - | - | not comparable | 31 Dec 2032 | under 10% built: too early to project | dubairealestateiq.com |
| The Greens at Sobha Sanctuary Sobha Realty · Al Yufrah 1 | 0% 15 Jul 2026 | - | - | not comparable | 31 Aug 2030 | under 10% built: too early to project | dubairealestateiq.com |
| The Grove at Sobha Sanctuary Sobha Realty · Al Yufrah 1 | 0% 20 May 2026 | - | - | not comparable | 31 Aug 2030 | under 10% built: too early to project | dubairealestateiq.com |
| The Woods Sobha Realty · Al Yufrah 1 | 0% 21 May 2026 | - | - | not comparable | 30 Dec 2030 | under 10% built: too early to project | dubairealestateiq.com |
Method
Time elapsed = (inspection date minus construction start on the register) divided by (registered completion date minus construction start). When no start date is printed, the registration date is used.
Gap = % built at the inspection minus % of time elapsed at the same date, in percentage points. Behind = a gap below -10 points. Registered date passed = the inspection is after the completion date on the register and the project is not at 100%.
Projection, only for 10% to 99% built: the remaining % divided by the observed pace, where the pace is % built per day since the start date, since the registration date and between the last two inspections we hold (when it rose). The range runs from the earliest to the latest of these estimates.
Limits: Construction does not move in a straight line (a slow start, faster structure, slow finishing), so a straight line from an early reading tends to give later dates than the work will need, and a late reading can give earlier ones. The % built is the DLD inspection figure, not ours.
Source: the Dubai Land Department project register as mirrored per project with its inspection history, read by our register job; 985 DLD records, 28 with two or more dated inspections.
Files: /data/n35a/pace.json · /open/n35a-build.py · /registers/changes/