Home / Dubai / Construction pace against the registered date

Construction pace against the registered date

For Dubai projects with DLD inspection readings: % built against the share of time elapsed to the completion date on the register, and the completion range the observed pace points to. A projection, not a promise.

Updated 23 Nov 2026

A projection from the pace on the register, not a promise, and not a finding about the developer.

815projects compared (DLD % built and dates on the register)
82.8%more than 10 points behind the time elapsed (95% interval 80.1 to 85.3%)
-27.1median gap in points, % built minus % of time elapsed (95% interval -29.5 to -26)
426projects with a projected range (10% to 99% built)
87.1%of them projected after the registered date (95% interval 83.6 to 89.9%)
≤-6090-50115-40162-30178-20130-10900291012207301401
Projects by gap between % built and % of time elapsed, in 10-point bins
Show as a table
Gap (points)Projects
-60 … -5090
-50 … -40115
-40 … -30162
-30 … -20178
-20 … -10130
-10 … 090
0 … 1029
10 … 2012
20 … 307
30 … 401
40 … 501

Projects

Developer: wasl · All

15 projects, page 1
Project% built (inspection)Time elapsedGap (points)PaceRegistered completionProjected rangeRegister
South Garden A
Wasl · Jabal Ali First
16.2%
7 Sept 2026
56%-40behind31 Dec 2027May 2035 – Dec 2036dubairealestateiq.com
South Garden B
Wasl · Jabal Ali First
16.2%
7 Sept 2026
56%-40behind31 Dec 2027May 2035 – Dec 2036dubairealestateiq.com
South Garden C
Wasl · Jabal Ali First
16.2%
7 Sept 2026
56%-40behind31 Dec 2027May 2035 – Dec 2036dubairealestateiq.com
One.B Tower
Wasl · Business Bay
10.1%
8 Oct 2026
42%-31.7behind31 Dec 2028Jan 2041 – Nov 2044dubairealestateiq.com
South Garden D
Wasl · Jabal Ali First
5.7%
7 Sept 2026
33%-27.3behind31 May 2028under 10% built: too early to projectdubairealestateiq.com
Ashwood Estates
Wasl · Dubai Production City
0.1%
1 Jun 2026
25%-25.3behind18 Sept 2028under 10% built: too early to projectdubairealestateiq.com
South Garden E
Wasl · Jabal Ali First
8%
7 Sept 2026
33%-25behind31 May 2028under 10% built: too early to projectdubairealestateiq.com
Avenue Park Towers
Wasl · Al Kifaf
7.7%
8 Sept 2026
32%-24.6behind31 Dec 2028under 10% built: too early to projectdubairealestateiq.com
Boulevard Park 2
Wasl · Jabal Ali First
0%
29 Jun 2026
5%-4.6on pace or ahead30 Nov 2029under 10% built: too early to projectdubairealestateiq.com
Boulevard Park 1
Wasl · Jabal Ali First
0%
29 Jun 2026
4%-4.1on pace or ahead30 Apr 2030under 10% built: too early to projectdubairealestateiq.com
Nine Collective
Wasl · Wasl 1, Al Kifaf (Zabeel Park)
-
-
--not comparable-no projectiondubairealestateiq.com
Cedarwood Estates
Wasl · Dubai Production City
0%
8 Jan 2026
--not comparable4 Oct 2028under 10% built: too early to projectdubairealestateiq.com
Pinewood Estate Homes
Wasl · Dubai Production City
0.3%
11 Mar 2026
--not comparable17 Nov 2028under 10% built: too early to projectdubairealestateiq.com
Cedarwood Estates-South
Wasl · Dubai Production City
0%
14 May 2026
--not comparable31 Jan 2029under 10% built: too early to projectdubairealestateiq.com
Avenue Park Towers II
Wasl · Al Kifaf
0%
8 Jun 2026
--not comparable6 Mar 2030under 10% built: too early to projectdubairealestateiq.com

Method

Time elapsed = (inspection date minus construction start on the register) divided by (registered completion date minus construction start). When no start date is printed, the registration date is used.

Gap = % built at the inspection minus % of time elapsed at the same date, in percentage points. Behind = a gap below -10 points. Registered date passed = the inspection is after the completion date on the register and the project is not at 100%.

Projection, only for 10% to 99% built: the remaining % divided by the observed pace, where the pace is % built per day since the start date, since the registration date and between the last two inspections we hold (when it rose). The range runs from the earliest to the latest of these estimates.

Limits: Construction does not move in a straight line (a slow start, faster structure, slow finishing), so a straight line from an early reading tends to give later dates than the work will need, and a late reading can give earlier ones. The % built is the DLD inspection figure, not ours.

Source: the Dubai Land Department project register as mirrored per project with its inspection history, read by our register job; 929 DLD records, 28 with two or more dated inspections.

Files: /data/n35a/pace.json · /open/n35a-build.py · /registers/changes/