Construction pace against the registered date

For Dubai projects with DLD inspection readings: % built against the share of time elapsed to the completion date on the register, and the completion range the observed pace points to. A projection, not a promise.

Updated 23 Nov 2026

A projection from the pace on the register, not a promise, and not a finding about the developer.

815projects compared (DLD % built and dates on the register)
82.8%more than 10 points behind the time elapsed (95% interval 80.1 to 85.3%)
-27.1median gap in points, % built minus % of time elapsed (95% interval -29.5 to -26)
426projects with a projected range (10% to 99% built)
87.1%of them projected after the registered date (95% interval 83.6 to 89.9%)
≤-6090-50115-40162-30178-20130-10900291012207301401
Projects by gap between % built and % of time elapsed, in 10-point bins
Show as a table
Gap (points)Projects
-60 … -5090
-50 … -40115
-40 … -30162
-30 … -20178
-20 … -10130
-10 … 090
0 … 1029
10 … 2012
20 … 307
30 … 401
40 … 501

Projects

Developer: nakheel · All

23 projects, page 1
Project% built (inspection)Time elapsedGap (points)PaceRegistered completionProjected rangeRegister
Bay Villas - Dubai Islands
Nakheel · Palm Deira
22.8%
19 Aug 2026
75%-51.9behind2 May 2027Aug 2033 – Feb 2035dubairealestateiq.com
Palm Jebel Ali - Frond C
Nakheel · Palm Jabal Ali
8.6%
28 Sept 2026
57%-48.1behind17 Jan 2028under 10% built: too early to projectdubairealestateiq.com
Palm Jebel Ali - Frond D
Nakheel · Palm Jabal Ali
8.7%
28 Sept 2026
57%-47.9behind17 Jan 2028under 10% built: too early to projectdubairealestateiq.com
Palm Jebel Ali - Frond E
Nakheel · Palm Jabal Ali
9.2%
28 Sept 2026
57%-47.4behind17 Jan 2028under 10% built: too early to projectdubairealestateiq.com
Palm Jebel Ali - Frond B
Nakheel · Palm Jabal Ali
10%
28 Sept 2026
57%-46.6behind17 Jan 2028Jan 2042 – Aug 2043dubairealestateiq.com
Palm Jebel Ali - Frond F
Nakheel · Palm Jabal Ali
11.8%
28 Sept 2026
57%-44.8behind17 Jan 2028Jun 2039 – Sept 2040dubairealestateiq.com
Bay Grove Residences
Nakheel · Dubai Islands
12.3%
23 Oct 2026
57%-44.6behind15 Mar 2028Dec 2039 – Jul 2041dubairealestateiq.com
Rixos Bay Residences, Dubai Islands
Nakheel · Dubai Islands (Palm Deira)
47.9%
22 Jun 2026
89%-40.8behind15 Oct 2026Mar 2029 – Aug 2029dubairealestateiq.com
Palm Jebel Ali - Frond P
Nakheel · Palm Jabal Ali
48.8%
10 Nov 2026
78%-29.3behind29 Sept 2027Mar 2030 – Jul 2030dubairealestateiq.com
Palm Jebel Ali - the Beach and Coral Collection - Frond D
Nakheel · Palm Jabal Ali
2.2%
13 Oct 2026
29%-26.3behind4 Dec 2028under 10% built: too early to projectdubairealestateiq.com
Palm Jebel Ali - Frond M
Nakheel · Palm Jabal Ali
51.3%
10 Nov 2026
77%-26.1behind8 Oct 2027Oct 2029 – Feb 2030dubairealestateiq.com
Palm Jebel Ali - the Beach and Coral Collection
Nakheel · Palm Jabal Ali
2.4%
13 Oct 2026
29%-26.1behind4 Dec 2028under 10% built: too early to projectdubairealestateiq.com
Palm Jebel Ali - the Beach and Coral Collection - Frond F
Nakheel · Palm Jabal Ali
2.5%
13 Oct 2026
29%-26behind4 Dec 2028under 10% built: too early to projectdubairealestateiq.com
Palm Jebel Ali - the Beach and Coral Collection - Frond E
Nakheel · Palm Jabal Ali
2.6%
13 Oct 2026
29%-25.9behind4 Dec 2028under 10% built: too early to projectdubairealestateiq.com
Palm Jebel Ali - the Beach and Coral Collection - Frond B
Nakheel · Palm Jabal Ali
2.7%
13 Oct 2026
29%-25.8behind4 Dec 2028under 10% built: too early to projectdubairealestateiq.com
Palm Jebel Ali - the Beach and Coral Collection - Frond C
Nakheel · Palm Jabal Ali
2.8%
13 Oct 2026
29%-25.8behind4 Dec 2028under 10% built: too early to projectdubairealestateiq.com
Palm Central Private Residences - Frond M
Nakheel · Palm Jabal Ali
0.1%
15 Sept 2026
20%-19.5behind31 Jul 2029under 10% built: too early to projectdubairealestateiq.com
Palm Jebel Ali - Frond N
Nakheel · Palm Jabal Ali
58%
10 Nov 2026
77%-19.4behind8 Oct 2027Feb 2029 – May 2029dubairealestateiq.com
Palm Jebel Ali - Frond K
Nakheel · Palm Jabal Ali
58.3%
10 Nov 2026
74%-15.2behind1 Dec 2027Dec 2028 – Apr 2029dubairealestateiq.com
Palm Jebel Ali - Frond O
Nakheel · Palm Jabal Ali
67.5%
10 Nov 2026
78%-10.6behind29 Sept 2027May 2028 – Jul 2028dubairealestateiq.com
Palm Jebel Ali - Frond A Villas
Nakheel · Palm Jebel Ali
51.3%
10 Nov 2026
61%-9.2on pace or ahead17 Jan 2028Jan 2027 – Sept 2028dubairealestateiq.com
Bay Estate
Nakheel · Palm Deira
0%
20 Aug 2026
--not comparable15 Aug 2030under 10% built: too early to projectdubairealestateiq.com
Palm Central Private Residences - Frond N
Nakheel · Palm Jabal Ali
0%
27 Feb 2026
--not comparable13 Dec 2030under 10% built: too early to projectdubairealestateiq.com

Method

Time elapsed = (inspection date minus construction start on the register) divided by (registered completion date minus construction start). When no start date is printed, the registration date is used.

Gap = % built at the inspection minus % of time elapsed at the same date, in percentage points. Behind = a gap below -10 points. Registered date passed = the inspection is after the completion date on the register and the project is not at 100%.

Projection, only for 10% to 99% built: the remaining % divided by the observed pace, where the pace is % built per day since the start date, since the registration date and between the last two inspections we hold (when it rose). The range runs from the earliest to the latest of these estimates.

Limits: Construction does not move in a straight line (a slow start, faster structure, slow finishing), so a straight line from an early reading tends to give later dates than the work will need, and a late reading can give earlier ones. The % built is the DLD inspection figure, not ours.

Source: the Dubai Land Department project register as mirrored per project with its inspection history, read by our register job; 929 DLD records, 28 with two or more dated inspections.