Home / Dubai / Construction pace against the registered date

Construction pace against the registered date

For Dubai projects with DLD inspection readings: % built against the share of time elapsed to the completion date on the register, and the completion range the observed pace points to. A projection, not a promise.

Updated 23 Nov 2026

A projection from the pace on the register, not a promise, and not a finding about the developer.

815projects compared (DLD % built and dates on the register)
82.8%more than 10 points behind the time elapsed (95% interval 80.1 to 85.3%)
-27.1median gap in points, % built minus % of time elapsed (95% interval -29.5 to -26)
426projects with a projected range (10% to 99% built)
87.1%of them projected after the registered date (95% interval 83.6 to 89.9%)
≤-6090-50115-40162-30178-20130-10900291012207301401
Projects by gap between % built and % of time elapsed, in 10-point bins
Show as a table
Gap (points)Projects
-60 … -5090
-50 … -40115
-40 … -30162
-30 … -20178
-20 … -10130
-10 … 090
0 … 1029
10 … 2012
20 … 307
30 … 401
40 … 501

Projects

Developer: damac-properties · All

54 projects, page 1
Project% built (inspection)Time elapsedGap (points)PaceRegistered completionProjected rangeRegister
Amali Island
DAMAC Properties · The World
18.7%
27 Oct 2026
85%-65.8behind31 Mar 2027Nov 2036 – Jun 2037dubairealestateiq.com
Autograph Collection (DAMAC Hills)
DAMAC Properties · DAMAC Hills
17.9%
30 Oct 2026
80%-62.1behind30 May 2027Jun 2037 – Aug 2037dubairealestateiq.com
DAMAC Bay by Cavalli
DAMAC Properties · Dubai Harbour
33.8%
18 Aug 2026
89%-55.3behind15 Jan 2027Mar 2033 – Aug 2033dubairealestateiq.com
Canal Heights de GRISOGONO
DAMAC Properties · Business Bay
36.3%
17 Aug 2026
90%-53.4behind31 Dec 2026Apr 2032 – Aug 2032dubairealestateiq.com
Canal Crown 2
DAMAC Properties · Business Bay
32.5%
8 Sept 2026
85%-52.1behind31 Mar 2027Jan 2033 – Jun 2033dubairealestateiq.com
ELO 3 (DAMAC Hills 2)
DAMAC Properties · DAMAC Hills 2
6.4%
15 Apr 2026
57%-50.9behind30 Jun 2027under 10% built: too early to projectdubairealestateiq.com
ELO 2 (DAMAC Hills 2)
DAMAC Properties · DAMAC Hills 2
6.4%
15 Apr 2026
57%-50.9behind30 Jun 2027under 10% built: too early to projectdubairealestateiq.com
Casa Ahs
DAMAC Properties · Al Wasl
16.1%
24 Sept 2026
66%-49.8behind31 May 2027Aug 2033 – May 2034dubairealestateiq.com
DAMAC Hills (2) - Park Greens 1
DAMAC Properties · Madinat Hind 4
38.9%
30 Oct 2026
87%-47.8behind30 Mar 2027Jan 2031 – May 2031dubairealestateiq.com
Aykon City 3
DAMAC Properties · Business Bay
38.3%
3 Nov 2026
86%-47.4behind30 Dec 2027Nov 2031 – Dec 2037dubairealestateiq.com
Canal Heights 2 de GRISOGONO
DAMAC Properties · Business Bay
36.4%
14 Aug 2026
84%-47.1behind31 Mar 2027Mar 2032 – Jul 2032dubairealestateiq.com
DAMAC Lagoons - Lagoon Views 13
DAMAC Properties · Al Hebiah Fifth
6%
3 Jul 2026
52%-46.1behind31 Dec 2027under 10% built: too early to projectdubairealestateiq.com
DAMAC Riverside - Sage
DAMAC Properties · Dubai Investment Park Second
13.3%
26 Aug 2026
59%-45.5behind31 Dec 2027Mar 2039 – Jun 2040dubairealestateiq.com
DAMAC Riverside Views
DAMAC Properties · Dubai Investments Park
5.8%
30 Sept 2026
50%-44.2behind31 May 2028under 10% built: too early to projectdubairealestateiq.com
Golf Greens (DAMAC Hills)
DAMAC Properties · DAMAC Hills
40.5%
8 Sept 2026
83%-42.4behind30 Mar 2027Aug 2030 – Nov 2030dubairealestateiq.com
Valencia (DAMAC Lagoons District)
DAMAC Properties · DAMAC Lagoons
5.2%
20 May 2026
46%-41.2behind28 Feb 2028under 10% built: too early to projectdubairealestateiq.com
Canal Crown de GRISOGONO
DAMAC Properties · Business Bay
42.2%
15 Jul 2026
83%-40.4behind28 Feb 2027Aug 2030 – Nov 2030dubairealestateiq.com
Violet 4 (DAMAC Hills 2)
DAMAC Properties · DAMAC Hills 2
14.2%
13 May 2026
52%-38.1behind30 Aug 2027Dec 2034 – Jul 2035dubairealestateiq.com
DAMAC Hills - Ivory
DAMAC Properties · DAMAC Hills
3.5%
4 Nov 2026
42%-38behind30 Jun 2028under 10% built: too early to projectdubairealestateiq.com
Volta Tower
DAMAC Properties · Downtown Dubai
29.3%
18 Aug 2026
66%-36.9behind31 Dec 2027Feb 2033 – Sept 2033dubairealestateiq.com
DAMAC Islands
DAMAC Properties · Dubailand
6.6%
12 Oct 2026
41%-34.6behind31 Dec 2028under 10% built: too early to projectdubairealestateiq.com
DAMAC Lagoons - Lagoon Views 9
DAMAC Properties · Al Hebiah Fifth
47.3%
1 Sept 2026
78%-30.5behind31 Mar 2027Dec 2028 – Jan 2029dubairealestateiq.com
DAMAC Lagoons - Lagoon Views 10
DAMAC Properties · Al Hebiah Fifth
47.4%
1 Sept 2026
78%-30.4behind31 Mar 2027Dec 2028 – Jan 2029dubairealestateiq.com
DAMAC Lagoons - Lagoon Views 12
DAMAC Properties · Al Hebiah Fifth
36.5%
17 Jul 2026
64%-27behind30 Jun 2027Jun 2029 – Dec 2029dubairealestateiq.com
DAMAC Hills (2) - Violet 2
DAMAC Properties · Madinat Hind 4
57.6%
22 Sept 2026
82%-24behind27 Feb 2027Feb 2028dubairealestateiq.com
Chelsea Residences by DAMAC
DAMAC Properties · Dubai Maritime City
6.5%
11 Nov 2026
30%-23behind31 Dec 2029under 10% built: too early to projectdubairealestateiq.com
DAMAC Lagoons - Lagoon Views 11
DAMAC Properties · Al Hebiah Fifth
42.6%
17 Jul 2026
65%-22.1behind30 Jun 2027Nov 2028 – Mar 2029dubairealestateiq.com
DAMAC Riverside - Ivy
DAMAC Properties · Dubai Investment Park Second
38.1%
26 Aug 2026
59%-20.6behind31 Dec 2027Oct 2029 – Jan 2030dubairealestateiq.com
Chelsea Residences 2 by DAMAC
DAMAC Properties · Dubai Maritime City
6.5%
11 Nov 2026
26%-19.7behind31 Dec 2029under 10% built: too early to projectdubairealestateiq.com
DAMAC Hills (2) - Violet 3
DAMAC Properties · Madinat Hind 4
36.2%
16 May 2026
56%-19.4behind30 Jun 2027Nov 2028 – Jan 2029dubairealestateiq.com
DAMAC Sun City
DAMAC Properties · Al Yelayiss 1
36.5%
24 Sept 2026
55%-17.9behind30 Mar 2028Nov 2029 – Apr 2030dubairealestateiq.com
DAMAC Riverside - Lush
DAMAC Properties · Dubai Investment Park Second
41.7%
26 Aug 2026
59%-17.1behind31 Dec 2027May 2029 – Aug 2029dubairealestateiq.com
Harbour Lights de GRISOGONO
DAMAC Properties · Dubai
64.3%
9 Jul 2026
80%-15.4behind21 May 2027May 2028 – Jul 2028dubairealestateiq.com
DAMAC District
DAMAC Properties · DAMAC Hills
4.1%
22 Sept 2026
19%-15.2behind30 Mar 2029under 10% built: too early to projectdubairealestateiq.com
DAMAC Riverside - Olive
DAMAC Properties · Dubai Investment Park Second
5.5%
11 Apr 2026
19%-13.7behind30 Jun 2028under 10% built: too early to projectdubairealestateiq.com
DAMAC Islands 2 - Antigua 1
DAMAC Properties · Al Yelayiss 1
0.3%
16 Sept 2026
4%-3.5on pace or ahead31 Dec 2030under 10% built: too early to projectdubairealestateiq.com
DAMAC Islands 2 - Barbados 1
DAMAC Properties · Al Yelayiss 1
0.2%
10 Jun 2026
3%-2.4on pace or ahead30 Jun 2030under 10% built: too early to projectdubairealestateiq.com
DAMAC Islands 2 - Barbados 2
DAMAC Properties · Al Yelayiss 1
0.2%
10 Jun 2026
3%-2.4on pace or ahead30 Jun 2030under 10% built: too early to projectdubairealestateiq.com
DAMAC Islands 2 - Cuba
DAMAC Properties · Al Yelayiss 1
0.2%
10 Jun 2026
3%-2.4on pace or ahead30 Jun 2030under 10% built: too early to projectdubairealestateiq.com
DAMAC Islands 2 - Maui
DAMAC Properties · Al Yelayiss 1
0.2%
10 Jun 2026
3%-2.4on pace or ahead30 Jun 2030under 10% built: too early to projectdubairealestateiq.com
DAMAC Islands 2 - Bermuda
DAMAC Properties · Al Yelayiss 1
0.2%
10 Jun 2026
3%-2.3on pace or ahead30 Jun 2030under 10% built: too early to projectdubairealestateiq.com
DAMAC Islands 2 - Tahiti 1
DAMAC Properties · Al Yelayiss 1
0.3%
2 Jun 2026
2%-1.7on pace or ahead30 Jun 2030under 10% built: too early to projectdubairealestateiq.com
DAMAC Islands 2 - Tahiti 2
DAMAC Properties · Al Yelayiss 1
0.3%
2 Jun 2026
2%-1.7on pace or ahead30 Jun 2030under 10% built: too early to projectdubairealestateiq.com
Piazza Roma
DAMAC Properties · Al Hebiah Fifth
0.2%
18 Aug 2026
1%-1.1on pace or ahead30 Jun 2030under 10% built: too early to projectdubairealestateiq.com
DAMAC Islands 2 - Bahamas 1
DAMAC Properties · Al Yelayiss 1
0.3%
14 May 2026
1%-0.5on pace or ahead30 Jun 2030under 10% built: too early to projectdubairealestateiq.com
DAMAC Islands 2 - Bahamas 2
DAMAC Properties · Al Yelayiss 1
0.3%
14 May 2026
1%-0.5on pace or ahead30 Jun 2030under 10% built: too early to projectdubairealestateiq.com
Ahs Tower
DAMAC Properties · Trade Center Second
67.4%
19 May 2026
46%21.8on pace or ahead31 Jan 2027Jul 2026 – Aug 2026dubairealestateiq.com
Couture by Cavalli
DAMAC Properties · Dubai Canal, Safa Park
27.6%
4 Nov 2026
100%-registered date passed31 May 2025Apr 2036 – Jul 2037dubairealestateiq.com
Lagoon Views (DAMAC Lagoons)
DAMAC Properties · DAMAC Lagoons
63.9%
3 Nov 2026
--not comparable-no projectiondubairealestateiq.com
ELO (DAMAC Hills 2)
DAMAC Properties · DAMAC Hills 2
31.5%
30 Oct 2026
--not comparable-no projectiondubairealestateiq.com
Evergreens (DAMAC Hills 2)
DAMAC Properties · DAMAC Hills 2
48.1%
30 Oct 2026
--not comparable-no projectiondubairealestateiq.com
Golf Gate 2 (DAMAC Hills)
DAMAC Properties · DAMAC Hills
80.4%
20 Jul 2026
--not comparable-no projectiondubairealestateiq.com
DAMAC Casa
DAMAC Properties · Al Sufouh
33.6%
18 Aug 2026
--not comparable-no projectiondubairealestateiq.com
DAMAC Bay 2 by Cavalli
DAMAC Properties · Dubai Harbour
30.3%
15 Jul 2026
--not comparable-no projectiondubairealestateiq.com

Method

Time elapsed = (inspection date minus construction start on the register) divided by (registered completion date minus construction start). When no start date is printed, the registration date is used.

Gap = % built at the inspection minus % of time elapsed at the same date, in percentage points. Behind = a gap below -10 points. Registered date passed = the inspection is after the completion date on the register and the project is not at 100%.

Projection, only for 10% to 99% built: the remaining % divided by the observed pace, where the pace is % built per day since the start date, since the registration date and between the last two inspections we hold (when it rose). The range runs from the earliest to the latest of these estimates.

Limits: Construction does not move in a straight line (a slow start, faster structure, slow finishing), so a straight line from an early reading tends to give later dates than the work will need, and a late reading can give earlier ones. The % built is the DLD inspection figure, not ours.

Source: the Dubai Land Department project register as mirrored per project with its inspection history, read by our register job; 929 DLD records, 28 with two or more dated inspections.