Construction pace against the registered date
For Dubai projects with DLD inspection readings: % built against the share of time elapsed to the completion date on the register, and the completion range the observed pace points to. A projection, not a promise.
Updated 23 Nov 2026
A projection from the pace on the register, not a promise, and not a finding about the developer.
Show as a table
| Gap (points) | Projects |
|---|---|
| -60 … -50 | 90 |
| -50 … -40 | 115 |
| -40 … -30 | 162 |
| -30 … -20 | 178 |
| -20 … -10 | 130 |
| -10 … 0 | 90 |
| 0 … 10 | 29 |
| 10 … 20 | 12 |
| 20 … 30 | 7 |
| 30 … 40 | 1 |
| 40 … 50 | 1 |
Projects
Developer: samana-developers · All
| Project | % built (inspection) | Time elapsed | Gap (points) | Pace | Registered completion | Projected range | Register |
|---|---|---|---|---|---|---|---|
| SAMANA Manhattan 2 SAMANA Developers · Jumeirah Village Circle | 21.2% 17 Sept 2026 | 95% | -74 | behind | 1 Nov 2026 | Nov 2035 – Jun 2036 | dubairealestateiq.com |
| SAMANA Ocean Pearl SAMANA Developers · Dubai Islands | 25.1% 17 Sept 2026 | 88% | -62.9 | behind | 31 Dec 2026 | Jan 2033 | dubairealestateiq.com |
| SAMANA Ibiza SAMANA Developers · Dubai Land Residence Complex (DLRC) | 5.5% 21 Oct 2026 | 61% | -55.4 | behind | 28 Feb 2028 | under 10% built: too early to project | dubairealestateiq.com |
| SAMANA Barari Views SAMANA Developers · Majan (Al Barari) | 32.4% 28 Oct 2026 | 87% | -54.9 | behind | 31 Mar 2027 | Nov 2032 | dubairealestateiq.com |
| SAMANA Ocean Pearl 2 SAMANA Developers · Dubai Islands | 23.3% 17 Sept 2026 | 78% | -54.4 | behind | 31 Mar 2027 | Nov 2032 | dubairealestateiq.com |
| SAMANA Ivy Gardens 2 SAMANA Developers · Dubai Land Residence Complex | 20% 21 Oct 2026 | 66% | -45.9 | behind | 31 Dec 2027 | Jan 2036 – Jan 2036 | dubairealestateiq.com |
| SAMANA Resorts SAMANA Developers · Dubai Production City | 5.9% 22 Oct 2026 | 48% | -42 | behind | 30 May 2028 | under 10% built: too early to project | dubairealestateiq.com |
| Samana Ocean Crest Samana Developers · Dubai Islands | 1.4% 22 Sept 2026 | 37% | -36 | behind | 30 Jun 2028 | under 10% built: too early to project | dubairealestateiq.com |
| Samana Sky Views Samana Developers · Dubai Production City (IMPZ) | 4.4% 28 Oct 2026 | 40% | -35.3 | behind | 31 Jul 2028 | under 10% built: too early to project | dubairealestateiq.com |
| SAMANA Barari Lagoons SAMANA Developers · Majan, Dubailand | 16.5% 20 Oct 2026 | 52% | -35.3 | behind | 31 Mar 2028 | Aug 2034 – Feb 2036 | dubairealestateiq.com |
| SAMANA Ocean Bay SAMANA Developers · Dubai Islands | 3.2% 22 Sept 2026 | 37% | -34.2 | behind | 30 Jun 2028 | under 10% built: too early to project | dubairealestateiq.com |
| SAMANA Barari Heights SAMANA Developers · Majan, Dubailand | 5.7% 28 Oct 2026 | 40% | -34 | behind | 31 Oct 2028 | under 10% built: too early to project | dubairealestateiq.com |
| Rome 2 by Sd SAMANA Developers · Majan | 40.4% 5 Nov 2026 | 74% | -33.6 | behind | 30 Jun 2027 | Jul 2029 – Sept 2029 | dubairealestateiq.com |
| Samana Imperial Garden Samana Developers · Arjan | 4.2% 23 Oct 2026 | 38% | -33.2 | behind | 31 Dec 2028 | under 10% built: too early to project | dubairealestateiq.com |
| Rome 3 by Sd SAMANA Developers · Majan | 10.2% 15 Oct 2026 | 43% | -32.8 | behind | 30 Jun 2028 | Jun 2035 – Feb 2038 | dubairealestateiq.com |
| Samana Hills South Samana Developers · Dubai South / Dubai Industrial City | 12.1% 28 Sept 2026 | 45% | -32.7 | behind | 15 May 2028 | Nov 2035 – May 2036 | dubairealestateiq.com |
| Samana Boulevard Heights Samana Developers · Dubailand Residence Complex | 6.6% 5 Nov 2026 | 39% | -31.8 | behind | 31 Dec 2028 | under 10% built: too early to project | dubairealestateiq.com |
| SAMANA Avenue SAMANA Developers · Dubai Land Residence Complex (DLRC) | 31.8% 1 Oct 2026 | 64% | -31.7 | behind | 31 Dec 2027 | May 2031 | dubairealestateiq.com |
| SAMANA Park Meadows SAMANA Developers · Dubai Land Residence Complex (DLRC) | 38% 1 Oct 2026 | 70% | -31.6 | behind | 31 Aug 2027 | Mar 2030 | dubairealestateiq.com |
| SAMANA Barari Avenue SAMANA Developers · Majan, Dubailand | 6% 23 Sept 2026 | 37% | -30.8 | behind | 31 Oct 2028 | under 10% built: too early to project | dubairealestateiq.com |
| Samana Greenfield Samana Developers · Al Warsan 4, International City Phase 2 | 3.2% 28 Oct 2026 | 33% | -29.8 | behind | 31 Oct 2028 | under 10% built: too early to project | dubairealestateiq.com |
| Samana Business Park 2 SAMANA Developers · Majan | 3.2% 28 Oct 2026 | 33% | -29.8 | behind | 31 Oct 2028 | under 10% built: too early to project | dubairealestateiq.com |
| SAMANA ParkVille SAMANA Developers · Dubai Land Residence Complex (DLRC) | 13.9% 21 Oct 2026 | 42% | -27.8 | behind | 30 Sept 2028 | Apr 2035 – Jun 2035 | dubairealestateiq.com |
| Samana Business Park SAMANA Developers · Majan | 12.8% 24 Sept 2026 | 39% | -26.6 | behind | 30 Sept 2028 | Apr 2035 – Aug 2035 | dubairealestateiq.com |
| Samana Hills South 2 SAMANA Developers · Dubai Industrial City (Saih Shuaib 2) | 12.4% 28 Oct 2026 | 39% | -26.1 | behind | 31 Aug 2028 | Nov 2034 – Dec 2034 | dubairealestateiq.com |
| SAMANA Hills South 3 SAMANA Developers · Dubai South | 15% 28 Oct 2026 | 39% | -23.6 | behind | 31 Aug 2028 | Nov 2031 – May 2033 | dubairealestateiq.com |
| Samana Rome Samana Developers · Meydan, MBR City | 38.7% 16 Sept 2026 | 57% | -18.2 | behind | 31 Dec 2027 | May 2029 – Aug 2029 | dubairealestateiq.com |
| SAMANA Business Hub SAMANA Developers · Jabal Ali Industrial Second | 0.8% 28 Sept 2026 | 15% | -14.2 | behind | 30 Sept 2029 | under 10% built: too early to project | dubairealestateiq.com |
| SAMANA Mykonos Signature SAMANA Developers · Arjan | 86% 12 Oct 2026 | 100% | - | registered date passed | 30 Apr 2026 | Apr 2027 | dubairealestateiq.com |
| SAMANA Skyros SAMANA Developers · Arjan | 71.3% 29 Sept 2026 | 100% | - | registered date passed | 30 Apr 2026 | Jan 2028 | dubairealestateiq.com |
| SAMANA Waves SAMANA Developers · Jumeirah Village Circle (JVC) | 90.6% 16 Oct 2026 | 100% | - | registered date passed | 15 Apr 2026 | Apr 2027 | dubairealestateiq.com |
| SAMANA Waves 2 SAMANA Developers · Jumeirah Village Circle (JVC) | 52.1% 2 Oct 2026 | 100% | - | registered date passed | 20 Mar 2026 | Dec 2029 | dubairealestateiq.com |
| Samana Portside Samana Developers · Downtown Jebel Ali | 0% 7 Jul 2026 | - | - | not comparable | 30 Jun 2029 | under 10% built: too early to project | dubairealestateiq.com |
| SAMANA Lake Views 2 SAMANA Developers · Dubai Production City | 12% 28 Oct 2026 | - | - | not comparable | - | no projection | dubairealestateiq.com |
| SAMANA Greenfield 2 SAMANA Developers · Al Warsan (International City Ph 2 & 3) | 0% 18 May 2026 | - | - | not comparable | 31 Aug 2029 | under 10% built: too early to project | dubairealestateiq.com |
| SAMANA Ivy Gardens SAMANA Developers · Dubai Land Residence Complex (DLRC) | 40.7% 1 Oct 2026 | - | - | not comparable | - | no projection | dubairealestateiq.com |
| SAMANA South Haven SAMANA Developers · Dubai South | 0% 4 May 2026 | - | - | not comparable | 31 Dec 2028 | under 10% built: too early to project | dubairealestateiq.com |
| SAMANA South Haven 2 SAMANA Developers · Dubai South | 0% 7 Jul 2026 | - | - | not comparable | 30 Jun 2029 | under 10% built: too early to project | dubairealestateiq.com |
Method
Time elapsed = (inspection date minus construction start on the register) divided by (registered completion date minus construction start). When no start date is printed, the registration date is used.
Gap = % built at the inspection minus % of time elapsed at the same date, in percentage points. Behind = a gap below -10 points. Registered date passed = the inspection is after the completion date on the register and the project is not at 100%.
Projection, only for 10% to 99% built: the remaining % divided by the observed pace, where the pace is % built per day since the start date, since the registration date and between the last two inspections we hold (when it rose). The range runs from the earliest to the latest of these estimates.
Limits: Construction does not move in a straight line (a slow start, faster structure, slow finishing), so a straight line from an early reading tends to give later dates than the work will need, and a late reading can give earlier ones. The % built is the DLD inspection figure, not ours.
Source: the Dubai Land Department project register as mirrored per project with its inspection history, read by our register job; 929 DLD records, 28 with two or more dated inspections.
Files: /data/n35a/pace.json · /open/n35a-build.py · /registers/changes/