Home / Dubai / Construction pace against the registered date
Construction pace against the registered date
For Dubai projects with DLD inspection readings: % built against the share of time elapsed to the completion date on the register, and the completion range the observed pace points to. A projection, not a promise.
Updated 23 Nov 2026
A projection from the pace on the register, not a promise, and not a finding about the developer.
Show as a table
| Gap (points) | Projects |
|---|---|
| -60 … -50 | 90 |
| -50 … -40 | 115 |
| -40 … -30 | 162 |
| -30 … -20 | 178 |
| -20 … -10 | 130 |
| -10 … 0 | 90 |
| 0 … 10 | 29 |
| 10 … 20 | 12 |
| 20 … 30 | 7 |
| 30 … 40 | 1 |
| 40 … 50 | 1 |
Projects
Developer: emaar-properties · All
| Project | % built (inspection) | Time elapsed | Gap (points) | Pace | Registered completion | Projected range | Register |
|---|---|---|---|---|---|---|---|
| Golf Point Emaar Properties · Madinat Al Mataar | 5.4% 4 Nov 2026 | 49% | -43.6 | behind | 31 Oct 2028 | under 10% built: too early to project | dubairealestateiq.com |
| Golf Dale Emaar · Emaar South | 4.3% 9 Nov 2026 | 41% | -36.3 | behind | 31 Dec 2028 | under 10% built: too early to project | dubairealestateiq.com |
| The Valley - Rivera Emaar Properties · Al Yufrah 1 | 3.9% 6 May 2026 | 37% | -33.4 | behind | 30 Nov 2028 | under 10% built: too early to project | dubairealestateiq.com |
| Marina Cove Emaar Properties · Dubai Marina | 5.7% 1 Oct 2026 | 39% | -33.4 | behind | 30 Sept 2029 | under 10% built: too early to project | dubairealestateiq.com |
| Porto View Emaar Properties · Dubai Maritime City | 6.3% 2 Jun 2026 | 35% | -28.3 | behind | 31 Oct 2028 | under 10% built: too early to project | dubairealestateiq.com |
| The Valley - Farm Grove 2 Emaar Properties · Al Yufrah 1 | 9.8% 6 Jul 2026 | 37% | -27 | behind | 31 Oct 2028 | under 10% built: too early to project | dubairealestateiq.com |
| Marina Views Emaar Properties · Dubai Maritime City | 7.1% 5 May 2026 | 34% | -27 | behind | 31 Dec 2028 | under 10% built: too early to project | dubairealestateiq.com |
| Ocean Views Emaar Properties · Dubai Maritime City | 6.2% 21 Apr 2026 | 33% | -26.9 | behind | 30 Sept 2028 | under 10% built: too early to project | dubairealestateiq.com |
| Golf Acres Emaar Properties · Madinat Al Mataar | 3.5% 23 Jun 2026 | 30% | -26.6 | behind | 31 Dec 2028 | under 10% built: too early to project | dubairealestateiq.com |
| The Valley - Vindera Emaar Properties · Al Yufrah 1 | 2% 20 Jan 2026 | 28% | -26.3 | behind | 31 Dec 2028 | under 10% built: too early to project | dubairealestateiq.com |
| The Valley - Farm Grove Emaar Properties · Al Yufrah 1 | 10% 15 Jul 2026 | 36% | -25.8 | behind | 31 Dec 2028 | Nov 2038 – Jan 2041 | dubairealestateiq.com |
| Marina Place 2 Emaar Properties · Dubai Maritime City | 1.5% 21 Apr 2026 | 27% | -25.4 | behind | 31 Dec 2028 | under 10% built: too early to project | dubairealestateiq.com |
| Grand Polo - Chevalia Estate Emaar Properties · Grand Polo Club, Dubai Investment Park Second | 2.3% 21 Apr 2026 | 27% | -24.9 | behind | 28 Feb 2029 | under 10% built: too early to project | dubairealestateiq.com |
| Pier Point 1 Emaar Properties · Dubai Maritime City | 8.3% 14 May 2026 | 33% | -24.8 | behind | 31 Oct 2028 | under 10% built: too early to project | dubairealestateiq.com |
| Grand Polo - Montura 3 Emaar Properties · Grand Polo Club, Dubai Investment Park Second | 1.1% 21 Apr 2026 | 26% | -24.7 | behind | 30 Jun 2029 | under 10% built: too early to project | dubairealestateiq.com |
| Pier Point 2 Emaar Properties · Dubai Maritime City | 8.5% 14 May 2026 | 33% | -24.6 | behind | 31 Oct 2028 | under 10% built: too early to project | dubairealestateiq.com |
| Seapoint Residences Emaar Properties · Emaar Beachfront | 36.8% 24 Jun 2026 | 61% | -24.4 | behind | 31 Mar 2028 | Apr 2031 – Jan 2032 | dubairealestateiq.com |
| Grand Polo - Montura 2 Emaar Properties · Grand Polo Club, Dubai Investment Park Second | 5% 6 Jul 2026 | 29% | -23.9 | behind | 31 May 2029 | under 10% built: too early to project | dubairealestateiq.com |
| Terra Heights Emaar Properties · Madinat Al Mataar | 9.1% 31 Jul 2026 | 33% | -23.8 | behind | 31 Mar 2029 | under 10% built: too early to project | dubairealestateiq.com |
| Grand Polo - Chevalia Fields Emaar Properties · Grand Polo Club, Dubai Investment Park Second | 10% 21 Jul 2026 | 33% | -22.8 | behind | 30 Apr 2029 | Sept 2037 – Sept 2038 | dubairealestateiq.com |
| The Oasis - Address Villas - Tierra Emaar Properties · Me'Aisem Second | 6.8% 21 Jul 2026 | 29% | -22.2 | behind | 30 Jun 2029 | under 10% built: too early to project | dubairealestateiq.com |
| Grand Polo - Montura Emaar Properties · Grand Polo Club, Dubai Investment Park Second | 11.1% 5 Aug 2026 | 33% | -21.4 | behind | 30 Jun 2029 | Dec 2036 – Oct 2037 | dubairealestateiq.com |
| Marina Place 1 Emaar Properties · Dubai Maritime City | 4.2% 3 Apr 2026 | 26% | -21.3 | behind | 31 Dec 2028 | under 10% built: too early to project | dubairealestateiq.com |
| Ocean Cove Emaar Properties · Dubai Maritime City | 17.9% 14 Apr 2026 | 38% | -20.1 | behind | 31 Aug 2028 | Dec 2032 – Apr 2034 | dubairealestateiq.com |
| Golf Verge Emaar Properties · Madinat Al Mataar | 4.2% 22 Jul 2026 | 24% | -20.1 | behind | 31 May 2029 | under 10% built: too early to project | dubairealestateiq.com |
| The Bristol Emaar Beachfront Emaar Properties · Dubai Marina | 5.8% 23 Jun 2026 | 26% | -19.8 | behind | 30 Sept 2029 | under 10% built: too early to project | dubairealestateiq.com |
| The Valley - Elea Emaar Properties · Al Yufrah 1 | 22% 15 Jul 2026 | 41% | -19.2 | behind | 30 Jun 2028 | May 2031 – May 2032 | dubairealestateiq.com |
| Address the Bay Emaar Properties · Dubai Marina | 70.1% 15 Jul 2026 | 89% | -18.7 | behind | 31 Dec 2026 | Feb 2028 – Apr 2028 | dubairealestateiq.com |
| Golf Meadow Emaar Properties · Madinat Al Mataar | 4.5% 19 Jul 2026 | 23% | -18.6 | behind | 31 Jul 2029 | under 10% built: too early to project | dubairealestateiq.com |
| The Oasis - Lavita Emaar Properties · Me'Aisem Second | 20.1% 2 Jun 2026 | 39% | -18.3 | behind | 31 Jan 2029 | Jan 2033 – Apr 2033 | dubairealestateiq.com |
| The St. Regis Residences, Downtown Dubai Emaar Properties · Downtown Dubai | 76.1% 2 Jun 2026 | 94% | -18.2 | behind | 25 Dec 2026 | May 2029 – Jun 2029 | dubairealestateiq.com |
| The Valley - Kaia Emaar Properties · Al Yufrah 1 | 19.1% 9 Jun 2026 | 37% | -18.2 | behind | 31 Jul 2028 | Oct 2031 – Dec 2032 | dubairealestateiq.com |
| Sera 2 Emaar Properties · Dubai Maritime City | 1.2% 11 Nov 2026 | 19% | -17.6 | behind | 30 Nov 2029 | under 10% built: too early to project | dubairealestateiq.com |
| Palace Residences Hillside B Emaar Properties · Hadaeq Sheikh Mohammed Bin Rashid | 0% 30 Sept 2026 | 18% | -17.5 | behind | 31 Oct 2029 | under 10% built: too early to project | dubairealestateiq.com |
| The Oasis - Palace Villas - Ostra Emaar Properties · Me'Aisem Second | 6.5% 20 Jul 2026 | 23% | -16.5 | behind | 30 Sept 2029 | under 10% built: too early to project | dubairealestateiq.com |
| Greenway 2 Emaar Properties · Madinat Al Mataar | 34.4% 29 Jul 2026 | 49% | -14.6 | behind | 31 May 2028 | Dec 2029 – Aug 2030 | dubairealestateiq.com |
| Altan Emaar Properties · Dubai Creek Harbour (Green Gate) | 11.1% 2 Jul 2026 | 26% | -14.5 | behind | 31 Jul 2029 | Jan 2035 – Feb 2041 | dubairealestateiq.com |
| Aurea Emaar Properties · Dubai Maritime City | 0.4% 9 Nov 2026 | 14% | -13.9 | behind | 30 Jun 2030 | under 10% built: too early to project | dubairealestateiq.com |
| Albero Emaar Properties · Al Khairan First | 11% 2 Jul 2026 | 24% | -13 | behind | 30 Sept 2029 | Oct 2034 – Oct 2036 | dubairealestateiq.com |
| The Oasis - Palmiera Collective Emaar Properties · Me'Aisem Second | 1.3% 16 Jun 2026 | 14% | -12.9 | behind | 28 Feb 2029 | under 10% built: too early to project | dubairealestateiq.com |
| Rosehill Emaar Properties · Dubai Hills Estate | 7.8% 2 Jun 2026 | 21% | -12.8 | behind | 30 Jun 2029 | under 10% built: too early to project | dubairealestateiq.com |
| Grand Polo - Selvara Emaar Properties · Grand Polo Club, Dubai Investment Park Second | 2.8% 14 May 2026 | 15% | -12.3 | behind | 30 Apr 2029 | under 10% built: too early to project | dubairealestateiq.com |
| Parkwood Emaar Properties · Hadaeq Sheikh Mohammed Bin Rashid | 15% 7 May 2026 | 27% | -12 | behind | 31 Jan 2029 | Feb 2032 – Aug 2033 | dubairealestateiq.com |
| Terra Gardens Emaar Properties · Madinat Al Mataar | 3.6% 4 Nov 2026 | 16% | -11.9 | behind | 31 Oct 2029 | under 10% built: too early to project | dubairealestateiq.com |
| Vida Residences Hillside Emaar Properties · Hadaeq Sheikh Mohammed Bin Rashid | 10% 4 May 2026 | 22% | -11.5 | behind | 31 May 2029 | Dec 2033 – May 2037 | dubairealestateiq.com |
| Greencrest Emaar Properties · Hadaeq Sheikh Mohammed Bin Rashid | 1.2% 7 May 2026 | 13% | -11.4 | behind | 30 Jun 2029 | under 10% built: too early to project | dubairealestateiq.com |
| Silva Emaar Properties · Al Khairan First | 10.2% 19 Jul 2026 | 22% | -11.4 | behind | 30 Sept 2029 | May 2034 – Apr 2037 | dubairealestateiq.com |
| Grand Polo - Selvara 4 Emaar Properties · Grand Polo Club, Dubai Investment Park Second | 2.9% 6 May 2026 | 14% | -11.3 | behind | 31 May 2029 | under 10% built: too early to project | dubairealestateiq.com |
| Grand Polo - Selvara 3 Emaar Properties · Grand Polo Club, Dubai Investment Park Second | 3% 6 May 2026 | 14% | -11.2 | behind | 31 May 2029 | under 10% built: too early to project | dubairealestateiq.com |
| Grand Polo - Selvara 2 Emaar Properties · Grand Polo Club, Dubai Investment Park Second | 4% 14 May 2026 | 15% | -11.1 | behind | 30 Apr 2029 | under 10% built: too early to project | dubairealestateiq.com |
| Golf Hills 2 Emaar Properties · Madinat Al Mataar | 4.2% 20 Jul 2026 | 15% | -10.6 | behind | 30 Sept 2029 | under 10% built: too early to project | dubairealestateiq.com |
| The Valley - Alva Emaar Properties · Al Yufrah 1 | 0% 27 Aug 2026 | 10% | -10.2 | behind | 31 Mar 2030 | under 10% built: too early to project | dubairealestateiq.com |
| Address Residences L Dubai Hills Estate Emaar Properties · Hadaeq Sheikh Mohammed Bin Rashid | 26.5% 10 Jun 2026 | 36% | -9.2 | on pace or ahead | 28 Feb 2029 | Aug 2030 – Jun 2031 | dubairealestateiq.com |
| Golf Hills Emaar Properties · Madinat Al Mataar | 3.7% 23 Jun 2026 | 13% | -9.1 | on pace or ahead | 30 Sept 2029 | under 10% built: too early to project | dubairealestateiq.com |
| Golf Fields Emaar Properties · Madinat Al Mataar | 0% 6 Aug 2026 | 9% | -8.6 | on pace or ahead | 28 Feb 2030 | under 10% built: too early to project | dubairealestateiq.com |
| Palace Residences Creek Blue Emaar Properties · Al Khairan First | 40.2% 5 Nov 2026 | 49% | -8.3 | on pace or ahead | 31 Mar 2029 | Mar 2030 – May 2030 | dubairealestateiq.com |
| Palace Residences Hillside A Emaar Properties · Hadaeq Sheikh Mohammed Bin Rashid | 7.9% 5 May 2026 | 16% | -8 | on pace or ahead | 30 Jun 2029 | under 10% built: too early to project | dubairealestateiq.com |
| Sera 1 Emaar Properties · Dubai Maritime City | 0% 2 Jun 2026 | 7% | -7 | on pace or ahead | 30 Nov 2029 | under 10% built: too early to project | dubairealestateiq.com |
| The Valley - Avena 2 Emaar Properties · Al Yufrah 1 | 42.9% 20 Jul 2026 | 50% | -6.6 | on pace or ahead | 31 Jul 2028 | Mar 2029 – Mar 2029 | dubairealestateiq.com |
| Grand Polo - Chevalia Estate 2 Emaar Properties · Grand Polo Club, Dubai Investment Park Second | 4.1% 25 Jun 2026 | 11% | -6.4 | on pace or ahead | 30 Jun 2029 | under 10% built: too early to project | dubairealestateiq.com |
Method
Time elapsed = (inspection date minus construction start on the register) divided by (registered completion date minus construction start). When no start date is printed, the registration date is used.
Gap = % built at the inspection minus % of time elapsed at the same date, in percentage points. Behind = a gap below -10 points. Registered date passed = the inspection is after the completion date on the register and the project is not at 100%.
Projection, only for 10% to 99% built: the remaining % divided by the observed pace, where the pace is % built per day since the start date, since the registration date and between the last two inspections we hold (when it rose). The range runs from the earliest to the latest of these estimates.
Limits: Construction does not move in a straight line (a slow start, faster structure, slow finishing), so a straight line from an early reading tends to give later dates than the work will need, and a late reading can give earlier ones. The % built is the DLD inspection figure, not ours.
Source: the Dubai Land Department project register as mirrored per project with its inspection history, read by our register job; 929 DLD records, 28 with two or more dated inspections.
Files: /data/n35a/pace.json · /open/n35a-build.py · /registers/changes/