Home / Dubai / Construction pace against the registered date

Construction pace against the registered date

For Dubai projects with DLD inspection readings: % built against the share of time elapsed to the completion date on the register, and the completion range the observed pace points to. A projection, not a promise.

Updated 23 Nov 2026

A projection from the pace on the register, not a promise, and not a finding about the developer.

815projects compared (DLD % built and dates on the register)
82.8%more than 10 points behind the time elapsed (95% interval 80.1 to 85.3%)
-27.1median gap in points, % built minus % of time elapsed (95% interval -29.5 to -26)
426projects with a projected range (10% to 99% built)
87.1%of them projected after the registered date (95% interval 83.6 to 89.9%)
≤-6090-50115-40162-30178-20130-10900291012207301401
Projects by gap between % built and % of time elapsed, in 10-point bins
Show as a table
Gap (points)Projects
-60 … -5090
-50 … -40115
-40 … -30162
-30 … -20178
-20 … -10130
-10 … 090
0 … 1029
10 … 2012
20 … 307
30 … 401
40 … 501

Projects

Developer: emaar-properties · All

114 projects, page 1
Project% built (inspection)Time elapsedGap (points)PaceRegistered completionProjected rangeRegister
Golf Point
Emaar Properties · Madinat Al Mataar
5.4%
4 Nov 2026
49%-43.6behind31 Oct 2028under 10% built: too early to projectdubairealestateiq.com
Golf Dale
Emaar · Emaar South
4.3%
9 Nov 2026
41%-36.3behind31 Dec 2028under 10% built: too early to projectdubairealestateiq.com
The Valley - Rivera
Emaar Properties · Al Yufrah 1
3.9%
6 May 2026
37%-33.4behind30 Nov 2028under 10% built: too early to projectdubairealestateiq.com
Marina Cove
Emaar Properties · Dubai Marina
5.7%
1 Oct 2026
39%-33.4behind30 Sept 2029under 10% built: too early to projectdubairealestateiq.com
Porto View
Emaar Properties · Dubai Maritime City
6.3%
2 Jun 2026
35%-28.3behind31 Oct 2028under 10% built: too early to projectdubairealestateiq.com
The Valley - Farm Grove 2
Emaar Properties · Al Yufrah 1
9.8%
6 Jul 2026
37%-27behind31 Oct 2028under 10% built: too early to projectdubairealestateiq.com
Marina Views
Emaar Properties · Dubai Maritime City
7.1%
5 May 2026
34%-27behind31 Dec 2028under 10% built: too early to projectdubairealestateiq.com
Ocean Views
Emaar Properties · Dubai Maritime City
6.2%
21 Apr 2026
33%-26.9behind30 Sept 2028under 10% built: too early to projectdubairealestateiq.com
Golf Acres
Emaar Properties · Madinat Al Mataar
3.5%
23 Jun 2026
30%-26.6behind31 Dec 2028under 10% built: too early to projectdubairealestateiq.com
The Valley - Vindera
Emaar Properties · Al Yufrah 1
2%
20 Jan 2026
28%-26.3behind31 Dec 2028under 10% built: too early to projectdubairealestateiq.com
The Valley - Farm Grove
Emaar Properties · Al Yufrah 1
10%
15 Jul 2026
36%-25.8behind31 Dec 2028Nov 2038 – Jan 2041dubairealestateiq.com
Marina Place 2
Emaar Properties · Dubai Maritime City
1.5%
21 Apr 2026
27%-25.4behind31 Dec 2028under 10% built: too early to projectdubairealestateiq.com
Grand Polo - Chevalia Estate
Emaar Properties · Grand Polo Club, Dubai Investment Park Second
2.3%
21 Apr 2026
27%-24.9behind28 Feb 2029under 10% built: too early to projectdubairealestateiq.com
Pier Point 1
Emaar Properties · Dubai Maritime City
8.3%
14 May 2026
33%-24.8behind31 Oct 2028under 10% built: too early to projectdubairealestateiq.com
Grand Polo - Montura 3
Emaar Properties · Grand Polo Club, Dubai Investment Park Second
1.1%
21 Apr 2026
26%-24.7behind30 Jun 2029under 10% built: too early to projectdubairealestateiq.com
Pier Point 2
Emaar Properties · Dubai Maritime City
8.5%
14 May 2026
33%-24.6behind31 Oct 2028under 10% built: too early to projectdubairealestateiq.com
Seapoint Residences
Emaar Properties · Emaar Beachfront
36.8%
24 Jun 2026
61%-24.4behind31 Mar 2028Apr 2031 – Jan 2032dubairealestateiq.com
Grand Polo - Montura 2
Emaar Properties · Grand Polo Club, Dubai Investment Park Second
5%
6 Jul 2026
29%-23.9behind31 May 2029under 10% built: too early to projectdubairealestateiq.com
Terra Heights
Emaar Properties · Madinat Al Mataar
9.1%
31 Jul 2026
33%-23.8behind31 Mar 2029under 10% built: too early to projectdubairealestateiq.com
Grand Polo - Chevalia Fields
Emaar Properties · Grand Polo Club, Dubai Investment Park Second
10%
21 Jul 2026
33%-22.8behind30 Apr 2029Sept 2037 – Sept 2038dubairealestateiq.com
The Oasis - Address Villas - Tierra
Emaar Properties · Me'Aisem Second
6.8%
21 Jul 2026
29%-22.2behind30 Jun 2029under 10% built: too early to projectdubairealestateiq.com
Grand Polo - Montura
Emaar Properties · Grand Polo Club, Dubai Investment Park Second
11.1%
5 Aug 2026
33%-21.4behind30 Jun 2029Dec 2036 – Oct 2037dubairealestateiq.com
Marina Place 1
Emaar Properties · Dubai Maritime City
4.2%
3 Apr 2026
26%-21.3behind31 Dec 2028under 10% built: too early to projectdubairealestateiq.com
Ocean Cove
Emaar Properties · Dubai Maritime City
17.9%
14 Apr 2026
38%-20.1behind31 Aug 2028Dec 2032 – Apr 2034dubairealestateiq.com
Golf Verge
Emaar Properties · Madinat Al Mataar
4.2%
22 Jul 2026
24%-20.1behind31 May 2029under 10% built: too early to projectdubairealestateiq.com
The Bristol Emaar Beachfront
Emaar Properties · Dubai Marina
5.8%
23 Jun 2026
26%-19.8behind30 Sept 2029under 10% built: too early to projectdubairealestateiq.com
The Valley - Elea
Emaar Properties · Al Yufrah 1
22%
15 Jul 2026
41%-19.2behind30 Jun 2028May 2031 – May 2032dubairealestateiq.com
Address the Bay
Emaar Properties · Dubai Marina
70.1%
15 Jul 2026
89%-18.7behind31 Dec 2026Feb 2028 – Apr 2028dubairealestateiq.com
Golf Meadow
Emaar Properties · Madinat Al Mataar
4.5%
19 Jul 2026
23%-18.6behind31 Jul 2029under 10% built: too early to projectdubairealestateiq.com
The Oasis - Lavita
Emaar Properties · Me'Aisem Second
20.1%
2 Jun 2026
39%-18.3behind31 Jan 2029Jan 2033 – Apr 2033dubairealestateiq.com
The St. Regis Residences, Downtown Dubai
Emaar Properties · Downtown Dubai
76.1%
2 Jun 2026
94%-18.2behind25 Dec 2026May 2029 – Jun 2029dubairealestateiq.com
The Valley - Kaia
Emaar Properties · Al Yufrah 1
19.1%
9 Jun 2026
37%-18.2behind31 Jul 2028Oct 2031 – Dec 2032dubairealestateiq.com
Sera 2
Emaar Properties · Dubai Maritime City
1.2%
11 Nov 2026
19%-17.6behind30 Nov 2029under 10% built: too early to projectdubairealestateiq.com
Palace Residences Hillside B
Emaar Properties · Hadaeq Sheikh Mohammed Bin Rashid
0%
30 Sept 2026
18%-17.5behind31 Oct 2029under 10% built: too early to projectdubairealestateiq.com
The Oasis - Palace Villas - Ostra
Emaar Properties · Me'Aisem Second
6.5%
20 Jul 2026
23%-16.5behind30 Sept 2029under 10% built: too early to projectdubairealestateiq.com
Greenway 2
Emaar Properties · Madinat Al Mataar
34.4%
29 Jul 2026
49%-14.6behind31 May 2028Dec 2029 – Aug 2030dubairealestateiq.com
Altan
Emaar Properties · Dubai Creek Harbour (Green Gate)
11.1%
2 Jul 2026
26%-14.5behind31 Jul 2029Jan 2035 – Feb 2041dubairealestateiq.com
Aurea
Emaar Properties · Dubai Maritime City
0.4%
9 Nov 2026
14%-13.9behind30 Jun 2030under 10% built: too early to projectdubairealestateiq.com
Albero
Emaar Properties · Al Khairan First
11%
2 Jul 2026
24%-13behind30 Sept 2029Oct 2034 – Oct 2036dubairealestateiq.com
The Oasis - Palmiera Collective
Emaar Properties · Me'Aisem Second
1.3%
16 Jun 2026
14%-12.9behind28 Feb 2029under 10% built: too early to projectdubairealestateiq.com
Rosehill
Emaar Properties · Dubai Hills Estate
7.8%
2 Jun 2026
21%-12.8behind30 Jun 2029under 10% built: too early to projectdubairealestateiq.com
Grand Polo - Selvara
Emaar Properties · Grand Polo Club, Dubai Investment Park Second
2.8%
14 May 2026
15%-12.3behind30 Apr 2029under 10% built: too early to projectdubairealestateiq.com
Parkwood
Emaar Properties · Hadaeq Sheikh Mohammed Bin Rashid
15%
7 May 2026
27%-12behind31 Jan 2029Feb 2032 – Aug 2033dubairealestateiq.com
Terra Gardens
Emaar Properties · Madinat Al Mataar
3.6%
4 Nov 2026
16%-11.9behind31 Oct 2029under 10% built: too early to projectdubairealestateiq.com
Vida Residences Hillside
Emaar Properties · Hadaeq Sheikh Mohammed Bin Rashid
10%
4 May 2026
22%-11.5behind31 May 2029Dec 2033 – May 2037dubairealestateiq.com
Greencrest
Emaar Properties · Hadaeq Sheikh Mohammed Bin Rashid
1.2%
7 May 2026
13%-11.4behind30 Jun 2029under 10% built: too early to projectdubairealestateiq.com
Silva
Emaar Properties · Al Khairan First
10.2%
19 Jul 2026
22%-11.4behind30 Sept 2029May 2034 – Apr 2037dubairealestateiq.com
Grand Polo - Selvara 4
Emaar Properties · Grand Polo Club, Dubai Investment Park Second
2.9%
6 May 2026
14%-11.3behind31 May 2029under 10% built: too early to projectdubairealestateiq.com
Grand Polo - Selvara 3
Emaar Properties · Grand Polo Club, Dubai Investment Park Second
3%
6 May 2026
14%-11.2behind31 May 2029under 10% built: too early to projectdubairealestateiq.com
Grand Polo - Selvara 2
Emaar Properties · Grand Polo Club, Dubai Investment Park Second
4%
14 May 2026
15%-11.1behind30 Apr 2029under 10% built: too early to projectdubairealestateiq.com
Golf Hills 2
Emaar Properties · Madinat Al Mataar
4.2%
20 Jul 2026
15%-10.6behind30 Sept 2029under 10% built: too early to projectdubairealestateiq.com
The Valley - Alva
Emaar Properties · Al Yufrah 1
0%
27 Aug 2026
10%-10.2behind31 Mar 2030under 10% built: too early to projectdubairealestateiq.com
Address Residences L Dubai Hills Estate
Emaar Properties · Hadaeq Sheikh Mohammed Bin Rashid
26.5%
10 Jun 2026
36%-9.2on pace or ahead28 Feb 2029Aug 2030 – Jun 2031dubairealestateiq.com
Golf Hills
Emaar Properties · Madinat Al Mataar
3.7%
23 Jun 2026
13%-9.1on pace or ahead30 Sept 2029under 10% built: too early to projectdubairealestateiq.com
Golf Fields
Emaar Properties · Madinat Al Mataar
0%
6 Aug 2026
9%-8.6on pace or ahead28 Feb 2030under 10% built: too early to projectdubairealestateiq.com
Palace Residences Creek Blue
Emaar Properties · Al Khairan First
40.2%
5 Nov 2026
49%-8.3on pace or ahead31 Mar 2029Mar 2030 – May 2030dubairealestateiq.com
Palace Residences Hillside A
Emaar Properties · Hadaeq Sheikh Mohammed Bin Rashid
7.9%
5 May 2026
16%-8on pace or ahead30 Jun 2029under 10% built: too early to projectdubairealestateiq.com
Sera 1
Emaar Properties · Dubai Maritime City
0%
2 Jun 2026
7%-7on pace or ahead30 Nov 2029under 10% built: too early to projectdubairealestateiq.com
The Valley - Avena 2
Emaar Properties · Al Yufrah 1
42.9%
20 Jul 2026
50%-6.6on pace or ahead31 Jul 2028Mar 2029 – Mar 2029dubairealestateiq.com
Grand Polo - Chevalia Estate 2
Emaar Properties · Grand Polo Club, Dubai Investment Park Second
4.1%
25 Jun 2026
11%-6.4on pace or ahead30 Jun 2029under 10% built: too early to projectdubairealestateiq.com

Next page

Method

Time elapsed = (inspection date minus construction start on the register) divided by (registered completion date minus construction start). When no start date is printed, the registration date is used.

Gap = % built at the inspection minus % of time elapsed at the same date, in percentage points. Behind = a gap below -10 points. Registered date passed = the inspection is after the completion date on the register and the project is not at 100%.

Projection, only for 10% to 99% built: the remaining % divided by the observed pace, where the pace is % built per day since the start date, since the registration date and between the last two inspections we hold (when it rose). The range runs from the earliest to the latest of these estimates.

Limits: Construction does not move in a straight line (a slow start, faster structure, slow finishing), so a straight line from an early reading tends to give later dates than the work will need, and a late reading can give earlier ones. The % built is the DLD inspection figure, not ours.

Source: the Dubai Land Department project register as mirrored per project with its inspection history, read by our register job; 929 DLD records, 28 with two or more dated inspections.

Files: /data/n35a/pace.json · /open/n35a-build.py · /registers/changes/