Home / Dubai / Construction pace against the registered date
Construction pace against the registered date
For Dubai projects with DLD inspection readings: % built against the share of time elapsed to the completion date on the register, and the completion range the observed pace points to. A projection, not a promise.
Updated 23 Nov 2026
A projection from the pace on the register, not a promise, and not a finding about the developer.
Show as a table
| Gap (points) | Projects |
|---|---|
| -60 … -50 | 98 |
| -50 … -40 | 119 |
| -40 … -30 | 168 |
| -30 … -20 | 186 |
| -20 … -10 | 140 |
| -10 … 0 | 94 |
| 0 … 10 | 29 |
| 10 … 20 | 13 |
| 20 … 30 | 9 |
| 30 … 40 | 3 |
| 40 … 50 | 1 |
Projects
Developer: emaar-properties · All
| Project | % built (inspection) | Time elapsed | Gap (points) | Pace | Registered completion | Projected range | Register |
|---|---|---|---|---|---|---|---|
| Montiva by Vida Emaar Properties · Dubai Creek Harbour | 5.9% 22 Apr 2026 | 12% | -6.3 | on pace or ahead | 30 Sept 2029 | under 10% built: too early to project | dubairealestateiq.com |
| The Valley - Ovelle Emaar Properties · Al Yufrah 1 | 2.4% 16 Jun 2026 | 9% | -6.3 | on pace or ahead | 31 Dec 2029 | under 10% built: too early to project | dubairealestateiq.com |
| Mareva 2 the Oasis Emaar Properties · Me'Aisem Second | 1.3% 6 Jul 2026 | 7% | -6 | on pace or ahead | 28 Feb 2030 | under 10% built: too early to project | dubairealestateiq.com |
| The Valley - Avelia Emaar Properties · Al Yufrah 1 | 0.3% 9 Jun 2026 | 6% | -5.9 | on pace or ahead | 31 Dec 2029 | under 10% built: too early to project | dubairealestateiq.com |
| Baystar by Vida Emaar Properties · Dubai Maritime City | 6.3% 16 Jun 2026 | 12% | -5.6 | on pace or ahead | 31 Dec 2029 | under 10% built: too early to project | dubairealestateiq.com |
| Grand Polo - Equiterra 2 Emaar Properties · Grand Polo Club, Dubai Investment Park Second | 1% 29 Apr 2026 | 6% | -5.2 | on pace or ahead | 31 Jul 2029 | under 10% built: too early to project | dubairealestateiq.com |
| Serro the Heights Emaar Properties · Al Yelayiss 5 | 0.5% 9 Jun 2026 | 6% | -5.1 | on pace or ahead | 31 Mar 2030 | under 10% built: too early to project | dubairealestateiq.com |
| Creek Haven Emaar Properties · Al Khairan First | 0.9% 16 Jun 2026 | 6% | -5 | on pace or ahead | 31 Mar 2030 | under 10% built: too early to project | dubairealestateiq.com |
| Lyvia by Palace Emaar Properties · Al Khairan First | 4.8% 17 Mar 2026 | 10% | -4.8 | on pace or ahead | 31 Jul 2029 | under 10% built: too early to project | dubairealestateiq.com |
| The Valley - Avena Emaar Properties · Al Yufrah 1 | 54.4% 5 Nov 2026 | 59% | -4.5 | on pace or ahead | 30 Jun 2028 | Oct 2028 – Oct 2028 | dubairealestateiq.com |
| Creek Bay Emaar Properties · Al Khairan First | 0.6% 16 Jun 2026 | 5% | -4.5 | on pace or ahead | 30 Apr 2030 | under 10% built: too early to project | dubairealestateiq.com |
| Grand Polo - Equiterra Emaar Properties · Grand Polo Club, Dubai Investment Park Second | 0.8% 14 May 2026 | 5% | -4.4 | on pace or ahead | 31 Aug 2029 | under 10% built: too early to project | dubairealestateiq.com |
| Valia Emaar Properties · Dubai Creek Harbour | 0% 6 Aug 2026 | 4% | -3.9 | on pace or ahead | 31 Aug 2030 | under 10% built: too early to project | dubairealestateiq.com |
| Mareva the Oasis Emaar Properties · Me'Aisem Second | 2.1% 16 Jun 2026 | 6% | -3.9 | on pace or ahead | 28 Feb 2030 | under 10% built: too early to project | dubairealestateiq.com |
| The Valley - Velora 2 Emaar Properties · Al Yufrah 1 | 40.3% 6 Jul 2026 | 44% | -3.6 | on pace or ahead | 31 Jul 2028 | Nov 2028 – Jun 2029 | dubairealestateiq.com |
| Hillsedge Emaar Properties · Hadaeq Sheikh Mohammed Bin Rashid | 25.6% 6 Jun 2026 | 29% | -3.6 | on pace or ahead | 31 Jan 2029 | Aug 2029 – Nov 2030 | dubairealestateiq.com |
| Palace Residences Dubai Hills Estate Emaar Properties · Dubai Hills Estate | 50.7% 16 Jun 2026 | 54% | -3.4 | on pace or ahead | 30 Apr 2028 | Aug 2028 – Nov 2028 | dubairealestateiq.com |
| Serro 2 the Heights Emaar Properties · Al Yelayiss 5 | 0.5% 9 Jun 2026 | 4% | -3 | on pace or ahead | 31 May 2030 | under 10% built: too early to project | dubairealestateiq.com |
| Park Gate 2 Emaar Properties · Hadaeq Sheikh Mohammed Bin Rashid | 55.2% 8 Jun 2026 | 57% | -2.2 | on pace or ahead | 28 Feb 2027 | Mar 2027 – May 2027 | dubairealestateiq.com |
| Avarra by Palace Emaar Properties · Business Bay | 0.1% 10 Jun 2026 | 1% | -1.3 | on pace or ahead | 30 Jun 2031 | under 10% built: too early to project | dubairealestateiq.com |
| Salva the Heights Emaar Properties · Al Yelayiss 5 | 0.5% 9 Jun 2026 | 1% | -0.9 | on pace or ahead | 31 Jul 2030 | under 10% built: too early to project | dubairealestateiq.com |
| Greenridge Emaar Properties · Madinat Al Mataar | 35.6% 17 Jun 2026 | 35% | 0.4 | on pace or ahead | 31 Dec 2028 | Dec 2028 – Aug 2029 | dubairealestateiq.com |
| Bayview Emaar Properties · Dubai Marina | 63% 14 Sept 2026 | 61% | 2.2 | on pace or ahead | 31 Jul 2028 | May 2028 – Aug 2028 | dubairealestateiq.com |
| Marina Shores Emaar Properties · Dubai Marina | 87.2% 14 May 2026 | 84% | 2.9 | on pace or ahead | 31 Dec 2026 | Nov 2026 – Dec 2026 | dubairealestateiq.com |
| Fairway Villas 2 Emaar Properties · Madinat Al Mataar | 92.2% 17 Aug 2026 | 89% | 3 | on pace or ahead | 31 Dec 2026 | Nov 2026 – Nov 2026 | dubairealestateiq.com |
| Vida Residences Club Point Emaar Properties · Hadaeq Sheikh Mohammed Bin Rashid | 43.5% 3 Aug 2026 | 40% | 3.2 | on pace or ahead | 28 Feb 2029 | Nov 2028 – Dec 2028 | dubairealestateiq.com |
| Address Residences Dubai Creek Harbour Emaar Properties · Dubai Creek Harbour | 50.1% 16 Nov 2026 | 47% | 3.5 | on pace or ahead | 31 Jan 2029 | Jan 2028 – Feb 2029 | dubairealestateiq.com |
| The Valley - Elva Emaar Properties · Al Yufrah 1 | 49.9% 11 Nov 2026 | 46% | 3.6 | on pace or ahead | 31 Oct 2028 | Jul 2028 – Sept 2028 | dubairealestateiq.com |
| Greenspoint 2 Emaar Properties · Madinat Al Mataar | 40.1% 3 Aug 2026 | 36% | 3.9 | on pace or ahead | 31 Mar 2029 | Oct 2028 – Nov 2028 | dubairealestateiq.com |
| The Valley - Venera Emaar Properties · Al Yufrah 1 | 51.7% 5 Aug 2026 | 46% | 5.3 | on pace or ahead | 30 Sept 2028 | May 2028 – Jul 2028 | dubairealestateiq.com |
| The Valley - Velora Emaar Properties · Al Yufrah 1 | 50.1% 9 Jun 2026 | 45% | 5.5 | on pace or ahead | 31 Aug 2028 | Mar 2028 – May 2028 | dubairealestateiq.com |
| Park Lane Emaar Properties · Hadaeq Sheikh Mohammed Bin Rashid | 55.4% 22 May 2026 | 49% | 6.2 | on pace or ahead | 31 Oct 2028 | Apr 2028 – Jun 2028 | dubairealestateiq.com |
| The Valley - Rivana Emaar Properties · Al Yufrah 1 | 95.2% 28 Oct 2026 | 88% | 7.1 | on pace or ahead | 31 Mar 2027 | Dec 2026 – Dec 2026 | dubairealestateiq.com |
| Greenspoint Emaar Properties · Madinat Al Mataar | 42.9% 21 Jul 2026 | 35% | 7.6 | on pace or ahead | 31 Mar 2029 | Jul 2028 – Jul 2028 | dubairealestateiq.com |
| Creek Waters Emaar Properties · Al Khairan First | 81.1% 3 Aug 2026 | 72% | 9.1 | on pace or ahead | 30 Sept 2027 | Apr 2027 – May 2027 | dubairealestateiq.com |
| Parkland Emaar Properties · Hadaeq Sheikh Mohammed Bin Rashid | 50% 22 Jun 2026 | 40% | 9.9 | on pace or ahead | 30 Nov 2028 | Feb 2028 – May 2028 | dubairealestateiq.com |
| Greenville 2 Emaar Properties · Madinat Al Mataar | 47.3% 19 Jul 2026 | 35% | 12.1 | on pace or ahead | 31 Mar 2029 | Mar 2028 – Jul 2028 | dubairealestateiq.com |
| Creek Waters 2 Emaar Properties · Dubai Creek Harbour | 81.8% 31 Jul 2026 | 68% | 14.4 | on pace or ahead | 31 Dec 2027 | Mar 2027 – Apr 2027 | dubairealestateiq.com |
| Greenville Emaar Properties · Madinat Al Mataar | 46% 14 May 2026 | 31% | 15.2 | on pace or ahead | 31 Mar 2029 | Nov 2027 – Apr 2028 | dubairealestateiq.com |
| Parkside Hills Emaar Properties · Dubai Hills Estate | 68.3% 7 May 2026 | 53% | 15.6 | on pace or ahead | 30 Jun 2028 | Jun 2027 – Aug 2027 | dubairealestateiq.com |
| Golf Hillside Emaar Properties · Hadaeq Sheikh Mohammed Bin Rashid | 65.8% 11 Aug 2026 | 43% | 22.6 | on pace or ahead | 31 Dec 2028 | Jul 2027 – Aug 2027 | dubairealestateiq.com |
| Club Place Emaar Properties · Dubai Hills Estate | 68.8% 16 Jun 2026 | 41% | 27.9 | on pace or ahead | 31 Dec 2028 | Apr 2027 – Apr 2027 | dubairealestateiq.com |
| The Oasis - Palmiera 3 Emaar Properties · Me'Aisem Second | 72.6% 9 Jun 2026 | 43% | 29.8 | on pace or ahead | 31 Oct 2028 | Feb 2027 – Feb 2027 | dubairealestateiq.com |
| Altus Emaar Properties · Al Khairan First | 86.5% 10 Nov 2026 | 47% | 40 | on pace or ahead | 31 Jan 2029 | Feb 2027 – Mar 2027 | dubairealestateiq.com |
| Golf Vale Emaar Properties · Emaar South / Expo City | 0% 24 Feb 2026 | - | - | not comparable | 31 Mar 2030 | under 10% built: too early to project | dubairealestateiq.com |
| Club Drive Emaar Properties · Dubai Hills Estate | 100% 19 Oct 2026 | - | - | not comparable | - | no projection | dubairealestateiq.com |
| Golf Edge Emaar Properties · Madinat Al Mataar | 0% 5 Nov 2024 | - | - | not comparable | 28 Feb 2029 | under 10% built: too early to project | dubairealestateiq.com |
| Grand Polo - Equestra Emaar Properties · Grand Polo Club, Dubai Investment Park Second | 1% 4 May 2026 | - | - | not comparable | 31 Aug 2029 | under 10% built: too early to project | dubairealestateiq.com |
| Grove Ridge Emaar Properties · Madinat Al Mataar | 0% 4 Nov 2025 | - | - | not comparable | 30 Sept 2029 | under 10% built: too early to project | dubairealestateiq.com |
| Vista Ridge Emaar Properties · Madinat Al Mataar | 0% 4 Nov 2025 | - | - | not comparable | 30 Sept 2029 | under 10% built: too early to project | dubairealestateiq.com |
| Terra Woods Emaar Properties · Madinat Al Mataar | 0% 28 Jan 2026 | - | - | not comparable | 31 Mar 2030 | under 10% built: too early to project | dubairealestateiq.com |
| Fior 1 Emaar Properties · Dubai Maritime City | 0% 11 Dec 2025 | - | - | not comparable | 31 Jul 2030 | under 10% built: too early to project | dubairealestateiq.com |
| Golf Trails Emaar Properties · Madinat Al Mataar | 0% 1 Jul 2026 | - | - | not comparable | 31 Oct 2030 | under 10% built: too early to project | dubairealestateiq.com |
| Palace by the Beach Emaar Properties · Dubai Marina | 0% 12 Jan 2026 | - | - | not comparable | 30 Nov 2031 | under 10% built: too early to project | dubairealestateiq.com |
Method
Time elapsed = (inspection date minus construction start on the register) divided by (registered completion date minus construction start). When no start date is printed, the registration date is used.
Gap = % built at the inspection minus % of time elapsed at the same date, in percentage points. Behind = a gap below -10 points. Registered date passed = the inspection is after the completion date on the register and the project is not at 100%.
Projection, only for 10% to 99% built: the remaining % divided by the observed pace, where the pace is % built per day since the start date, since the registration date and between the last two inspections we hold (when it rose). The range runs from the earliest to the latest of these estimates.
Limits: Construction does not move in a straight line (a slow start, faster structure, slow finishing), so a straight line from an early reading tends to give later dates than the work will need, and a late reading can give earlier ones. The % built is the DLD inspection figure, not ours.
Source: the Dubai Land Department project register as mirrored per project with its inspection history, read by our register job; 985 DLD records, 28 with two or more dated inspections.
Files: /data/n35a/pace.json · /open/n35a-build.py · /registers/changes/