Home / Dubai / Construction pace against the registered date

Construction pace against the registered date

For Dubai projects with DLD inspection readings: % built against the share of time elapsed to the completion date on the register, and the completion range the observed pace points to. A projection, not a promise.

Updated 23 Nov 2026

A projection from the pace on the register, not a promise, and not a finding about the developer.

860projects compared (DLD % built and dates on the register)
82.7%more than 10 points behind the time elapsed (95% interval 80 to 85.1%)
-27median gap in points, % built minus % of time elapsed (95% interval -29.1 to -26)
452projects with a projected range (10% to 99% built)
86.7%of them projected after the registered date (95% interval 83.3 to 89.5%)
≤-6098-50119-40168-30186-20140-10940291013209303401
Projects by gap between % built and % of time elapsed, in 10-point bins
Show as a table
Gap (points)Projects
-60 … -5098
-50 … -40119
-40 … -30168
-30 … -20186
-20 … -10140
-10 … 094
0 … 1029
10 … 2013
20 … 309
30 … 403
40 … 501

Projects

Developer: emaar-properties · All

114 projects, page 2
Project% built (inspection)Time elapsedGap (points)PaceRegistered completionProjected rangeRegister
Montiva by Vida
Emaar Properties · Dubai Creek Harbour
5.9%
22 Apr 2026
12%-6.3on pace or ahead30 Sept 2029under 10% built: too early to projectdubairealestateiq.com
The Valley - Ovelle
Emaar Properties · Al Yufrah 1
2.4%
16 Jun 2026
9%-6.3on pace or ahead31 Dec 2029under 10% built: too early to projectdubairealestateiq.com
Mareva 2 the Oasis
Emaar Properties · Me'Aisem Second
1.3%
6 Jul 2026
7%-6on pace or ahead28 Feb 2030under 10% built: too early to projectdubairealestateiq.com
The Valley - Avelia
Emaar Properties · Al Yufrah 1
0.3%
9 Jun 2026
6%-5.9on pace or ahead31 Dec 2029under 10% built: too early to projectdubairealestateiq.com
Baystar by Vida
Emaar Properties · Dubai Maritime City
6.3%
16 Jun 2026
12%-5.6on pace or ahead31 Dec 2029under 10% built: too early to projectdubairealestateiq.com
Grand Polo - Equiterra 2
Emaar Properties · Grand Polo Club, Dubai Investment Park Second
1%
29 Apr 2026
6%-5.2on pace or ahead31 Jul 2029under 10% built: too early to projectdubairealestateiq.com
Serro the Heights
Emaar Properties · Al Yelayiss 5
0.5%
9 Jun 2026
6%-5.1on pace or ahead31 Mar 2030under 10% built: too early to projectdubairealestateiq.com
Creek Haven
Emaar Properties · Al Khairan First
0.9%
16 Jun 2026
6%-5on pace or ahead31 Mar 2030under 10% built: too early to projectdubairealestateiq.com
Lyvia by Palace
Emaar Properties · Al Khairan First
4.8%
17 Mar 2026
10%-4.8on pace or ahead31 Jul 2029under 10% built: too early to projectdubairealestateiq.com
The Valley - Avena
Emaar Properties · Al Yufrah 1
54.4%
5 Nov 2026
59%-4.5on pace or ahead30 Jun 2028Oct 2028 – Oct 2028dubairealestateiq.com
Creek Bay
Emaar Properties · Al Khairan First
0.6%
16 Jun 2026
5%-4.5on pace or ahead30 Apr 2030under 10% built: too early to projectdubairealestateiq.com
Grand Polo - Equiterra
Emaar Properties · Grand Polo Club, Dubai Investment Park Second
0.8%
14 May 2026
5%-4.4on pace or ahead31 Aug 2029under 10% built: too early to projectdubairealestateiq.com
Valia
Emaar Properties · Dubai Creek Harbour
0%
6 Aug 2026
4%-3.9on pace or ahead31 Aug 2030under 10% built: too early to projectdubairealestateiq.com
Mareva the Oasis
Emaar Properties · Me'Aisem Second
2.1%
16 Jun 2026
6%-3.9on pace or ahead28 Feb 2030under 10% built: too early to projectdubairealestateiq.com
The Valley - Velora 2
Emaar Properties · Al Yufrah 1
40.3%
6 Jul 2026
44%-3.6on pace or ahead31 Jul 2028Nov 2028 – Jun 2029dubairealestateiq.com
Hillsedge
Emaar Properties · Hadaeq Sheikh Mohammed Bin Rashid
25.6%
6 Jun 2026
29%-3.6on pace or ahead31 Jan 2029Aug 2029 – Nov 2030dubairealestateiq.com
Palace Residences Dubai Hills Estate
Emaar Properties · Dubai Hills Estate
50.7%
16 Jun 2026
54%-3.4on pace or ahead30 Apr 2028Aug 2028 – Nov 2028dubairealestateiq.com
Serro 2 the Heights
Emaar Properties · Al Yelayiss 5
0.5%
9 Jun 2026
4%-3on pace or ahead31 May 2030under 10% built: too early to projectdubairealestateiq.com
Park Gate 2
Emaar Properties · Hadaeq Sheikh Mohammed Bin Rashid
55.2%
8 Jun 2026
57%-2.2on pace or ahead28 Feb 2027Mar 2027 – May 2027dubairealestateiq.com
Avarra by Palace
Emaar Properties · Business Bay
0.1%
10 Jun 2026
1%-1.3on pace or ahead30 Jun 2031under 10% built: too early to projectdubairealestateiq.com
Salva the Heights
Emaar Properties · Al Yelayiss 5
0.5%
9 Jun 2026
1%-0.9on pace or ahead31 Jul 2030under 10% built: too early to projectdubairealestateiq.com
Greenridge
Emaar Properties · Madinat Al Mataar
35.6%
17 Jun 2026
35%0.4on pace or ahead31 Dec 2028Dec 2028 – Aug 2029dubairealestateiq.com
Bayview
Emaar Properties · Dubai Marina
63%
14 Sept 2026
61%2.2on pace or ahead31 Jul 2028May 2028 – Aug 2028dubairealestateiq.com
Marina Shores
Emaar Properties · Dubai Marina
87.2%
14 May 2026
84%2.9on pace or ahead31 Dec 2026Nov 2026 – Dec 2026dubairealestateiq.com
Fairway Villas 2
Emaar Properties · Madinat Al Mataar
92.2%
17 Aug 2026
89%3on pace or ahead31 Dec 2026Nov 2026 – Nov 2026dubairealestateiq.com
Vida Residences Club Point
Emaar Properties · Hadaeq Sheikh Mohammed Bin Rashid
43.5%
3 Aug 2026
40%3.2on pace or ahead28 Feb 2029Nov 2028 – Dec 2028dubairealestateiq.com
Address Residences Dubai Creek Harbour
Emaar Properties · Dubai Creek Harbour
50.1%
16 Nov 2026
47%3.5on pace or ahead31 Jan 2029Jan 2028 – Feb 2029dubairealestateiq.com
The Valley - Elva
Emaar Properties · Al Yufrah 1
49.9%
11 Nov 2026
46%3.6on pace or ahead31 Oct 2028Jul 2028 – Sept 2028dubairealestateiq.com
Greenspoint 2
Emaar Properties · Madinat Al Mataar
40.1%
3 Aug 2026
36%3.9on pace or ahead31 Mar 2029Oct 2028 – Nov 2028dubairealestateiq.com
The Valley - Venera
Emaar Properties · Al Yufrah 1
51.7%
5 Aug 2026
46%5.3on pace or ahead30 Sept 2028May 2028 – Jul 2028dubairealestateiq.com
The Valley - Velora
Emaar Properties · Al Yufrah 1
50.1%
9 Jun 2026
45%5.5on pace or ahead31 Aug 2028Mar 2028 – May 2028dubairealestateiq.com
Park Lane
Emaar Properties · Hadaeq Sheikh Mohammed Bin Rashid
55.4%
22 May 2026
49%6.2on pace or ahead31 Oct 2028Apr 2028 – Jun 2028dubairealestateiq.com
The Valley - Rivana
Emaar Properties · Al Yufrah 1
95.2%
28 Oct 2026
88%7.1on pace or ahead31 Mar 2027Dec 2026 – Dec 2026dubairealestateiq.com
Greenspoint
Emaar Properties · Madinat Al Mataar
42.9%
21 Jul 2026
35%7.6on pace or ahead31 Mar 2029Jul 2028 – Jul 2028dubairealestateiq.com
Creek Waters
Emaar Properties · Al Khairan First
81.1%
3 Aug 2026
72%9.1on pace or ahead30 Sept 2027Apr 2027 – May 2027dubairealestateiq.com
Parkland
Emaar Properties · Hadaeq Sheikh Mohammed Bin Rashid
50%
22 Jun 2026
40%9.9on pace or ahead30 Nov 2028Feb 2028 – May 2028dubairealestateiq.com
Greenville 2
Emaar Properties · Madinat Al Mataar
47.3%
19 Jul 2026
35%12.1on pace or ahead31 Mar 2029Mar 2028 – Jul 2028dubairealestateiq.com
Creek Waters 2
Emaar Properties · Dubai Creek Harbour
81.8%
31 Jul 2026
68%14.4on pace or ahead31 Dec 2027Mar 2027 – Apr 2027dubairealestateiq.com
Greenville
Emaar Properties · Madinat Al Mataar
46%
14 May 2026
31%15.2on pace or ahead31 Mar 2029Nov 2027 – Apr 2028dubairealestateiq.com
Parkside Hills
Emaar Properties · Dubai Hills Estate
68.3%
7 May 2026
53%15.6on pace or ahead30 Jun 2028Jun 2027 – Aug 2027dubairealestateiq.com
Golf Hillside
Emaar Properties · Hadaeq Sheikh Mohammed Bin Rashid
65.8%
11 Aug 2026
43%22.6on pace or ahead31 Dec 2028Jul 2027 – Aug 2027dubairealestateiq.com
Club Place
Emaar Properties · Dubai Hills Estate
68.8%
16 Jun 2026
41%27.9on pace or ahead31 Dec 2028Apr 2027 – Apr 2027dubairealestateiq.com
The Oasis - Palmiera 3
Emaar Properties · Me'Aisem Second
72.6%
9 Jun 2026
43%29.8on pace or ahead31 Oct 2028Feb 2027 – Feb 2027dubairealestateiq.com
Altus
Emaar Properties · Al Khairan First
86.5%
10 Nov 2026
47%40on pace or ahead31 Jan 2029Feb 2027 – Mar 2027dubairealestateiq.com
Golf Vale
Emaar Properties · Emaar South / Expo City
0%
24 Feb 2026
--not comparable31 Mar 2030under 10% built: too early to projectdubairealestateiq.com
Club Drive
Emaar Properties · Dubai Hills Estate
100%
19 Oct 2026
--not comparable-no projectiondubairealestateiq.com
Golf Edge
Emaar Properties · Madinat Al Mataar
0%
5 Nov 2024
--not comparable28 Feb 2029under 10% built: too early to projectdubairealestateiq.com
Grand Polo - Equestra
Emaar Properties · Grand Polo Club, Dubai Investment Park Second
1%
4 May 2026
--not comparable31 Aug 2029under 10% built: too early to projectdubairealestateiq.com
Grove Ridge
Emaar Properties · Madinat Al Mataar
0%
4 Nov 2025
--not comparable30 Sept 2029under 10% built: too early to projectdubairealestateiq.com
Vista Ridge
Emaar Properties · Madinat Al Mataar
0%
4 Nov 2025
--not comparable30 Sept 2029under 10% built: too early to projectdubairealestateiq.com
Terra Woods
Emaar Properties · Madinat Al Mataar
0%
28 Jan 2026
--not comparable31 Mar 2030under 10% built: too early to projectdubairealestateiq.com
Fior 1
Emaar Properties · Dubai Maritime City
0%
11 Dec 2025
--not comparable31 Jul 2030under 10% built: too early to projectdubairealestateiq.com
Golf Trails
Emaar Properties · Madinat Al Mataar
0%
1 Jul 2026
--not comparable31 Oct 2030under 10% built: too early to projectdubairealestateiq.com
Palace by the Beach
Emaar Properties · Dubai Marina
0%
12 Jan 2026
--not comparable30 Nov 2031under 10% built: too early to projectdubairealestateiq.com

Method

Time elapsed = (inspection date minus construction start on the register) divided by (registered completion date minus construction start). When no start date is printed, the registration date is used.

Gap = % built at the inspection minus % of time elapsed at the same date, in percentage points. Behind = a gap below -10 points. Registered date passed = the inspection is after the completion date on the register and the project is not at 100%.

Projection, only for 10% to 99% built: the remaining % divided by the observed pace, where the pace is % built per day since the start date, since the registration date and between the last two inspections we hold (when it rose). The range runs from the earliest to the latest of these estimates.

Limits: Construction does not move in a straight line (a slow start, faster structure, slow finishing), so a straight line from an early reading tends to give later dates than the work will need, and a late reading can give earlier ones. The % built is the DLD inspection figure, not ours.

Source: the Dubai Land Department project register as mirrored per project with its inspection history, read by our register job; 985 DLD records, 28 with two or more dated inspections.