Home / Dubai / Construction pace against the registered date

Construction pace against the registered date

For Dubai projects with DLD inspection readings: % built against the share of time elapsed to the completion date on the register, and the completion range the observed pace points to. A projection, not a promise.

Updated 23 Nov 2026

A projection from the pace on the register, not a promise, and not a finding about the developer.

815projects compared (DLD % built and dates on the register)
82.8%more than 10 points behind the time elapsed (95% interval 80.1 to 85.3%)
-27.1median gap in points, % built minus % of time elapsed (95% interval -29.5 to -26)
426projects with a projected range (10% to 99% built)
87.1%of them projected after the registered date (95% interval 83.6 to 89.9%)
≤-6090-50115-40162-30178-20130-10900291012207301401
Projects by gap between % built and % of time elapsed, in 10-point bins
Show as a table
Gap (points)Projects
-60 … -5090
-50 … -40115
-40 … -30162
-30 … -20178
-20 … -10130
-10 … 090
0 … 1029
10 … 2012
20 … 307
30 … 401
40 … 501

Projects

Developer: azizi-developments · All

44 projects, page 1
Project% built (inspection)Time elapsedGap (points)PaceRegistered completionProjected rangeRegister
Azizi Milan 51
Azizi Developments · City of Arabia
0%
5 Nov 2026
81%-80.7behind26 Mar 2027under 10% built: too early to projectdubairealestateiq.com
Azizi Milan 30
Azizi Developments · City of Arabia
0%
5 Nov 2026
80%-79.5behind4 Apr 2027under 10% built: too early to projectdubairealestateiq.com
Azizi Milan 18
Azizi Developments · City of Arabia
0%
5 Nov 2026
78%-77.8behind16 Apr 2027under 10% built: too early to projectdubairealestateiq.com
Azizi Milan 20
Azizi Developments · City of Arabia
0%
5 Nov 2026
77%-76.6behind30 Apr 2027under 10% built: too early to projectdubairealestateiq.com
Azizi Milan 53
Azizi Developments · City of Arabia
0%
5 Nov 2026
76%-76.3behind30 Apr 2027under 10% built: too early to projectdubairealestateiq.com
Azizi Milan 55
Azizi Developments · City of Arabia
0%
5 Nov 2026
76%-76.3behind30 Apr 2027under 10% built: too early to projectdubairealestateiq.com
Azizi Milan 9
Azizi Developments · City of Arabia
0%
5 Nov 2026
73%-72.9behind30 May 2027under 10% built: too early to projectdubairealestateiq.com
Azizi Milan 28
Azizi Developments · City of Arabia
0%
5 Nov 2026
71%-71.2behind3 Jun 2027under 10% built: too early to projectdubairealestateiq.com
Azizi Venice 16
Azizi Developments · Madinat Al Mataar
3.7%
16 Nov 2026
73%-69.2behind2 Jun 2027under 10% built: too early to projectdubairealestateiq.com
Azizi Ruby
Azizi Developments · Jumeirah Village Circle
4.1%
17 Nov 2026
61%-56.4behind23 Jan 2028under 10% built: too early to projectdubairealestateiq.com
Azizi Emerald
Azizi Developments · Um Hurair Second
3%
17 Nov 2026
59%-55.6behind13 Feb 2028under 10% built: too early to projectdubairealestateiq.com
Azizi Venice 12
Azizi Developments · Madinat Al Mataar
21.6%
15 Oct 2026
69%-46.9behind25 Sept 2027Dec 2033 – Mar 2034dubairealestateiq.com
Azizi Venice 11
Azizi Developments · Madinat Al Mataar
25.9%
9 Sept 2026
68%-42.1behind30 Aug 2027Jun 2032 – Aug 2032dubairealestateiq.com
Azizi Milan Heights
Azizi Developments · City of Arabia
0%
5 Nov 2026
39%-38.6behind8 Sept 2028under 10% built: too early to projectdubairealestateiq.com
Raffi by Azizi
Azizi Developments · Jabal Ali First
2%
25 Mar 2026
40%-37.6behind15 Jan 2028under 10% built: too early to projectdubairealestateiq.com
Arian by Azizi
Azizi Developments · Jabal Ali Industrial Second
2%
24 Mar 2026
40%-37.5behind16 Jan 2028under 10% built: too early to projectdubairealestateiq.com
Azizi Sikander
Azizi Developments · Jabal Ali First
2%
18 Mar 2026
38%-35.5behind17 Jun 2027under 10% built: too early to projectdubairealestateiq.com
Azizi Amir
Azizi Developments · Jabal Ali First
2.4%
18 Mar 2026
38%-35.2behind17 Jun 2027under 10% built: too early to projectdubairealestateiq.com
Azizi Neila
Azizi Developments · Jabal Ali First
38.5%
5 Oct 2026
73%-34.4behind30 Jul 2027Feb 2030 – Apr 2030dubairealestateiq.com
Wasl by Azizi
Azizi Developments · Palm Deira
2%
18 Mar 2026
36%-34.4behind12 Feb 2028under 10% built: too early to projectdubairealestateiq.com
Azizi Venice 6
Azizi Developments · Madinat Al Mataar
11.6%
8 May 2026
45%-33.7behind31 Dec 2027Mar 2036 – Oct 2036dubairealestateiq.com
Azizi Wares
Azizi Developments · Jabal Ali Industrial Second
2%
16 Nov 2026
35%-33.2behind4 Mar 2028under 10% built: too early to projectdubairealestateiq.com
Azizi Lina
Azizi Developments · Jabal Ali Industrial Second
2.4%
16 Nov 2026
30%-27.1behind30 Sept 2028under 10% built: too early to projectdubairealestateiq.com
Burj Azizi
Azizi Developments · Trade Center First
7.5%
3 Sept 2026
34%-26.3behind30 Aug 2030under 10% built: too early to projectdubairealestateiq.com
Azizi Leily
Azizi Developments · Al Jadaf
2%
5 Nov 2026
26%-24.1behind30 Sept 2028under 10% built: too early to projectdubairealestateiq.com
Azizi Venice 13
Azizi Developments · Madinat Al Mataar
45.9%
14 Oct 2026
69%-23.4behind16 Sept 2027Mar 2029 – Mar 2029dubairealestateiq.com
Azizi Noura
Azizi Developments · Jabal Ali Industrial Second
2.1%
16 Nov 2026
19%-16.3behind4 Jul 2028under 10% built: too early to projectdubairealestateiq.com
Azizi Riviera 49
Azizi Developments · Al Merkadh
54.4%
7 Aug 2026
70%-15.7behind13 Mar 2027May 2027 – Oct 2027dubairealestateiq.com
Azizi Riviera 50
Azizi Developments · Al Merkadh
60.9%
7 Aug 2026
70%-9.2on pace or ahead13 Mar 2027Feb 2027 – Jul 2027dubairealestateiq.com
Azizi Riviera 53
Azizi Developments · Al Merkadh
63.2%
30 Jul 2026
69%-5.9on pace or ahead13 Mar 2027Jan 2027 – May 2027dubairealestateiq.com
Azizi David
Azizi Developments · Al Jadaf
2%
24 Mar 2026
5%-3.1on pace or ahead30 Sept 2028under 10% built: too early to projectdubairealestateiq.com
Azizi Venice 15
Azizi Developments · Madinat Al Mataar
0%
6 May 2025
1%-0.5on pace or ahead30 May 2027under 10% built: too early to projectdubairealestateiq.com
Azizi Zain
Azizi Developments · Jabal Ali First
80.2%
15 Oct 2026
67%13.1on pace or ahead11 Oct 2027Apr 2027 – Apr 2027dubairealestateiq.com
Azizi Riviera 54
Azizi Developments · Al Merkadh
74.6%
7 Aug 2026
61%13.6on pace or ahead30 May 2027Dec 2026 – Jan 2027dubairealestateiq.com
Azizi Riviera 68
Azizi Developments · Al Merkadh
74.6%
7 Aug 2026
60%14.7on pace or ahead30 May 2027Dec 2026 – Jan 2027dubairealestateiq.com
Azizi Riviera 64
Azizi Developments · Al Merkadh
83.8%
7 Sept 2026
64%19.8on pace or ahead30 May 2027Nov 2026 – Dec 2026dubairealestateiq.com
Azizi Riviera 60
Azizi Developments · Al Merkadh
97.1%
15 Sept 2026
76%21.6on pace or ahead13 Mar 2027Sept 2026 – Oct 2026dubairealestateiq.com
Azizi Riviera 62
Azizi Developments · Al Merkadh
90.8%
30 Jul 2026
69%21.8on pace or ahead13 Mar 2027Aug 2026 – Sept 2026dubairealestateiq.com
Azizi Riviera 66
Azizi Developments · Al Merkadh
91%
7 Aug 2026
61%30on pace or ahead30 May 2027Sept 2026 – Sept 2026dubairealestateiq.com
Azizi Venice 14
Azizi Developments · Azizi Venice, Dubai South (DWC)
30.3%
22 Jun 2026
100%-registered date passed30 May 2026Nov 2030 – May 2031dubairealestateiq.com
Azizi Grand
Azizi Developments L.L.C · Dubai Sports City
82.1%
24 Jun 2026
100%-registered date passed2 Feb 2025Apr 2028 – Apr 2028dubairealestateiq.com
Azizi Abraham
Azizi Developments · Jabal Ali Industrial Second
2%
24 Mar 2026
--not comparable4 Aug 2027under 10% built: too early to projectdubairealestateiq.com
Azizi Gabriel
Azizi Developments · Jabal Ali Industrial Second
0%
17 Nov 2025
--not comparable4 Jul 2028under 10% built: too early to projectdubairealestateiq.com
Azizi Rose
Azizi Developments · Jabal Ali Industrial Second
0%
16 Feb 2026
--not comparable4 Jul 2028under 10% built: too early to projectdubairealestateiq.com

Method

Time elapsed = (inspection date minus construction start on the register) divided by (registered completion date minus construction start). When no start date is printed, the registration date is used.

Gap = % built at the inspection minus % of time elapsed at the same date, in percentage points. Behind = a gap below -10 points. Registered date passed = the inspection is after the completion date on the register and the project is not at 100%.

Projection, only for 10% to 99% built: the remaining % divided by the observed pace, where the pace is % built per day since the start date, since the registration date and between the last two inspections we hold (when it rose). The range runs from the earliest to the latest of these estimates.

Limits: Construction does not move in a straight line (a slow start, faster structure, slow finishing), so a straight line from an early reading tends to give later dates than the work will need, and a late reading can give earlier ones. The % built is the DLD inspection figure, not ours.

Source: the Dubai Land Department project register as mirrored per project with its inspection history, read by our register job; 929 DLD records, 28 with two or more dated inspections.