Home / Dubai / Construction pace against the registered date

Construction pace against the registered date

For Dubai projects with DLD inspection readings: % built against the share of time elapsed to the completion date on the register, and the completion range the observed pace points to. A projection, not a promise.

Updated 23 Nov 2026

A projection from the pace on the register, not a promise, and not a finding about the developer.

815projects compared (DLD % built and dates on the register)
82.8%more than 10 points behind the time elapsed (95% interval 80.1 to 85.3%)
-27.1median gap in points, % built minus % of time elapsed (95% interval -29.5 to -26)
426projects with a projected range (10% to 99% built)
87.1%of them projected after the registered date (95% interval 83.6 to 89.9%)
≤-6090-50115-40162-30178-20130-10900291012207301401
Projects by gap between % built and % of time elapsed, in 10-point bins
Show as a table
Gap (points)Projects
-60 … -5090
-50 … -40115
-40 … -30162
-30 … -20178
-20 … -10130
-10 … 090
0 … 1029
10 … 2012
20 … 307
30 … 401
40 … 501

Projects

Developer: danube-properties · All

15 projects, page 1
Project% built (inspection)Time elapsedGap (points)PaceRegistered completionProjected rangeRegister
Sparklz by Danube
Danube Properties · Al Furjan
7.8%
25 Aug 2026
41%-33.3behind31 May 2028under 10% built: too early to projectdubairealestateiq.com
Bayz 102
Danube Properties · Business Bay
6.5%
6 Oct 2026
36%-29.8behind31 Dec 2029under 10% built: too early to projectdubairealestateiq.com
Oasiz 1 by Danube
Danube Properties · Silicon Oasis (Nadd Hessa)
38.2%
12 Nov 2026
65%-26.8behind30 Nov 2027Jan 2030 – May 2030dubairealestateiq.com
Oasiz 2 by Danube
Danube Properties · Silicon Oasis (Nadd Hessa)
31%
29 Jul 2026
55%-24.3behind30 Nov 2027Apr 2030 – Aug 2030dubairealestateiq.com
Breez by Danube
Danube Properties · Dubai Maritime City
0.7%
28 Oct 2026
24%-22.8behind30 Jun 2029under 10% built: too early to projectdubairealestateiq.com
Aspirz
Danube Properties · Dubai Sports City
8.6%
28 Oct 2026
31%-22.6behind31 Dec 2028under 10% built: too early to projectdubairealestateiq.com
Timez by Danube
Danube Properties · Dubai Silicon Oasis
21.5%
9 Sept 2026
43%-21.8behind31 Jul 2028Dec 2031 – Jun 2032dubairealestateiq.com
Shahrukhz Residences by Danube
Danube Properties Development L.L.C · Dubai Maritime City
1.9%
13 Aug 2026
18%-15.7behind30 Jun 2029under 10% built: too early to projectdubairealestateiq.com
Serenz by Danube
Danube Properties · Jumeirah Village Circle
4%
9 Nov 2026
14%-10.3behind31 Dec 2029under 10% built: too early to projectdubairealestateiq.com
Greenz by Danube
Danube Properties · Dubai Academic City
0.1%
14 Oct 2026
8%-8.1on pace or ahead31 Dec 2029under 10% built: too early to projectdubairealestateiq.com
Viewz 2 by Danube
Danube Properties Development L.L.C · Jumeirah Lake Towers (Al Thanyah Fifth)
65%
20 Oct 2026
100%-registered date passed30 Jun 2026Jul 2028 – Sept 2028dubairealestateiq.com
Bayz 101 by Danube
Danube Properties · Business Bay
10%
12 Aug 2026
--not comparable-no projectiondubairealestateiq.com
Oceanz by Danube
Danube Properties · Dubai Maritime City
50%
25 Aug 2026
--not comparable-no projectiondubairealestateiq.com
Fashionz by Danube
Danube Properties · Jumeirah Village Triangle
40%
10 Sept 2026
--not comparable-no projectiondubairealestateiq.com
Diamondz by Danube
Danube Properties · Jumeirah Lake Towers
18.5%
27 Oct 2026
--not comparable-no projectiondubairealestateiq.com

Method

Time elapsed = (inspection date minus construction start on the register) divided by (registered completion date minus construction start). When no start date is printed, the registration date is used.

Gap = % built at the inspection minus % of time elapsed at the same date, in percentage points. Behind = a gap below -10 points. Registered date passed = the inspection is after the completion date on the register and the project is not at 100%.

Projection, only for 10% to 99% built: the remaining % divided by the observed pace, where the pace is % built per day since the start date, since the registration date and between the last two inspections we hold (when it rose). The range runs from the earliest to the latest of these estimates.

Limits: Construction does not move in a straight line (a slow start, faster structure, slow finishing), so a straight line from an early reading tends to give later dates than the work will need, and a late reading can give earlier ones. The % built is the DLD inspection figure, not ours.

Source: the Dubai Land Department project register as mirrored per project with its inspection history, read by our register job; 929 DLD records, 28 with two or more dated inspections.

Files: /data/n35a/pace.json · /open/n35a-build.py · /registers/changes/