Construction pace against the registered date

For Dubai projects with DLD inspection readings: % built against the share of time elapsed to the completion date on the register, and the completion range the observed pace points to. A projection, not a promise.

Updated 23 Nov 2026

A projection from the pace on the register, not a promise, and not a finding about the developer.

860projects compared (DLD % built and dates on the register)
82.7%more than 10 points behind the time elapsed (95% interval 80 to 85.1%)
-27median gap in points, % built minus % of time elapsed (95% interval -29.1 to -26)
452projects with a projected range (10% to 99% built)
86.7%of them projected after the registered date (95% interval 83.3 to 89.5%)
≤-6098-50119-40168-30186-20140-10940291013209303401
Projects by gap between % built and % of time elapsed, in 10-point bins
Show as a table
Gap (points)Projects
-60 … -5098
-50 … -40119
-40 … -30168
-30 … -20186
-20 … -10140
-10 … 094
0 … 1029
10 … 2013
20 … 309
30 … 403
40 … 501

Projects

Developer: dubai-holding-real-estate · All

18 projects, page 1
Project% built (inspection)Time elapsedGap (points)PaceRegistered completionProjected rangeRegister
Como Residences
Dubai Holding Real Estate · Palm Jumeirah
24.8%
9 Oct 2026
88%-63.5behind27 Mar 2027May 2037dubairealestateiq.com
The Acres 3 & Estates
Dubai Holding Real Estate · Wadi Al Safa 7
14.9%
30 Sept 2026
65%-49.7behind19 Nov 2027Jul 2038dubairealestateiq.com
Design Quarter
Dubai Holding Real Estate · Zaabeel Second
40.8%
28 Sept 2026
90%-48.8behind25 Feb 2027Nov 2031dubairealestateiq.com
Verdes by Haven
Dubai Holding Real Estate · Dubai Land Residence Complex
17.7%
21 Oct 2026
57%-39.1behind31 May 2028Aug 2036dubairealestateiq.com
Jumeirah Residences - Asora Bay - Ocean Mansions
Dubai Holding Real Estate · La Mer
0.5%
12 Aug 2026
36%-35.5behind31 Mar 2029under 10% built: too early to projectdubairealestateiq.com
The Acres 2 & Estates 2
Dubai Holding Real Estate · Wadi Al Safa 7
14.9%
30 Sept 2026
49%-34.4behind3 May 2028Aug 2035dubairealestateiq.com
Jumeirah Asora Bay
Dubai Holding Real Estate · La Mer
4.4%
12 Aug 2026
36%-31.8behind31 Mar 2029under 10% built: too early to projectdubairealestateiq.com
Athlon by Al Dar
Dubai Holding Real Estate · Dubai Land Residence Complex
27.3%
22 Oct 2026
59%-31.2behind31 May 2028Nov 2032dubairealestateiq.com
Atelis at D3
Dubai Holding Real Estate · Zaabeel Second
1.4%
8 Oct 2026
31%-30behind14 Aug 2029under 10% built: too early to projectdubairealestateiq.com
The Wilds
Dubai Holding Real Estate · Majan
7.5%
14 Sept 2026
36%-28.2behind31 Jan 2029under 10% built: too early to projectdubairealestateiq.com
Nourelle
Dubai Holding Real Estate · Um Suqaim Third
6.3%
3 Nov 2026
32%-25.6behind1 Mar 2029under 10% built: too early to projectdubairealestateiq.com
Rise by Athlon
Dubai Holding Real Estate · Dubai Land Residence Complex
3.7%
22 Oct 2026
26%-22.2behind30 Dec 2029under 10% built: too early to projectdubairealestateiq.com
Jumeirah Residences Emirates Towers
Dubai Holding Real Estate · Trade Center Second
4.2%
28 Sept 2026
24%-19.6behind1 Sept 2030under 10% built: too early to projectdubairealestateiq.com
The Edit at D3
Dubai Holding Real Estate · Zaabeel Second
0.2%
19 Aug 2026
19%-18.2behind31 Jan 2030under 10% built: too early to projectdubairealestateiq.com
The Wilds Residences
Dubai Holding Real Estate · Majan
0%
13 Oct 2026
14%-14behind30 Jun 2030under 10% built: too early to projectdubairealestateiq.com
Haven by Aldar
Dubai Holding Real Estate · Dubai Land Residence Complex
61%
21 Oct 2026
72%-10.4behind28 Nov 2027Jul 2028dubairealestateiq.com
Palm Beach Towers
Dubai Holding Real Estate · Palm Jumeirah
81.6%
12 Aug 2026
91%-9.8on pace or ahead31 Dec 2026Jul 2027dubairealestateiq.com
Bulgari Lighthouse Dubai
Dubai Holding Real Estate · Jumeira Bay
80%
8 Oct 2026
89%-9.3on pace or ahead27 Mar 2027Sept 2027dubairealestateiq.com

Method

Time elapsed = (inspection date minus construction start on the register) divided by (registered completion date minus construction start). When no start date is printed, the registration date is used.

Gap = % built at the inspection minus % of time elapsed at the same date, in percentage points. Behind = a gap below -10 points. Registered date passed = the inspection is after the completion date on the register and the project is not at 100%.

Projection, only for 10% to 99% built: the remaining % divided by the observed pace, where the pace is % built per day since the start date, since the registration date and between the last two inspections we hold (when it rose). The range runs from the earliest to the latest of these estimates.

Limits: Construction does not move in a straight line (a slow start, faster structure, slow finishing), so a straight line from an early reading tends to give later dates than the work will need, and a late reading can give earlier ones. The % built is the DLD inspection figure, not ours.

Source: the Dubai Land Department project register as mirrored per project with its inspection history, read by our register job; 985 DLD records, 28 with two or more dated inspections.