Construction pace against the registered date
For Dubai projects with DLD inspection readings: % built against the share of time elapsed to the completion date on the register, and the completion range the observed pace points to. A projection, not a promise.
Updated 23 Nov 2026
A projection from the pace on the register, not a promise, and not a finding about the developer.
Show as a table
| Gap (points) | Projects |
|---|---|
| -60 … -50 | 98 |
| -50 … -40 | 119 |
| -40 … -30 | 168 |
| -30 … -20 | 186 |
| -20 … -10 | 140 |
| -10 … 0 | 94 |
| 0 … 10 | 29 |
| 10 … 20 | 13 |
| 20 … 30 | 9 |
| 30 … 40 | 3 |
| 40 … 50 | 1 |
Projects
| Project | % built (inspection) | Time elapsed | Gap (points) | Pace | Registered completion | Projected range | Register |
|---|---|---|---|---|---|---|---|
| Palace Residences Dubai Hills Estate Emaar Properties · Dubai Hills Estate | 50.7% 16 Jun 2026 | 54% | -3.4 | on pace or ahead | 30 Apr 2028 | Aug 2028 – Nov 2028 | dubairealestateiq.com |
| Soma Residences Origami · Palm Deira | 0% 16 Jul 2026 | 3% | -3.4 | on pace or ahead | 1 Sept 2028 | under 10% built: too early to project | dubairealestateiq.com |
| Azizi David Azizi Developments · Al Jadaf | 2% 24 Mar 2026 | 5% | -3.1 | on pace or ahead | 30 Sept 2028 | under 10% built: too early to project | dubairealestateiq.com |
| Franck Muller Vanguard London Gate · Dubai Marina | 48.3% 30 Apr 2026 | 51% | -3.1 | on pace or ahead | 1 Nov 2027 | Jan 2028 | dubairealestateiq.com |
| Serro 2 the Heights Emaar Properties · Al Yelayiss 5 | 0.5% 9 Jun 2026 | 4% | -3 | on pace or ahead | 31 May 2030 | under 10% built: too early to project | dubairealestateiq.com |
| Riverton House Ellington Properties · Bukadra | 0% 22 Dec 2025 | 3% | -2.8 | on pace or ahead | 31 Dec 2027 | under 10% built: too early to project | dubairealestateiq.com |
| Solanki One Solanki · Dubai Land Residence Complex | 35.2% 14 Sept 2026 | 38% | -2.8 | on pace or ahead | 30 May 2028 | Aug 2028 | dubairealestateiq.com |
| Serra Residence by Wujod Wujod · Wadi Al Safa 2 | 28.8% 30 Sept 2026 | 32% | -2.8 | on pace or ahead | 31 Dec 2027 | Mar 2028 | dubairealestateiq.com |
| Lilian Residences London Gate · Madinat Al Mataar | 47.7% 28 Oct 2026 | 50% | -2.7 | on pace or ahead | 1 Apr 2028 | May 2028 | dubairealestateiq.com |
| Soulever' by Beyond Beyond Developments · Dubai Maritime City | 0% 24 Apr 2026 | 3% | -2.5 | on pace or ahead | 30 Dec 2028 | under 10% built: too early to project | dubairealestateiq.com |
| DAMAC Islands 2 - Barbados 1 DAMAC Properties · Al Yelayiss 1 | 0.2% 10 Jun 2026 | 3% | -2.4 | on pace or ahead | 30 Jun 2030 | under 10% built: too early to project | dubairealestateiq.com |
| DAMAC Islands 2 - Barbados 2 DAMAC Properties · Al Yelayiss 1 | 0.2% 10 Jun 2026 | 3% | -2.4 | on pace or ahead | 30 Jun 2030 | under 10% built: too early to project | dubairealestateiq.com |
| DAMAC Islands 2 - Cuba DAMAC Properties · Al Yelayiss 1 | 0.2% 10 Jun 2026 | 3% | -2.4 | on pace or ahead | 30 Jun 2030 | under 10% built: too early to project | dubairealestateiq.com |
| DAMAC Islands 2 - Maui DAMAC Properties · Al Yelayiss 1 | 0.2% 10 Jun 2026 | 3% | -2.4 | on pace or ahead | 30 Jun 2030 | under 10% built: too early to project | dubairealestateiq.com |
| The First Collection at Dubai Sports City The First Group · Dubai Sports City | 65.7% 21 Sept 2026 | 68% | -2.4 | on pace or ahead | 30 Nov 2027 | Jan 2028 | dubairealestateiq.com |
| Luxor by Imtiaz Imtiaz Developments · Jumeirah Village Circle (JVC) | 90% 17 Sept 2026 | 92% | -2.3 | on pace or ahead | 15 Dec 2026 | Jan 2027 | dubairealestateiq.com |
| DAMAC Islands 2 - Bermuda DAMAC Properties · Al Yelayiss 1 | 0.2% 10 Jun 2026 | 3% | -2.3 | on pace or ahead | 30 Jun 2030 | under 10% built: too early to project | dubairealestateiq.com |
| Park Gate 2 Emaar Properties · Hadaeq Sheikh Mohammed Bin Rashid | 55.2% 8 Jun 2026 | 57% | -2.2 | on pace or ahead | 28 Feb 2027 | Mar 2027 – May 2027 | dubairealestateiq.com |
| Forest City Tower Al Helal Al Zahaby · Majan | 70.1% 13 Aug 2026 | 72% | -2.2 | on pace or ahead | 9 Apr 2027 | May 2027 | dubairealestateiq.com |
| Skyhills Astra by HRE HRE Development · Dubai Science Park | 50.6% 13 Nov 2026 | 53% | -1.9 | on pace or ahead | 30 Jun 2028 | Aug 2028 | dubairealestateiq.com |
| DAMAC Islands 2 - Tahiti 1 DAMAC Properties · Al Yelayiss 1 | 0.3% 2 Jun 2026 | 2% | -1.7 | on pace or ahead | 30 Jun 2030 | under 10% built: too early to project | dubairealestateiq.com |
| DAMAC Islands 2 - Tahiti 2 DAMAC Properties · Al Yelayiss 1 | 0.3% 2 Jun 2026 | 2% | -1.7 | on pace or ahead | 30 Jun 2030 | under 10% built: too early to project | dubairealestateiq.com |
| Tavora Residences by Jhk Heights Real Estate Development Jhk Heights · International City Ph 2 & 3 | 86.2% 15 Oct 2026 | 88% | -1.5 | on pace or ahead | 15 Dec 2026 | Dec 2026 | dubairealestateiq.com |
| Avarra by Palace Emaar Properties · Business Bay | 0.1% 10 Jun 2026 | 1% | -1.3 | on pace or ahead | 30 Jun 2031 | under 10% built: too early to project | dubairealestateiq.com |
| Piazza Roma DAMAC Properties · Al Hebiah Fifth | 0.2% 18 Aug 2026 | 1% | -1.1 | on pace or ahead | 30 Jun 2030 | under 10% built: too early to project | dubairealestateiq.com |
| Binghatti SkyTerraces Binghatti Developers · Motor City | 0% 7 Jan 2026 | 1% | -0.9 | on pace or ahead | 31 Oct 2027 | under 10% built: too early to project | dubairealestateiq.com |
| Salva the Heights Emaar Properties · Al Yelayiss 5 | 0.5% 9 Jun 2026 | 1% | -0.9 | on pace or ahead | 31 Jul 2030 | under 10% built: too early to project | dubairealestateiq.com |
| Sobha Estates Sobha Realty · Bukadra | 68.5% 15 Sept 2026 | 69% | -0.9 | on pace or ahead | 31 Dec 2027 | Dec 2027 – Jan 2028 | dubairealestateiq.com |
| Skyscape (Sobha Hartland II) Sobha Realty · Mohammed Bin Rashid City | 38.3% 21 Sept 2026 | 39% | -0.8 | on pace or ahead | 31 Dec 2029 | Sept 2028 – Feb 2030 | dubairealestateiq.com |
| Al Habtoor Tower Al Habtoor Group · Business Bay | 90% 31 Aug 2026 | 91% | -0.6 | on pace or ahead | 31 Dec 2026 | Jan 2027 | dubairealestateiq.com |
| DAMAC Islands 2 - Bahamas 1 DAMAC Properties · Al Yelayiss 1 | 0.3% 14 May 2026 | 1% | -0.5 | on pace or ahead | 30 Jun 2030 | under 10% built: too early to project | dubairealestateiq.com |
| DAMAC Islands 2 - Bahamas 2 DAMAC Properties · Al Yelayiss 1 | 0.3% 14 May 2026 | 1% | -0.5 | on pace or ahead | 30 Jun 2030 | under 10% built: too early to project | dubairealestateiq.com |
| Azizi Venice 15 Azizi Developments · Madinat Al Mataar | 0% 6 May 2025 | 1% | -0.5 | on pace or ahead | 30 May 2027 | under 10% built: too early to project | dubairealestateiq.com |
| Elemental 22 Al Barari · Al Satwa | 46% 4 Nov 2026 | 46% | -0.5 | on pace or ahead | 31 May 2028 | Jun 2028 | dubairealestateiq.com |
| Ayamore Residence Ayat · Palm Deira | 67.6% 8 Jul 2026 | 68% | 0.1 | on pace or ahead | 7 Mar 2027 | Mar 2027 | dubairealestateiq.com |
| Living Legends Phase 4 Al Ghurair Investment · Majan | 62.1% 13 Mar 2026 | 62% | 0.2 | on pace or ahead | 31 Mar 2027 | Mar 2027 | dubairealestateiq.com |
| Parkside Boulevard Tabeer · Arjan | 60.3% 28 Oct 2026 | 60% | 0.3 | on pace or ahead | 27 Dec 2027 | Dec 2027 | dubairealestateiq.com |
| Greenridge Emaar Properties · Madinat Al Mataar | 35.6% 17 Jun 2026 | 35% | 0.4 | on pace or ahead | 31 Dec 2028 | Dec 2028 – Aug 2029 | dubairealestateiq.com |
| Sunset Bay One by Imtiaz Imtiaz Developments · Palm Deira | 93.5% 2 Nov 2026 | 93% | 0.8 | on pace or ahead | 25 Dec 2026 | Dec 2026 – Dec 2026 | dubairealestateiq.com |
| MBL Signature MAG · Jumeirah Lakes Towers | 80% 10 Nov 2026 | 78% | 1.6 | on pace or ahead | 31 Mar 2027 | Mar 2027 | dubairealestateiq.com |
| Bayview Emaar Properties · Dubai Marina | 63% 14 Sept 2026 | 61% | 2.2 | on pace or ahead | 31 Jul 2028 | May 2028 – Aug 2028 | dubairealestateiq.com |
| Zenith Tower J1 Zenith Ventures · Jumeirah Village Circle | 72.2% 4 Aug 2026 | 70% | 2.6 | on pace or ahead | 25 Dec 2026 | Dec 2026 | dubairealestateiq.com |
| Westar Altair Westar Properties · Madinat Al Mataar | 62.9% 20 Jul 2026 | 60% | 2.8 | on pace or ahead | 31 May 2027 | Apr 2027 | dubairealestateiq.com |
| Marina Shores Emaar Properties · Dubai Marina | 87.2% 14 May 2026 | 84% | 2.9 | on pace or ahead | 31 Dec 2026 | Nov 2026 – Dec 2026 | dubairealestateiq.com |
| Fairway Villas 2 Emaar Properties · Madinat Al Mataar | 92.2% 17 Aug 2026 | 89% | 3 | on pace or ahead | 31 Dec 2026 | Nov 2026 – Nov 2026 | dubairealestateiq.com |
| Vida Residences Club Point Emaar Properties · Hadaeq Sheikh Mohammed Bin Rashid | 43.5% 3 Aug 2026 | 40% | 3.2 | on pace or ahead | 28 Feb 2029 | Nov 2028 – Dec 2028 | dubairealestateiq.com |
| Address Residences Dubai Creek Harbour Emaar Properties · Dubai Creek Harbour | 50.1% 16 Nov 2026 | 47% | 3.5 | on pace or ahead | 31 Jan 2029 | Jan 2028 – Feb 2029 | dubairealestateiq.com |
| The Valley - Elva Emaar Properties · Al Yufrah 1 | 49.9% 11 Nov 2026 | 46% | 3.6 | on pace or ahead | 31 Oct 2028 | Jul 2028 – Sept 2028 | dubairealestateiq.com |
| Expo City Al Waha Residences 01 Expo City Dubai · Madinat Al Mataar | 65.8% 26 Aug 2026 | 62% | 3.6 | on pace or ahead | 15 Jun 2027 | May 2027 – Jun 2027 | dubairealestateiq.com |
| Expo City Al Waha Residences 02 Expo City Dubai · Madinat Al Mataar | 61.4% 26 Aug 2026 | 58% | 3.6 | on pace or ahead | 30 Jun 2027 | May 2027 – Aug 2027 | dubairealestateiq.com |
| Greenspoint 2 Emaar Properties · Madinat Al Mataar | 40.1% 3 Aug 2026 | 36% | 3.9 | on pace or ahead | 31 Mar 2029 | Oct 2028 – Nov 2028 | dubairealestateiq.com |
| Mi Casa by London Gate Real Estate Development London Gate · Jumeirah Village Circle | 19.1% 21 Apr 2026 | 15% | 4.3 | on pace or ahead | 26 Oct 2028 | Feb 2028 | dubairealestateiq.com |
| Iridian Park 2 Object 1 · Jumeirah Village Circle | 21.3% 31 Jul 2026 | 17% | 4.6 | on pace or ahead | 1 Feb 2027 | Dec 2026 | dubairealestateiq.com |
| Verde by Sobha Sobha Realty · Jumeirah Lakes Towers | 85% 24 Aug 2026 | 80% | 5 | on pace or ahead | 30 Jun 2027 | Mar 2027 – Mar 2027 | dubairealestateiq.com |
| The Valley - Venera Emaar Properties · Al Yufrah 1 | 51.7% 5 Aug 2026 | 46% | 5.3 | on pace or ahead | 30 Sept 2028 | May 2028 – Jul 2028 | dubairealestateiq.com |
| The Valley - Velora Emaar Properties · Al Yufrah 1 | 50.1% 9 Jun 2026 | 45% | 5.5 | on pace or ahead | 31 Aug 2028 | Mar 2028 – May 2028 | dubairealestateiq.com |
| Park Lane Emaar Properties · Hadaeq Sheikh Mohammed Bin Rashid | 55.4% 22 May 2026 | 49% | 6.2 | on pace or ahead | 31 Oct 2028 | Apr 2028 – Jun 2028 | dubairealestateiq.com |
| Roof Comfort Roof Enterprises · Dubai Land Residence Complex | 50.2% 28 Jul 2026 | 44% | 6.4 | on pace or ahead | 31 Dec 2027 | Sept 2027 | dubairealestateiq.com |
| The Valley - Rivana Emaar Properties · Al Yufrah 1 | 95.2% 28 Oct 2026 | 88% | 7.1 | on pace or ahead | 31 Mar 2027 | Dec 2026 – Dec 2026 | dubairealestateiq.com |
| Greenspoint Emaar Properties · Madinat Al Mataar | 42.9% 21 Jul 2026 | 35% | 7.6 | on pace or ahead | 31 Mar 2029 | Jul 2028 – Jul 2028 | dubairealestateiq.com |
Method
Time elapsed = (inspection date minus construction start on the register) divided by (registered completion date minus construction start). When no start date is printed, the registration date is used.
Gap = % built at the inspection minus % of time elapsed at the same date, in percentage points. Behind = a gap below -10 points. Registered date passed = the inspection is after the completion date on the register and the project is not at 100%.
Projection, only for 10% to 99% built: the remaining % divided by the observed pace, where the pace is % built per day since the start date, since the registration date and between the last two inspections we hold (when it rose). The range runs from the earliest to the latest of these estimates.
Limits: Construction does not move in a straight line (a slow start, faster structure, slow finishing), so a straight line from an early reading tends to give later dates than the work will need, and a late reading can give earlier ones. The % built is the DLD inspection figure, not ours.
Source: the Dubai Land Department project register as mirrored per project with its inspection history, read by our register job; 985 DLD records, 28 with two or more dated inspections.
Files: /data/n35a/pace.json · /open/n35a-build.py · /registers/changes/