Construction pace against the registered date

For Dubai projects with DLD inspection readings: % built against the share of time elapsed to the completion date on the register, and the completion range the observed pace points to. A projection, not a promise.

Updated 23 Nov 2026

A projection from the pace on the register, not a promise, and not a finding about the developer.

860projects compared (DLD % built and dates on the register)
82.7%more than 10 points behind the time elapsed (95% interval 80 to 85.1%)
-27median gap in points, % built minus % of time elapsed (95% interval -29.1 to -26)
452projects with a projected range (10% to 99% built)
86.7%of them projected after the registered date (95% interval 83.3 to 89.5%)
≤-6098-50119-40168-30186-20140-10940291013209303401
Projects by gap between % built and % of time elapsed, in 10-point bins
Show as a table
Gap (points)Projects
-60 … -5098
-50 … -40119
-40 … -30168
-30 … -20186
-20 … -10140
-10 … 094
0 … 1029
10 … 2013
20 … 309
30 … 403
40 … 501

Projects

Developer: london-gate · All

5 projects, page 1
Project% built (inspection)Time elapsedGap (points)PaceRegistered completionProjected rangeRegister
Franck Muller Yachting
London Gate · Dubai Maritime City
0%
26 Mar 2026
21%-20.7behind29 Jul 2028under 10% built: too early to projectdubairealestateiq.com
Aeternitas Tower
London Gate · Dubai Marina
57.9%
25 Sept 2026
69%-11.5behind11 Dec 2027Sept 2028dubairealestateiq.com
Franck Muller Vanguard
London Gate · Dubai Marina
48.3%
30 Apr 2026
51%-3.1on pace or ahead1 Nov 2027Jan 2028dubairealestateiq.com
Lilian Residences
London Gate · Madinat Al Mataar
47.7%
28 Oct 2026
50%-2.7on pace or ahead1 Apr 2028May 2028dubairealestateiq.com
Mi Casa by London Gate Real Estate Development
London Gate · Jumeirah Village Circle
19.1%
21 Apr 2026
15%4.3on pace or ahead26 Oct 2028Feb 2028dubairealestateiq.com

Method

Time elapsed = (inspection date minus construction start on the register) divided by (registered completion date minus construction start). When no start date is printed, the registration date is used.

Gap = % built at the inspection minus % of time elapsed at the same date, in percentage points. Behind = a gap below -10 points. Registered date passed = the inspection is after the completion date on the register and the project is not at 100%.

Projection, only for 10% to 99% built: the remaining % divided by the observed pace, where the pace is % built per day since the start date, since the registration date and between the last two inspections we hold (when it rose). The range runs from the earliest to the latest of these estimates.

Limits: Construction does not move in a straight line (a slow start, faster structure, slow finishing), so a straight line from an early reading tends to give later dates than the work will need, and a late reading can give earlier ones. The % built is the DLD inspection figure, not ours.

Source: the Dubai Land Department project register as mirrored per project with its inspection history, read by our register job; 985 DLD records, 28 with two or more dated inspections.

Files: /data/n35a/pace.json · /open/n35a-build.py · /registers/changes/