Home / Dubai / Construction pace against the registered date

Construction pace against the registered date

For Dubai projects with DLD inspection readings: % built against the share of time elapsed to the completion date on the register, and the completion range the observed pace points to. A projection, not a promise.

Updated 23 Nov 2026

A projection from the pace on the register, not a promise, and not a finding about the developer.

860projects compared (DLD % built and dates on the register)
82.7%more than 10 points behind the time elapsed (95% interval 80 to 85.1%)
-27median gap in points, % built minus % of time elapsed (95% interval -29.1 to -26)
452projects with a projected range (10% to 99% built)
86.7%of them projected after the registered date (95% interval 83.3 to 89.5%)
≤-6098-50119-40168-30186-20140-10940291013209303401
Projects by gap between % built and % of time elapsed, in 10-point bins
Show as a table
Gap (points)Projects
-60 … -5098
-50 … -40119
-40 … -30168
-30 … -20186
-20 … -10140
-10 … 094
0 … 1029
10 … 2013
20 … 309
30 … 403
40 … 501

Projects

149 projects, page 3
Project% built (inspection)Time elapsedGap (points)PaceRegistered completionProjected rangeRegister
Bliss Tower
Pure Bliss Development L.L.C · Dubai Land Residence Complex
92.5%
17 Sept 2026
84%8.8on pace or ahead15 Dec 2026Oct 2026dubairealestateiq.com
Creek Waters
Emaar Properties · Al Khairan First
81.1%
3 Aug 2026
72%9.1on pace or ahead30 Sept 2027Apr 2027 – May 2027dubairealestateiq.com
Parkland
Emaar Properties · Hadaeq Sheikh Mohammed Bin Rashid
50%
22 Jun 2026
40%9.9on pace or ahead30 Nov 2028Feb 2028 – May 2028dubairealestateiq.com
Wellington Grand Villas
Mbr Mansions Real Estate Development L.L.C · Majan
62.1%
14 Oct 2026
52%10.2on pace or ahead24 Jan 2028Aug 2027dubairealestateiq.com
Azra Residence
Enaam · Dubai Land Residence Complex
27.5%
21 Sept 2026
17%10.4on pace or ahead31 Dec 2027Jun 2027dubairealestateiq.com
Greenville 2
Emaar Properties · Madinat Al Mataar
47.3%
19 Jul 2026
35%12.1on pace or ahead31 Mar 2029Mar 2028 – Jul 2028dubairealestateiq.com
Azizi Zain
Azizi Developments · Jabal Ali First
80.2%
15 Oct 2026
67%13.1on pace or ahead11 Oct 2027Apr 2027 – Apr 2027dubairealestateiq.com
Azizi Riviera 54
Azizi Developments · Al Merkadh
74.6%
7 Aug 2026
61%13.6on pace or ahead30 May 2027Dec 2026 – Jan 2027dubairealestateiq.com
Ag 7even
AG Properties · Dubai Land Residence Complex
93.7%
18 Jun 2026
80%13.9on pace or ahead31 Mar 2027Sept 2026dubairealestateiq.com
Creek Waters 2
Emaar Properties · Dubai Creek Harbour
81.8%
31 Jul 2026
68%14.4on pace or ahead31 Dec 2027Mar 2027 – Apr 2027dubairealestateiq.com
Azizi Riviera 68
Azizi Developments · Al Merkadh
74.6%
7 Aug 2026
60%14.7on pace or ahead30 May 2027Dec 2026 – Jan 2027dubairealestateiq.com
Greenville
Emaar Properties · Madinat Al Mataar
46%
14 May 2026
31%15.2on pace or ahead31 Mar 2029Nov 2027 – Apr 2028dubairealestateiq.com
Parkside Hills
Emaar Properties · Dubai Hills Estate
68.3%
7 May 2026
53%15.6on pace or ahead30 Jun 2028Jun 2027 – Aug 2027dubairealestateiq.com
Kingdom Gate
Kingdom Gate · Jabal Ali First
55.5%
18 Jun 2026
38%17.4on pace or ahead31 Mar 2027Nov 2026dubairealestateiq.com
11 Hills Park
Townx · Dubai Science Park
80.1%
30 Apr 2026
62%18.4on pace or ahead31 Mar 2027Sept 2026dubairealestateiq.com
Azizi Riviera 64
Azizi Developments · Al Merkadh
83.8%
7 Sept 2026
64%19.8on pace or ahead30 May 2027Nov 2026 – Dec 2026dubairealestateiq.com
Sartoria
Pinnacle A K S · Dubai Sports City
51.2%
15 Oct 2026
30%20.9on pace or ahead9 Oct 2027Mar 2027dubairealestateiq.com
Azizi Riviera 60
Azizi Developments · Al Merkadh
97.1%
15 Sept 2026
76%21.6on pace or ahead13 Mar 2027Sept 2026 – Oct 2026dubairealestateiq.com
Ahs Tower
DAMAC Properties · Trade Center Second
67.4%
19 May 2026
46%21.8on pace or ahead31 Jan 2027Jul 2026 – Aug 2026dubairealestateiq.com
Azizi Riviera 62
Azizi Developments · Al Merkadh
90.8%
30 Jul 2026
69%21.8on pace or ahead13 Mar 2027Aug 2026 – Sept 2026dubairealestateiq.com
Aryam Tower by Abu Alnaga
Abualnaga · Jabal Ali First
33.2%
29 Sept 2026
11%21.8on pace or ahead30 Jun 2028Mar 2027dubairealestateiq.com
Golf Hillside
Emaar Properties · Hadaeq Sheikh Mohammed Bin Rashid
65.8%
11 Aug 2026
43%22.6on pace or ahead31 Dec 2028Jul 2027 – Aug 2027dubairealestateiq.com
Ashley Hills
Townx · Arjan
74.1%
10 Jun 2026
48%26.5on pace or ahead31 Mar 2027Sept 2026dubairealestateiq.com
Club Place
Emaar Properties · Dubai Hills Estate
68.8%
16 Jun 2026
41%27.9on pace or ahead31 Dec 2028Apr 2027 – Apr 2027dubairealestateiq.com
The Oasis - Palmiera 3
Emaar Properties · Me'Aisem Second
72.6%
9 Jun 2026
43%29.8on pace or ahead31 Oct 2028Feb 2027 – Feb 2027dubairealestateiq.com
Azizi Riviera 66
Azizi Developments · Al Merkadh
91%
7 Aug 2026
61%30on pace or ahead30 May 2027Sept 2026 – Sept 2026dubairealestateiq.com
Paradise One
Danat Aldunia · Jumeirah Village Triangle
69.7%
23 Apr 2026
35%35on pace or ahead15 Apr 2027Jul 2026dubairealestateiq.com
Oasis Tower 2
P A L · Dubai Sports City
73.9%
8 Sept 2026
34%39.7on pace or ahead30 Jun 2027Nov 2026dubairealestateiq.com
Altus
Emaar Properties · Al Khairan First
86.5%
10 Nov 2026
47%40on pace or ahead31 Jan 2029Feb 2027 – Mar 2027dubairealestateiq.com

Method

Time elapsed = (inspection date minus construction start on the register) divided by (registered completion date minus construction start). When no start date is printed, the registration date is used.

Gap = % built at the inspection minus % of time elapsed at the same date, in percentage points. Behind = a gap below -10 points. Registered date passed = the inspection is after the completion date on the register and the project is not at 100%.

Projection, only for 10% to 99% built: the remaining % divided by the observed pace, where the pace is % built per day since the start date, since the registration date and between the last two inspections we hold (when it rose). The range runs from the earliest to the latest of these estimates.

Limits: Construction does not move in a straight line (a slow start, faster structure, slow finishing), so a straight line from an early reading tends to give later dates than the work will need, and a late reading can give earlier ones. The % built is the DLD inspection figure, not ours.

Source: the Dubai Land Department project register as mirrored per project with its inspection history, read by our register job; 985 DLD records, 28 with two or more dated inspections.

Files: /data/n35a/pace.json · /open/n35a-build.py · /registers/changes/