Home / Dubai / Construction pace against the registered date
Construction pace against the registered date
For Dubai projects with DLD inspection readings: % built against the share of time elapsed to the completion date on the register, and the completion range the observed pace points to. A projection, not a promise.
Updated 23 Nov 2026
A projection from the pace on the register, not a promise, and not a finding about the developer.
Show as a table
| Gap (points) | Projects |
|---|---|
| -60 … -50 | 98 |
| -50 … -40 | 119 |
| -40 … -30 | 168 |
| -30 … -20 | 186 |
| -20 … -10 | 140 |
| -10 … 0 | 94 |
| 0 … 10 | 29 |
| 10 … 20 | 13 |
| 20 … 30 | 9 |
| 30 … 40 | 3 |
| 40 … 50 | 1 |
Projects
| Project | % built (inspection) | Time elapsed | Gap (points) | Pace | Registered completion | Projected range | Register |
|---|---|---|---|---|---|---|---|
| Bliss Tower Pure Bliss Development L.L.C · Dubai Land Residence Complex | 92.5% 17 Sept 2026 | 84% | 8.8 | on pace or ahead | 15 Dec 2026 | Oct 2026 | dubairealestateiq.com |
| Creek Waters Emaar Properties · Al Khairan First | 81.1% 3 Aug 2026 | 72% | 9.1 | on pace or ahead | 30 Sept 2027 | Apr 2027 – May 2027 | dubairealestateiq.com |
| Parkland Emaar Properties · Hadaeq Sheikh Mohammed Bin Rashid | 50% 22 Jun 2026 | 40% | 9.9 | on pace or ahead | 30 Nov 2028 | Feb 2028 – May 2028 | dubairealestateiq.com |
| Wellington Grand Villas Mbr Mansions Real Estate Development L.L.C · Majan | 62.1% 14 Oct 2026 | 52% | 10.2 | on pace or ahead | 24 Jan 2028 | Aug 2027 | dubairealestateiq.com |
| Azra Residence Enaam · Dubai Land Residence Complex | 27.5% 21 Sept 2026 | 17% | 10.4 | on pace or ahead | 31 Dec 2027 | Jun 2027 | dubairealestateiq.com |
| Greenville 2 Emaar Properties · Madinat Al Mataar | 47.3% 19 Jul 2026 | 35% | 12.1 | on pace or ahead | 31 Mar 2029 | Mar 2028 – Jul 2028 | dubairealestateiq.com |
| Azizi Zain Azizi Developments · Jabal Ali First | 80.2% 15 Oct 2026 | 67% | 13.1 | on pace or ahead | 11 Oct 2027 | Apr 2027 – Apr 2027 | dubairealestateiq.com |
| Azizi Riviera 54 Azizi Developments · Al Merkadh | 74.6% 7 Aug 2026 | 61% | 13.6 | on pace or ahead | 30 May 2027 | Dec 2026 – Jan 2027 | dubairealestateiq.com |
| Ag 7even AG Properties · Dubai Land Residence Complex | 93.7% 18 Jun 2026 | 80% | 13.9 | on pace or ahead | 31 Mar 2027 | Sept 2026 | dubairealestateiq.com |
| Creek Waters 2 Emaar Properties · Dubai Creek Harbour | 81.8% 31 Jul 2026 | 68% | 14.4 | on pace or ahead | 31 Dec 2027 | Mar 2027 – Apr 2027 | dubairealestateiq.com |
| Azizi Riviera 68 Azizi Developments · Al Merkadh | 74.6% 7 Aug 2026 | 60% | 14.7 | on pace or ahead | 30 May 2027 | Dec 2026 – Jan 2027 | dubairealestateiq.com |
| Greenville Emaar Properties · Madinat Al Mataar | 46% 14 May 2026 | 31% | 15.2 | on pace or ahead | 31 Mar 2029 | Nov 2027 – Apr 2028 | dubairealestateiq.com |
| Parkside Hills Emaar Properties · Dubai Hills Estate | 68.3% 7 May 2026 | 53% | 15.6 | on pace or ahead | 30 Jun 2028 | Jun 2027 – Aug 2027 | dubairealestateiq.com |
| Kingdom Gate Kingdom Gate · Jabal Ali First | 55.5% 18 Jun 2026 | 38% | 17.4 | on pace or ahead | 31 Mar 2027 | Nov 2026 | dubairealestateiq.com |
| 11 Hills Park Townx · Dubai Science Park | 80.1% 30 Apr 2026 | 62% | 18.4 | on pace or ahead | 31 Mar 2027 | Sept 2026 | dubairealestateiq.com |
| Azizi Riviera 64 Azizi Developments · Al Merkadh | 83.8% 7 Sept 2026 | 64% | 19.8 | on pace or ahead | 30 May 2027 | Nov 2026 – Dec 2026 | dubairealestateiq.com |
| Sartoria Pinnacle A K S · Dubai Sports City | 51.2% 15 Oct 2026 | 30% | 20.9 | on pace or ahead | 9 Oct 2027 | Mar 2027 | dubairealestateiq.com |
| Azizi Riviera 60 Azizi Developments · Al Merkadh | 97.1% 15 Sept 2026 | 76% | 21.6 | on pace or ahead | 13 Mar 2027 | Sept 2026 – Oct 2026 | dubairealestateiq.com |
| Ahs Tower DAMAC Properties · Trade Center Second | 67.4% 19 May 2026 | 46% | 21.8 | on pace or ahead | 31 Jan 2027 | Jul 2026 – Aug 2026 | dubairealestateiq.com |
| Azizi Riviera 62 Azizi Developments · Al Merkadh | 90.8% 30 Jul 2026 | 69% | 21.8 | on pace or ahead | 13 Mar 2027 | Aug 2026 – Sept 2026 | dubairealestateiq.com |
| Aryam Tower by Abu Alnaga Abualnaga · Jabal Ali First | 33.2% 29 Sept 2026 | 11% | 21.8 | on pace or ahead | 30 Jun 2028 | Mar 2027 | dubairealestateiq.com |
| Golf Hillside Emaar Properties · Hadaeq Sheikh Mohammed Bin Rashid | 65.8% 11 Aug 2026 | 43% | 22.6 | on pace or ahead | 31 Dec 2028 | Jul 2027 – Aug 2027 | dubairealestateiq.com |
| Ashley Hills Townx · Arjan | 74.1% 10 Jun 2026 | 48% | 26.5 | on pace or ahead | 31 Mar 2027 | Sept 2026 | dubairealestateiq.com |
| Club Place Emaar Properties · Dubai Hills Estate | 68.8% 16 Jun 2026 | 41% | 27.9 | on pace or ahead | 31 Dec 2028 | Apr 2027 – Apr 2027 | dubairealestateiq.com |
| The Oasis - Palmiera 3 Emaar Properties · Me'Aisem Second | 72.6% 9 Jun 2026 | 43% | 29.8 | on pace or ahead | 31 Oct 2028 | Feb 2027 – Feb 2027 | dubairealestateiq.com |
| Azizi Riviera 66 Azizi Developments · Al Merkadh | 91% 7 Aug 2026 | 61% | 30 | on pace or ahead | 30 May 2027 | Sept 2026 – Sept 2026 | dubairealestateiq.com |
| Paradise One Danat Aldunia · Jumeirah Village Triangle | 69.7% 23 Apr 2026 | 35% | 35 | on pace or ahead | 15 Apr 2027 | Jul 2026 | dubairealestateiq.com |
| Oasis Tower 2 P A L · Dubai Sports City | 73.9% 8 Sept 2026 | 34% | 39.7 | on pace or ahead | 30 Jun 2027 | Nov 2026 | dubairealestateiq.com |
| Altus Emaar Properties · Al Khairan First | 86.5% 10 Nov 2026 | 47% | 40 | on pace or ahead | 31 Jan 2029 | Feb 2027 – Mar 2027 | dubairealestateiq.com |
Method
Time elapsed = (inspection date minus construction start on the register) divided by (registered completion date minus construction start). When no start date is printed, the registration date is used.
Gap = % built at the inspection minus % of time elapsed at the same date, in percentage points. Behind = a gap below -10 points. Registered date passed = the inspection is after the completion date on the register and the project is not at 100%.
Projection, only for 10% to 99% built: the remaining % divided by the observed pace, where the pace is % built per day since the start date, since the registration date and between the last two inspections we hold (when it rose). The range runs from the earliest to the latest of these estimates.
Limits: Construction does not move in a straight line (a slow start, faster structure, slow finishing), so a straight line from an early reading tends to give later dates than the work will need, and a late reading can give earlier ones. The % built is the DLD inspection figure, not ours.
Source: the Dubai Land Department project register as mirrored per project with its inspection history, read by our register job; 985 DLD records, 28 with two or more dated inspections.
Files: /data/n35a/pace.json · /open/n35a-build.py · /registers/changes/