Home / Dubai / Construction pace against the registered date

Construction pace against the registered date

For Dubai projects with DLD inspection readings: % built against the share of time elapsed to the completion date on the register, and the completion range the observed pace points to. A projection, not a promise.

Updated 23 Nov 2026

A projection from the pace on the register, not a promise, and not a finding about the developer.

815projects compared (DLD % built and dates on the register)
82.8%more than 10 points behind the time elapsed (95% interval 80.1 to 85.3%)
-27.1median gap in points, % built minus % of time elapsed (95% interval -29.5 to -26)
426projects with a projected range (10% to 99% built)
87.1%of them projected after the registered date (95% interval 83.6 to 89.9%)
≤-6090-50115-40162-30178-20130-10900291012207301401
Projects by gap between % built and % of time elapsed, in 10-point bins
Show as a table
Gap (points)Projects
-60 … -5090
-50 … -40115
-40 … -30162
-30 … -20178
-20 … -10130
-10 … 090
0 … 1029
10 … 2012
20 … 307
30 … 401
40 … 501

Projects

Developer: omniyat · All

10 projects, page 1
Project% built (inspection)Time elapsedGap (points)PaceRegistered completionProjected rangeRegister
The Alba Residences by Omniyat
OMNIYAT · Palm Jumeirah
8.4%
1 Sept 2026
58%-49.5behind31 Mar 2028under 10% built: too early to projectdubairealestateiq.com
Vela Viento
OMNIYAT · Business Bay
21.8%
18 May 2026
71%-48.7behind13 May 2027Jan 2033 – Oct 2034dubairealestateiq.com
Enara by Omniyat
OMNIYAT · Business Bay
7.3%
12 Jun 2026
52%-44.9behind31 Dec 2027under 10% built: too early to projectdubairealestateiq.com
Orise
OMNIYAT · Dubai Maritime City
17.6%
7 Oct 2026
58%-40.7behind30 Nov 2027Apr 2034 – May 2035dubairealestateiq.com
Saria
OMNIYAT · Dubai Maritime City
31%
1 Oct 2026
66%-34.7behind1 Oct 2027Jan 2031 – Apr 2031dubairealestateiq.com
Talea
OMNIYAT · Dubai Maritime City
4.7%
2 Nov 2026
26%-21.6behind30 Jun 2028under 10% built: too early to projectdubairealestateiq.com
ORLA, Dorchester Collection
Omniyat · Palm Jumeirah (The Crescent)
70%
21 Aug 2026
91%-20.8behind31 Dec 2026Feb 2028 – Mar 2028dubairealestateiq.com
The Mural
OMNIYAT · Dubai Maritime City
16.6%
1 Oct 2026
36%-18.8behind10 Jul 2028Aug 2031 – Feb 2034dubairealestateiq.com
Sensia
OMNIYAT · Dubai Maritime City
17.5%
1 Oct 2026
29%-11.1behind30 Mar 2029Jun 2031 – Mar 2034dubairealestateiq.com
Lumena Alta by Omniyat
OMNIYAT · Business Bay
0%
23 Jul 2026
6%-6.2on pace or ahead30 Apr 2031under 10% built: too early to projectdubairealestateiq.com

Method

Time elapsed = (inspection date minus construction start on the register) divided by (registered completion date minus construction start). When no start date is printed, the registration date is used.

Gap = % built at the inspection minus % of time elapsed at the same date, in percentage points. Behind = a gap below -10 points. Registered date passed = the inspection is after the completion date on the register and the project is not at 100%.

Projection, only for 10% to 99% built: the remaining % divided by the observed pace, where the pace is % built per day since the start date, since the registration date and between the last two inspections we hold (when it rose). The range runs from the earliest to the latest of these estimates.

Limits: Construction does not move in a straight line (a slow start, faster structure, slow finishing), so a straight line from an early reading tends to give later dates than the work will need, and a late reading can give earlier ones. The % built is the DLD inspection figure, not ours.

Source: the Dubai Land Department project register as mirrored per project with its inspection history, read by our register job; 929 DLD records, 28 with two or more dated inspections.

Files: /data/n35a/pace.json · /open/n35a-build.py · /registers/changes/