Home / Dubai / Construction pace against the registered date
Construction pace against the registered date
For Dubai projects with DLD inspection readings: % built against the share of time elapsed to the completion date on the register, and the completion range the observed pace points to. A projection, not a promise.
Updated 23 Nov 2026
A projection from the pace on the register, not a promise, and not a finding about the developer.
Show as a table
| Gap (points) | Projects |
|---|---|
| -60 … -50 | 90 |
| -50 … -40 | 115 |
| -40 … -30 | 162 |
| -30 … -20 | 178 |
| -20 … -10 | 130 |
| -10 … 0 | 90 |
| 0 … 10 | 29 |
| 10 … 20 | 12 |
| 20 … 30 | 7 |
| 30 … 40 | 1 |
| 40 … 50 | 1 |
Projects
Developer: nshama · All
| Project | % built (inspection) | Time elapsed | Gap (points) | Pace | Registered completion | Projected range | Register |
|---|---|---|---|---|---|---|---|
| Lexington Nshama · Al Yelayiss 2 | 4.5% 13 Aug 2026 | 61% | -56 | behind | 30 Sept 2027 | under 10% built: too early to project | dubairealestateiq.com |
| Berkshire Park Nshama · Al Yelayiss 2 | 17.6% 7 Oct 2026 | 73% | -55.6 | behind | 30 Jun 2027 | Feb 2036 | dubairealestateiq.com |
| Haya On the Park Nshama · Al Yelayiss 2 | 35.3% 10 Sept 2026 | 82% | -46.9 | behind | 26 Feb 2027 | Aug 2030 | dubairealestateiq.com |
| Augusta Nshama · Al Yelayiss 2 | 5.3% 10 Sept 2026 | 51% | -45.6 | behind | 14 Jan 2028 | under 10% built: too early to project | dubairealestateiq.com |
| Odessa Nshama · Al Yelayiss 2 | 8% 13 Aug 2026 | 51% | -43 | behind | 30 Dec 2027 | under 10% built: too early to project | dubairealestateiq.com |
| The Baltimore Nshama · Al Yelayiss 2 | 26.3% 7 Oct 2026 | 65% | -38.9 | behind | 30 Sept 2027 | Nov 2031 | dubairealestateiq.com |
| Address Grand Downtown Nshama · Burj Khalifa | 10.8% 7 Oct 2026 | 49% | -38.5 | behind | 10 Jun 2028 | Apr 2040 | dubairealestateiq.com |
| Alton Nshama · Al Yelayiss 2 | 5.2% 18 Aug 2026 | 42% | -36.7 | behind | 31 May 2028 | under 10% built: too early to project | dubairealestateiq.com |
| Savannah Nshama · Al Yelayiss 2 | 43.5% 17 Sept 2026 | 78% | -34.7 | behind | 30 Apr 2027 | Aug 2029 | dubairealestateiq.com |
| Camden Nshama · Al Yelayiss 2 | 7.2% 18 Aug 2026 | 42% | -34.2 | behind | 31 Mar 2028 | under 10% built: too early to project | dubairealestateiq.com |
| Hillcrest Nshama · Al Yelayiss 2 | 38.4% 17 Sept 2026 | 72% | -33.7 | behind | 30 Jun 2027 | Dec 2029 | dubairealestateiq.com |
| Olbia Nshama · Al Yelayiss 2 | 0% 25 Apr 2026 | 30% | -30.2 | behind | 31 May 2028 | under 10% built: too early to project | dubairealestateiq.com |
| Fiori Nshama · Al Yelayiss 2 | 0% 25 Apr 2026 | 22% | -21.6 | behind | 30 Jun 2028 | under 10% built: too early to project | dubairealestateiq.com |
| Rosewell Nshama · Al Yelayiss 2 | 0% 26 Jun 2026 | 21% | -20.6 | behind | 31 Dec 2028 | under 10% built: too early to project | dubairealestateiq.com |
| Ellison Nshama · Al Yelayiss 2 | 40.2% 17 Sept 2026 | 58% | -17.4 | behind | 30 Nov 2027 | Feb 2029 | dubairealestateiq.com |
| Evelyn On the Park Nshama · Al Yelayiss 2 | 0% 26 Jun 2026 | 15% | -15.3 | behind | 28 Feb 2029 | under 10% built: too early to project | dubairealestateiq.com |
Method
Time elapsed = (inspection date minus construction start on the register) divided by (registered completion date minus construction start). When no start date is printed, the registration date is used.
Gap = % built at the inspection minus % of time elapsed at the same date, in percentage points. Behind = a gap below -10 points. Registered date passed = the inspection is after the completion date on the register and the project is not at 100%.
Projection, only for 10% to 99% built: the remaining % divided by the observed pace, where the pace is % built per day since the start date, since the registration date and between the last two inspections we hold (when it rose). The range runs from the earliest to the latest of these estimates.
Limits: Construction does not move in a straight line (a slow start, faster structure, slow finishing), so a straight line from an early reading tends to give later dates than the work will need, and a late reading can give earlier ones. The % built is the DLD inspection figure, not ours.
Source: the Dubai Land Department project register as mirrored per project with its inspection history, read by our register job; 929 DLD records, 28 with two or more dated inspections.
Files: /data/n35a/pace.json · /open/n35a-build.py · /registers/changes/