Home / Dubai / Construction pace against the registered date

Construction pace against the registered date

For Dubai projects with DLD inspection readings: % built against the share of time elapsed to the completion date on the register, and the completion range the observed pace points to. A projection, not a promise.

Updated 23 Nov 2026

A projection from the pace on the register, not a promise, and not a finding about the developer.

815projects compared (DLD % built and dates on the register)
82.8%more than 10 points behind the time elapsed (95% interval 80.1 to 85.3%)
-27.1median gap in points, % built minus % of time elapsed (95% interval -29.5 to -26)
426projects with a projected range (10% to 99% built)
87.1%of them projected after the registered date (95% interval 83.6 to 89.9%)
≤-6090-50115-40162-30178-20130-10900291012207301401
Projects by gap between % built and % of time elapsed, in 10-point bins
Show as a table
Gap (points)Projects
-60 … -5090
-50 … -40115
-40 … -30162
-30 … -20178
-20 … -10130
-10 … 090
0 … 1029
10 … 2012
20 … 307
30 … 401
40 … 501

Projects

Developer: nshama · All

16 projects, page 1
Project% built (inspection)Time elapsedGap (points)PaceRegistered completionProjected rangeRegister
Lexington
Nshama · Al Yelayiss 2
4.5%
13 Aug 2026
61%-56behind30 Sept 2027under 10% built: too early to projectdubairealestateiq.com
Berkshire Park
Nshama · Al Yelayiss 2
17.6%
7 Oct 2026
73%-55.6behind30 Jun 2027Feb 2036dubairealestateiq.com
Haya On the Park
Nshama · Al Yelayiss 2
35.3%
10 Sept 2026
82%-46.9behind26 Feb 2027Aug 2030dubairealestateiq.com
Augusta
Nshama · Al Yelayiss 2
5.3%
10 Sept 2026
51%-45.6behind14 Jan 2028under 10% built: too early to projectdubairealestateiq.com
Odessa
Nshama · Al Yelayiss 2
8%
13 Aug 2026
51%-43behind30 Dec 2027under 10% built: too early to projectdubairealestateiq.com
The Baltimore
Nshama · Al Yelayiss 2
26.3%
7 Oct 2026
65%-38.9behind30 Sept 2027Nov 2031dubairealestateiq.com
Address Grand Downtown
Nshama · Burj Khalifa
10.8%
7 Oct 2026
49%-38.5behind10 Jun 2028Apr 2040dubairealestateiq.com
Alton
Nshama · Al Yelayiss 2
5.2%
18 Aug 2026
42%-36.7behind31 May 2028under 10% built: too early to projectdubairealestateiq.com
Savannah
Nshama · Al Yelayiss 2
43.5%
17 Sept 2026
78%-34.7behind30 Apr 2027Aug 2029dubairealestateiq.com
Camden
Nshama · Al Yelayiss 2
7.2%
18 Aug 2026
42%-34.2behind31 Mar 2028under 10% built: too early to projectdubairealestateiq.com
Hillcrest
Nshama · Al Yelayiss 2
38.4%
17 Sept 2026
72%-33.7behind30 Jun 2027Dec 2029dubairealestateiq.com
Olbia
Nshama · Al Yelayiss 2
0%
25 Apr 2026
30%-30.2behind31 May 2028under 10% built: too early to projectdubairealestateiq.com
Fiori
Nshama · Al Yelayiss 2
0%
25 Apr 2026
22%-21.6behind30 Jun 2028under 10% built: too early to projectdubairealestateiq.com
Rosewell
Nshama · Al Yelayiss 2
0%
26 Jun 2026
21%-20.6behind31 Dec 2028under 10% built: too early to projectdubairealestateiq.com
Ellison
Nshama · Al Yelayiss 2
40.2%
17 Sept 2026
58%-17.4behind30 Nov 2027Feb 2029dubairealestateiq.com
Evelyn On the Park
Nshama · Al Yelayiss 2
0%
26 Jun 2026
15%-15.3behind28 Feb 2029under 10% built: too early to projectdubairealestateiq.com

Method

Time elapsed = (inspection date minus construction start on the register) divided by (registered completion date minus construction start). When no start date is printed, the registration date is used.

Gap = % built at the inspection minus % of time elapsed at the same date, in percentage points. Behind = a gap below -10 points. Registered date passed = the inspection is after the completion date on the register and the project is not at 100%.

Projection, only for 10% to 99% built: the remaining % divided by the observed pace, where the pace is % built per day since the start date, since the registration date and between the last two inspections we hold (when it rose). The range runs from the earliest to the latest of these estimates.

Limits: Construction does not move in a straight line (a slow start, faster structure, slow finishing), so a straight line from an early reading tends to give later dates than the work will need, and a late reading can give earlier ones. The % built is the DLD inspection figure, not ours.

Source: the Dubai Land Department project register as mirrored per project with its inspection history, read by our register job; 929 DLD records, 28 with two or more dated inspections.

Files: /data/n35a/pace.json · /open/n35a-build.py · /registers/changes/