Home / Dubai / Construction pace against the registered date
Construction pace against the registered date
For Dubai projects with DLD inspection readings: % built against the share of time elapsed to the completion date on the register, and the completion range the observed pace points to. A projection, not a promise.
Updated 23 Nov 2026
A projection from the pace on the register, not a promise, and not a finding about the developer.
Show as a table
| Gap (points) | Projects |
|---|---|
| -60 … -50 | 98 |
| -50 … -40 | 119 |
| -40 … -30 | 168 |
| -30 … -20 | 186 |
| -20 … -10 | 140 |
| -10 … 0 | 94 |
| 0 … 10 | 29 |
| 10 … 20 | 13 |
| 20 … 30 | 9 |
| 30 … 40 | 3 |
| 40 … 50 | 1 |
Projects
| Project | % built (inspection) | Time elapsed | Gap (points) | Pace | Registered completion | Projected range | Register |
|---|---|---|---|---|---|---|---|
| Cotier House 2 by Imtiaz Imtiaz Developments · Dubai Islands | 20.2% 23 Oct 2026 | 76% | -56 | behind | 15 Apr 2027 | Sept 2032 – Oct 2032 | dubairealestateiq.com |
| Lexington Nshama · Al Yelayiss 2 | 4.5% 13 Aug 2026 | 61% | -56 | behind | 30 Sept 2027 | under 10% built: too early to project | dubairealestateiq.com |
| Stamn Yuni Stamn · Al Satwa | 11.6% 31 Jul 2026 | 67% | -55.8 | behind | 18 Mar 2027 | Jul 2036 | dubairealestateiq.com |
| Euphoric Residences East & West Properties · Burj Khalifa | 8.3% 27 Jul 2026 | 64% | -55.7 | behind | 31 Dec 2027 | under 10% built: too early to project | dubairealestateiq.com |
| Azizi Emerald Azizi Developments · Um Hurair Second | 3% 17 Nov 2026 | 59% | -55.6 | behind | 13 Feb 2028 | under 10% built: too early to project | dubairealestateiq.com |
| Berkshire Park Nshama · Al Yelayiss 2 | 17.6% 7 Oct 2026 | 73% | -55.6 | behind | 30 Jun 2027 | Feb 2036 | dubairealestateiq.com |
| Rove Home Marasi Drive IRTH Group · Business Bay | 10% 6 Jul 2026 | 66% | -55.6 | behind | 31 Aug 2027 | Apr 2046 | dubairealestateiq.com |
| Binghatti Skyrise Binghatti Developers · Business Bay | 35.9% 22 Oct 2026 | 91% | -55.4 | behind | 31 Dec 2026 | May 2030 – May 2030 | dubairealestateiq.com |
| SAMANA Ibiza SAMANA Developers · Dubai Land Residence Complex (DLRC) | 5.5% 21 Oct 2026 | 61% | -55.4 | behind | 28 Feb 2028 | under 10% built: too early to project | dubairealestateiq.com |
| Opulent Residences East & West Properties · Burj Khalifa | 8.5% 27 Jul 2026 | 64% | -55.4 | behind | 31 Dec 2027 | under 10% built: too early to project | dubairealestateiq.com |
| DAMAC Bay by Cavalli DAMAC Properties · Dubai Harbour | 33.8% 18 Aug 2026 | 89% | -55.3 | behind | 15 Jan 2027 | Mar 2033 – Aug 2033 | dubairealestateiq.com |
| The Palm Crown Dubai Holding · Palm Jumeirah | 22% 9 Nov 2026 | 77% | -55.3 | behind | 15 Jul 2027 | Jan 2035 – Jun 2036 | dubairealestateiq.com |
| Maison Elysee I Pantheon · Jumeirah Village Circle | 21.1% 6 Jul 2026 | 76% | -55.3 | behind | 31 Mar 2027 | May 2035 | dubairealestateiq.com |
| SAMANA Barari Views SAMANA Developers · Majan (Al Barari) | 32.4% 28 Oct 2026 | 87% | -54.9 | behind | 31 Mar 2027 | Nov 2032 | dubairealestateiq.com |
| Elevia Residences Valores · International City Ph 2 & 3 | 9.2% 19 Oct 2026 | 64% | -54.5 | behind | 30 Jun 2027 | under 10% built: too early to project | dubairealestateiq.com |
| SAMANA Ocean Pearl 2 SAMANA Developers · Dubai Islands | 23.3% 17 Sept 2026 | 78% | -54.4 | behind | 31 Mar 2027 | Nov 2032 | dubairealestateiq.com |
| The Waterway by Prestige One Prestige The Waterway Real Estate Development L.L.C · Bukadra | 14.7% 17 Aug 2026 | 69% | -54.3 | behind | 30 Jun 2027 | Oct 2037 | dubairealestateiq.com |
| The Hub Residences by Zazen Zazen · Jabal Ali First | 34% 19 Oct 2026 | 88% | -54.2 | behind | 15 Jan 2027 | Apr 2030 | dubairealestateiq.com |
| Regent Residences Dubai Sankari Place Marina Sky Villa Downtown · Business Bay | 15.5% 5 Nov 2026 | 70% | -54.2 | behind | 31 Dec 2027 | Apr 2041 | dubairealestateiq.com |
| Olivia Residences Karma · Dubai Investment Park First | 38.2% 21 Sept 2026 | 92% | -53.8 | behind | 24 Dec 2026 | Jul 2031 | dubairealestateiq.com |
| The Orchard Place - Tower C Peak Summit Real Estate Development L.L.C · Jumeirah Village Circle | 13% 7 May 2026 | 67% | -53.8 | behind | 31 Mar 2027 | Jun 2038 | dubairealestateiq.com |
| Canal Heights de GRISOGONO DAMAC Properties · Business Bay | 36.3% 17 Aug 2026 | 90% | -53.4 | behind | 31 Dec 2026 | Apr 2032 – Aug 2032 | dubairealestateiq.com |
| All Seasons Residence Abdulrahim Alzarooni · Dubai Sports City | 8.1% 20 Apr 2026 | 61% | -53.3 | behind | 30 Mar 2027 | under 10% built: too early to project | dubairealestateiq.com |
| Mercer House Ellington Properties · Uptown Dubai, Jumeirah Lake Towers | 18.1% 7 Aug 2026 | 71% | -53.2 | behind | 31 Jul 2027 | Apr 2036 – Aug 2037 | dubairealestateiq.com |
| 999 Residences by Reef Luxury Development Reef Luxury Development · Jabal Ali First | 13.2% 27 Aug 2026 | 66% | -52.8 | behind | 30 Jun 2027 | May 2037 | dubairealestateiq.com |
| Sunbliss Residences by Purvanchal Real Estate Developers Purvanchal · Jabal Ali First | 40.1% 12 Nov 2026 | 93% | -52.4 | behind | 31 Dec 2026 | May 2029 | dubairealestateiq.com |
| Villea West Palmridge · Al Satwa | 4.1% 26 Oct 2026 | 56% | -52.3 | behind | 1 Nov 2027 | under 10% built: too early to project | dubairealestateiq.com |
| Canal Crown 2 DAMAC Properties · Business Bay | 32.5% 8 Sept 2026 | 85% | -52.1 | behind | 31 Mar 2027 | Jan 2033 – Jun 2033 | dubairealestateiq.com |
| Bay Villas - Dubai Islands Nakheel · Palm Deira | 22.8% 19 Aug 2026 | 75% | -51.9 | behind | 2 May 2027 | Aug 2033 – Feb 2035 | dubairealestateiq.com |
| Vistara House 2 Object 1 · Jabal Ali First | 2.1% 12 Nov 2026 | 54% | -51.8 | behind | 30 Dec 2027 | under 10% built: too early to project | dubairealestateiq.com |
| Guzel Towers Tiger Properties · Jumeirah Village Triangle | 7.3% 7 Oct 2026 | 59% | -51.6 | behind | 25 Dec 2027 | under 10% built: too early to project | dubairealestateiq.com |
| Gharbi II Residences Rabdan · Jumeirah Village Circle | 20.6% 16 Nov 2026 | 72% | -51.4 | behind | 20 Jul 2027 | Jul 2033 | dubairealestateiq.com |
| Olivia Gardens Residence Segrex Terra · Al Satwa | 24.1% 2 Nov 2026 | 75% | -51.2 | behind | 30 Apr 2027 | Jul 2031 | dubairealestateiq.com |
| ELO 3 (DAMAC Hills 2) DAMAC Properties · DAMAC Hills 2 | 6.4% 15 Apr 2026 | 57% | -50.9 | behind | 30 Jun 2027 | under 10% built: too early to project | dubairealestateiq.com |
| ELO 2 (DAMAC Hills 2) DAMAC Properties · DAMAC Hills 2 | 6.4% 15 Apr 2026 | 57% | -50.9 | behind | 30 Jun 2027 | under 10% built: too early to project | dubairealestateiq.com |
| Sea Coral by Next Realty Next Realty · Palm Deira | 10.7% 2 Oct 2026 | 61% | -50.3 | behind | 31 Aug 2027 | Aug 2038 | dubairealestateiq.com |
| Bluewaters Bay Meraas · Bluewaters Island | 37% 25 Aug 2026 | 87% | -50.2 | behind | 1 Mar 2027 | Aug 2032 – Dec 2032 | dubairealestateiq.com |
| Peace Lagoons by Peace Homes Peace Homes · Dubai Land Residence Complex | 4.2% 21 Oct 2026 | 54% | -50.2 | behind | 30 Sept 2028 | under 10% built: too early to project | dubairealestateiq.com |
| Livia Residence Barco · Madinat Al Mataar | 23% 10 Nov 2026 | 73% | -50 | behind | 30 Apr 2027 | Feb 2031 | dubairealestateiq.com |
| Marea Sharafi · Palm Deira | 5.3% 16 Sept 2026 | 55% | -49.9 | behind | 20 Jun 2027 | under 10% built: too early to project | dubairealestateiq.com |
| Casa Ahs DAMAC Properties · Al Wasl | 16.1% 24 Sept 2026 | 66% | -49.8 | behind | 31 May 2027 | Aug 2033 – May 2034 | dubairealestateiq.com |
| The Acres 3 & Estates Dubai Holding Real Estate · Wadi Al Safa 7 | 14.9% 30 Sept 2026 | 65% | -49.7 | behind | 19 Nov 2027 | Jul 2038 | dubairealestateiq.com |
| Elm at Park Five Deyaar Development PJSC · Dubai Production City | 16.2% 3 Sept 2026 | 66% | -49.6 | behind | 1 Jun 2027 | Jan 2034 – Aug 2035 | dubairealestateiq.com |
| Flow Residences Main Realty · Palm Deira | 7.8% 2 Nov 2026 | 57% | -49.6 | behind | 31 Oct 2027 | under 10% built: too early to project | dubairealestateiq.com |
| The Alba Residences by Omniyat OMNIYAT · Palm Jumeirah | 8.4% 1 Sept 2026 | 58% | -49.5 | behind | 31 Mar 2028 | under 10% built: too early to project | dubairealestateiq.com |
| Cove Edition 4 by Imtiaz Imtiaz Developments · Dubailand (DLRC) | 40% 6 Nov 2026 | 90% | -49.5 | behind | 21 Jan 2027 | Jul 2029 | dubairealestateiq.com |
| Beverly Grande HMB Homes · Al Hebiah First | 2.3% 29 Sept 2026 | 52% | -49.4 | behind | 31 Dec 2027 | under 10% built: too early to project | dubairealestateiq.com |
| Ashwood Residences by Skyland Horizons Real Estate Development Skyland Horizons · Jumeirah Village Triangle | 14.6% 3 Aug 2026 | 64% | -49.4 | behind | 31 Mar 2027 | Jun 2033 | dubairealestateiq.com |
| Ember at Park Five Deyaar Development PJSC · Dubai Production City | 18.2% 17 Sept 2026 | 68% | -49.3 | behind | 1 Jun 2027 | Apr 2033 – Jul 2034 | dubairealestateiq.com |
| Vega Acube · Dubai Sports City | 20.3% 19 Aug 2026 | 69% | -49.1 | behind | 15 May 2027 | Mar 2033 | dubairealestateiq.com |
| Design Quarter Dubai Holding Real Estate · Zaabeel Second | 40.8% 28 Sept 2026 | 90% | -48.8 | behind | 25 Feb 2027 | Nov 2031 | dubairealestateiq.com |
| Vela Viento OMNIYAT · Business Bay | 21.8% 18 May 2026 | 71% | -48.7 | behind | 13 May 2027 | Jan 2033 – Oct 2034 | dubairealestateiq.com |
| Silviana Park Living Object 1 · Jumeirah Village Triangle | 2.7% 13 Aug 2026 | 51% | -48.6 | behind | 30 Mar 2027 | under 10% built: too early to project | dubairealestateiq.com |
| Armani Beach Residences at Palm Jumeirah Arada Developments L.L.C S.O.C · Palm Jumeirah | 10.2% 20 Jul 2026 | 59% | -48.5 | behind | 31 Dec 2027 | Sept 2044 | dubairealestateiq.com |
| Livel Residenza Vantage Capital · Jumeirah Village Circle | 20% 15 Jul 2026 | 68% | -48.3 | behind | 31 Dec 2026 | Jul 2030 | dubairealestateiq.com |
| Binghatti Circle Binghatti Developers · Jumeirah Village Circle (JVC) | 22.1% 26 Oct 2026 | 70% | -48.1 | behind | 31 May 2027 | Apr 2031 – Oct 2031 | dubairealestateiq.com |
| Palm Jebel Ali - Frond C Nakheel · Palm Jabal Ali | 8.6% 28 Sept 2026 | 57% | -48.1 | behind | 17 Jan 2028 | under 10% built: too early to project | dubairealestateiq.com |
| Mira Villas Designed by Bentley Home M I R A Developments L.L.C · Majan | 31.8% 1 Jul 2026 | 80% | -48.1 | behind | 31 Dec 2026 | Oct 2030 | dubairealestateiq.com |
| Laguna Residence One International Real Estate Development L.L.C · City of Arabia | 5.7% 13 Jul 2026 | 54% | -48 | behind | 31 Dec 2027 | under 10% built: too early to project | dubairealestateiq.com |
| Pg Maison Pg · Jabal Ali First | 15% 12 Nov 2026 | 63% | -48 | behind | 31 Dec 2027 | Oct 2037 | dubairealestateiq.com |
Method
Time elapsed = (inspection date minus construction start on the register) divided by (registered completion date minus construction start). When no start date is printed, the registration date is used.
Gap = % built at the inspection minus % of time elapsed at the same date, in percentage points. Behind = a gap below -10 points. Registered date passed = the inspection is after the completion date on the register and the project is not at 100%.
Projection, only for 10% to 99% built: the remaining % divided by the observed pace, where the pace is % built per day since the start date, since the registration date and between the last two inspections we hold (when it rose). The range runs from the earliest to the latest of these estimates.
Limits: Construction does not move in a straight line (a slow start, faster structure, slow finishing), so a straight line from an early reading tends to give later dates than the work will need, and a late reading can give earlier ones. The % built is the DLD inspection figure, not ours.
Source: the Dubai Land Department project register as mirrored per project with its inspection history, read by our register job; 985 DLD records, 28 with two or more dated inspections.
Files: /data/n35a/pace.json · /open/n35a-build.py · /registers/changes/