Construction pace against the registered date
For Dubai projects with DLD inspection readings: % built against the share of time elapsed to the completion date on the register, and the completion range the observed pace points to. A projection, not a promise.
Updated 23 Nov 2026
A projection from the pace on the register, not a promise, and not a finding about the developer.
Show as a table
| Gap (points) | Projects |
|---|---|
| -60 … -50 | 98 |
| -50 … -40 | 119 |
| -40 … -30 | 168 |
| -30 … -20 | 186 |
| -20 … -10 | 140 |
| -10 … 0 | 94 |
| 0 … 10 | 29 |
| 10 … 20 | 13 |
| 20 … 30 | 9 |
| 30 … 40 | 3 |
| 40 … 50 | 1 |
Projects
| Project | % built (inspection) | Time elapsed | Gap (points) | Pace | Registered completion | Projected range | Register |
|---|---|---|---|---|---|---|---|
| Palm Jebel Ali - Frond D Nakheel · Palm Jabal Ali | 8.7% 28 Sept 2026 | 57% | -47.9 | behind | 17 Jan 2028 | under 10% built: too early to project | dubairealestateiq.com |
| Marquis Vista Marquis · Dubai Land Residence Complex | 3.5% 19 Oct 2026 | 51% | -47.9 | behind | 31 Dec 2027 | under 10% built: too early to project | dubairealestateiq.com |
| One by Binghatti Binghatti Developers · Business Bay | 50.2% 14 May 2026 | 98% | -47.8 | behind | 30 May 2026 | Mar 2028 – Jul 2028 | dubairealestateiq.com |
| DAMAC Hills (2) - Park Greens 1 DAMAC Properties · Madinat Hind 4 | 38.9% 30 Oct 2026 | 87% | -47.8 | behind | 30 Mar 2027 | Jan 2031 – May 2031 | dubairealestateiq.com |
| Flora Isle Royal Centurion · Palm Deira | 11.3% 20 Oct 2026 | 59% | -47.6 | behind | 18 Jan 2028 | Oct 2040 | dubairealestateiq.com |
| Cove Edition III by Imtiaz Imtiaz Developments · Dubailand (DLRC) | 44% 26 Oct 2026 | 92% | -47.5 | behind | 25 Dec 2026 | Jan 2029 | dubairealestateiq.com |
| The Boulevard by Prestige One Prestige The Boulevard Real Estate Development L.L.C · Dubai Land Residence Complex | 10.6% 23 Sept 2026 | 58% | -47.5 | behind | 30 Nov 2027 | Aug 2040 | dubairealestateiq.com |
| Edgewater Residences 3 M G S · Palm Deira | 30.4% 31 Aug 2026 | 78% | -47.5 | behind | 31 Jan 2027 | Jan 2030 | dubairealestateiq.com |
| Aykon City 3 DAMAC Properties · Business Bay | 38.3% 3 Nov 2026 | 86% | -47.4 | behind | 30 Dec 2027 | Nov 2031 – Dec 2037 | dubairealestateiq.com |
| Palm Jebel Ali - Frond E Nakheel · Palm Jabal Ali | 9.2% 28 Sept 2026 | 57% | -47.4 | behind | 17 Jan 2028 | under 10% built: too early to project | dubairealestateiq.com |
| Celesto Tower Tarrad · Dubai Land Residence Complex | 0% 28 Oct 2026 | 47% | -47.3 | behind | 31 Dec 2027 | under 10% built: too early to project | dubairealestateiq.com |
| Allura Residences by Citi Developers Citi Developers · Jumeirah Village Circle | 7.8% 23 Jun 2026 | 55% | -47.3 | behind | 27 Jul 2027 | under 10% built: too early to project | dubairealestateiq.com |
| Terra Golf Collection Taraf · Dubai Production City | 20.1% 1 Sept 2026 | 67% | -47.2 | behind | 31 Dec 2027 | Jul 2037 | dubairealestateiq.com |
| Canal Heights 2 de GRISOGONO DAMAC Properties · Business Bay | 36.4% 14 Aug 2026 | 84% | -47.1 | behind | 31 Mar 2027 | Mar 2032 – Jul 2032 | dubairealestateiq.com |
| Sikanta Residences Sikanta · Madinat Al Mataar | 27% 5 Nov 2026 | 74% | -47.1 | behind | 31 Mar 2027 | Dec 2029 | dubairealestateiq.com |
| 311 Boulevard by Bam Eskan BAM · Jumeirah Village Circle | 10% 17 Aug 2026 | 57% | -47 | behind | 1 Oct 2027 | Jan 2040 | dubairealestateiq.com |
| Amazonia Palladium Prime · Al Jadaf | 1.4% 13 Oct 2026 | 48% | -47 | behind | 30 Oct 2027 | under 10% built: too early to project | dubairealestateiq.com |
| Luzora Residences D I A Homes · Palm Deira | 43.5% 9 Nov 2026 | 91% | -47 | behind | 6 Jan 2027 | Oct 2028 | dubairealestateiq.com |
| Azizi Venice 12 Azizi Developments · Madinat Al Mataar | 21.6% 15 Oct 2026 | 69% | -46.9 | behind | 25 Sept 2027 | Dec 2033 – Mar 2034 | dubairealestateiq.com |
| Haya On the Park Nshama · Al Yelayiss 2 | 35.3% 10 Sept 2026 | 82% | -46.9 | behind | 26 Feb 2027 | Aug 2030 | dubairealestateiq.com |
| Maison Elysee III by Pantheon Pantheon · Jumeirah Village Circle | 4.4% 25 Jun 2026 | 51% | -46.9 | behind | 31 Oct 2027 | under 10% built: too early to project | dubairealestateiq.com |
| The Melgrano The Melgrano · Jumeirah Second | 42.8% 12 Oct 2026 | 90% | -46.8 | behind | 31 Dec 2026 | Apr 2029 | dubairealestateiq.com |
| Palm Jebel Ali - Frond B Nakheel · Palm Jabal Ali | 10% 28 Sept 2026 | 57% | -46.6 | behind | 17 Jan 2028 | Jan 2042 – Aug 2043 | dubairealestateiq.com |
| Knightsbridge Park LEOS Developments · Majan | 10.8% 5 Aug 2026 | 57% | -46.6 | behind | 15 Nov 2027 | Oct 2040 | dubairealestateiq.com |
| Serenova Pob1 Properties · Silicon Oasis (Nadd Hessa) | 1.6% 12 Jun 2026 | 48% | -46.6 | behind | 31 Mar 2028 | under 10% built: too early to project | dubairealestateiq.com |
| Nad Al Sheba Gardens Phase 7 Meraas · Nad Al Sheba First (Meydan) | 4% 12 Aug 2026 | 50% | -46.4 | behind | 15 Feb 2028 | under 10% built: too early to project | dubairealestateiq.com |
| Empire Livings Empire · Dubai Science Park | 13.3% 31 Jul 2026 | 60% | -46.4 | behind | 30 Nov 2027 | Jun 2039 | dubairealestateiq.com |
| Dreamlife Residences Nova Power · Palm Deira | 31% 3 Sept 2026 | 77% | -46.3 | behind | 15 Jan 2027 | Jun 2029 | dubairealestateiq.com |
| Verano by Prescott Prescott · Dubai Studio City | 41.1% 29 Sept 2026 | 87% | -46.2 | behind | 31 Dec 2026 | Mar 2029 | dubairealestateiq.com |
| Bhuvi Residence Bravima · Madinat Al Mataar | 31.6% 6 Aug 2026 | 78% | -46.2 | behind | 15 Dec 2026 | Apr 2029 | dubairealestateiq.com |
| DAMAC Lagoons - Lagoon Views 13 DAMAC Properties · Al Hebiah Fifth | 6% 3 Jul 2026 | 52% | -46.1 | behind | 31 Dec 2027 | under 10% built: too early to project | dubairealestateiq.com |
| Verdania Object 1 · Dubai Land Residence Complex | 30.9% 28 Oct 2026 | 77% | -46.1 | behind | 30 Mar 2027 | Dec 2029 | dubairealestateiq.com |
| Legado by Prescott Prescott · Jumeirah Village Circle | 23.3% 30 Sept 2026 | 69% | -46 | behind | 31 Aug 2027 | Jul 2033 | dubairealestateiq.com |
| SAMANA Ivy Gardens 2 SAMANA Developers · Dubai Land Residence Complex | 20% 21 Oct 2026 | 66% | -45.9 | behind | 31 Dec 2027 | Jan 2036 – Jan 2036 | dubairealestateiq.com |
| Claydon House by Ellington Ellington Properties · Bukadra | 15.7% 6 Aug 2026 | 61% | -45.6 | behind | 31 Dec 2027 | Dec 2035 – Jul 2038 | dubairealestateiq.com |
| Augusta Nshama · Al Yelayiss 2 | 5.3% 10 Sept 2026 | 51% | -45.6 | behind | 14 Jan 2028 | under 10% built: too early to project | dubairealestateiq.com |
| DAMAC Riverside - Sage DAMAC Properties · Dubai Investment Park Second | 13.3% 26 Aug 2026 | 59% | -45.5 | behind | 31 Dec 2027 | Mar 2039 – Jun 2040 | dubairealestateiq.com |
| One Park Central by Iman Iman Developers · Jumeirah Village Circle | 32.3% 28 Oct 2026 | 78% | -45.4 | behind | 30 Jun 2027 | Sept 2031 | dubairealestateiq.com |
| Weybridge Gardens 5 LEOS Developments · Dubai Land Residence Complex | 0% 6 Aug 2026 | 45% | -45.3 | behind | 15 Sept 2027 | under 10% built: too early to project | dubairealestateiq.com |
| Enara by Omniyat OMNIYAT · Business Bay | 7.3% 12 Jun 2026 | 52% | -44.9 | behind | 31 Dec 2027 | under 10% built: too early to project | dubairealestateiq.com |
| Palm Jebel Ali - Frond F Nakheel · Palm Jabal Ali | 11.8% 28 Sept 2026 | 57% | -44.8 | behind | 17 Jan 2028 | Jun 2039 – Sept 2040 | dubairealestateiq.com |
| Omoria Hotel Residences Innovate · Palm Deira | 1.1% 11 Nov 2026 | 46% | -44.7 | behind | 31 Jul 2028 | under 10% built: too early to project | dubairealestateiq.com |
| Bay Grove Residences Nakheel · Dubai Islands | 12.3% 23 Oct 2026 | 57% | -44.6 | behind | 15 Mar 2028 | Dec 2039 – Jul 2041 | dubairealestateiq.com |
| Greygate Residences by Ade A D E Properties L.L.C · Jumeirah Village Circle | 10.9% 23 Oct 2026 | 55% | -44.6 | behind | 31 Mar 2028 | Jun 2041 | dubairealestateiq.com |
| Avenue Residence 7 by Nabni Nabni · Jabal Ali First | 17.3% 1 Sept 2026 | 62% | -44.6 | behind | 31 Oct 2027 | Sept 2035 | dubairealestateiq.com |
| The Watercrest Ellington Properties · Mohammed Bin Rashid City | 2.2% 24 Jul 2026 | 47% | -44.5 | behind | 31 Mar 2028 | under 10% built: too early to project | dubairealestateiq.com |
| Parkway by Prestige One Prestige The Parkway Real Estate Development L.L.C · Bukadra | 10.9% 17 Aug 2026 | 55% | -44.3 | behind | 31 Jan 2028 | Apr 2041 | dubairealestateiq.com |
| DAMAC Riverside Views DAMAC Properties · Dubai Investments Park | 5.8% 30 Sept 2026 | 50% | -44.2 | behind | 31 May 2028 | under 10% built: too early to project | dubairealestateiq.com |
| Reportage Village 1 Reportage Properties · Wadi Al Safa 7 | 28% 11 Nov 2026 | 72% | -44.2 | behind | 31 Dec 2027 | Jun 2034 | dubairealestateiq.com |
| Whitecliffs Residences Agp Builders Real Estate Development L.L.C · Palm Deira | 17.5% 26 Oct 2026 | 62% | -44.1 | behind | 31 Dec 2027 | Sept 2035 | dubairealestateiq.com |
| Shoaq Avenew · Palm Deira | 16% 27 Oct 2026 | 60% | -44 | behind | 30 Oct 2027 | Oct 2034 | dubairealestateiq.com |
| Takaya Union Properties PJSC · Motor City | 15.6% 5 Aug 2026 | 59% | -43.8 | behind | 31 Dec 2027 | Aug 2029 – Sept 2037 | dubairealestateiq.com |
| Azha Downtown Residences Azha Downtown Residences · Burj Khalifa | 27% 23 Sept 2026 | 71% | -43.7 | behind | 31 Aug 2027 | Nov 2032 | dubairealestateiq.com |
| Golf Point Emaar Properties · Madinat Al Mataar | 5.4% 4 Nov 2026 | 49% | -43.6 | behind | 31 Oct 2028 | under 10% built: too early to project | dubairealestateiq.com |
| The Pier LMD · Dubai Maritime City | 48.4% 20 Oct 2026 | 92% | -43.6 | behind | 31 Dec 2026 | Mar 2029 | dubairealestateiq.com |
| Evergrin House Object 1 · Al Satwa | 23.6% 7 Aug 2026 | 67% | -43.5 | behind | 30 Dec 2026 | Mar 2029 | dubairealestateiq.com |
| The Central Downtown Aqua Properties · Arjan | 10.5% 21 Apr 2026 | 54% | -43.2 | behind | 31 Mar 2028 | Jul 2045 | dubairealestateiq.com |
| California Residences GFH · City of Arabia | 1.7% 10 Sept 2026 | 45% | -43.1 | behind | 1 Apr 2028 | under 10% built: too early to project | dubairealestateiq.com |
| Odessa Nshama · Al Yelayiss 2 | 8% 13 Aug 2026 | 51% | -43 | behind | 30 Dec 2027 | under 10% built: too early to project | dubairealestateiq.com |
| Arya Residences by Citi Developers Citi Developers · Palm Deira | 3% 15 Sept 2026 | 46% | -43 | behind | 31 Dec 2027 | under 10% built: too early to project | dubairealestateiq.com |
Method
Time elapsed = (inspection date minus construction start on the register) divided by (registered completion date minus construction start). When no start date is printed, the registration date is used.
Gap = % built at the inspection minus % of time elapsed at the same date, in percentage points. Behind = a gap below -10 points. Registered date passed = the inspection is after the completion date on the register and the project is not at 100%.
Projection, only for 10% to 99% built: the remaining % divided by the observed pace, where the pace is % built per day since the start date, since the registration date and between the last two inspections we hold (when it rose). The range runs from the earliest to the latest of these estimates.
Limits: Construction does not move in a straight line (a slow start, faster structure, slow finishing), so a straight line from an early reading tends to give later dates than the work will need, and a late reading can give earlier ones. The % built is the DLD inspection figure, not ours.
Source: the Dubai Land Department project register as mirrored per project with its inspection history, read by our register job; 985 DLD records, 28 with two or more dated inspections.
Files: /data/n35a/pace.json · /open/n35a-build.py · /registers/changes/