Construction pace against the registered date

For Dubai projects with DLD inspection readings: % built against the share of time elapsed to the completion date on the register, and the completion range the observed pace points to. A projection, not a promise.

Updated 23 Nov 2026

A projection from the pace on the register, not a promise, and not a finding about the developer.

860projects compared (DLD % built and dates on the register)
82.7%more than 10 points behind the time elapsed (95% interval 80 to 85.1%)
-27median gap in points, % built minus % of time elapsed (95% interval -29.1 to -26)
452projects with a projected range (10% to 99% built)
86.7%of them projected after the registered date (95% interval 83.3 to 89.5%)
≤-6098-50119-40168-30186-20140-10940291013209303401
Projects by gap between % built and % of time elapsed, in 10-point bins
Show as a table
Gap (points)Projects
-60 … -5098
-50 … -40119
-40 … -30168
-30 … -20186
-20 … -10140
-10 … 094
0 … 1029
10 … 2013
20 … 309
30 … 403
40 … 501

Projects

711 projects, page 3
Project% built (inspection)Time elapsedGap (points)PaceRegistered completionProjected rangeRegister
Palm Jebel Ali - Frond D
Nakheel · Palm Jabal Ali
8.7%
28 Sept 2026
57%-47.9behind17 Jan 2028under 10% built: too early to projectdubairealestateiq.com
Marquis Vista
Marquis · Dubai Land Residence Complex
3.5%
19 Oct 2026
51%-47.9behind31 Dec 2027under 10% built: too early to projectdubairealestateiq.com
One by Binghatti
Binghatti Developers · Business Bay
50.2%
14 May 2026
98%-47.8behind30 May 2026Mar 2028 – Jul 2028dubairealestateiq.com
DAMAC Hills (2) - Park Greens 1
DAMAC Properties · Madinat Hind 4
38.9%
30 Oct 2026
87%-47.8behind30 Mar 2027Jan 2031 – May 2031dubairealestateiq.com
Flora Isle
Royal Centurion · Palm Deira
11.3%
20 Oct 2026
59%-47.6behind18 Jan 2028Oct 2040dubairealestateiq.com
Cove Edition III by Imtiaz
Imtiaz Developments · Dubailand (DLRC)
44%
26 Oct 2026
92%-47.5behind25 Dec 2026Jan 2029dubairealestateiq.com
The Boulevard by Prestige One
Prestige The Boulevard Real Estate Development L.L.C · Dubai Land Residence Complex
10.6%
23 Sept 2026
58%-47.5behind30 Nov 2027Aug 2040dubairealestateiq.com
Edgewater Residences 3
M G S · Palm Deira
30.4%
31 Aug 2026
78%-47.5behind31 Jan 2027Jan 2030dubairealestateiq.com
Aykon City 3
DAMAC Properties · Business Bay
38.3%
3 Nov 2026
86%-47.4behind30 Dec 2027Nov 2031 – Dec 2037dubairealestateiq.com
Palm Jebel Ali - Frond E
Nakheel · Palm Jabal Ali
9.2%
28 Sept 2026
57%-47.4behind17 Jan 2028under 10% built: too early to projectdubairealestateiq.com
Celesto Tower
Tarrad · Dubai Land Residence Complex
0%
28 Oct 2026
47%-47.3behind31 Dec 2027under 10% built: too early to projectdubairealestateiq.com
Allura Residences by Citi Developers
Citi Developers · Jumeirah Village Circle
7.8%
23 Jun 2026
55%-47.3behind27 Jul 2027under 10% built: too early to projectdubairealestateiq.com
Terra Golf Collection
Taraf · Dubai Production City
20.1%
1 Sept 2026
67%-47.2behind31 Dec 2027Jul 2037dubairealestateiq.com
Canal Heights 2 de GRISOGONO
DAMAC Properties · Business Bay
36.4%
14 Aug 2026
84%-47.1behind31 Mar 2027Mar 2032 – Jul 2032dubairealestateiq.com
Sikanta Residences
Sikanta · Madinat Al Mataar
27%
5 Nov 2026
74%-47.1behind31 Mar 2027Dec 2029dubairealestateiq.com
311 Boulevard by Bam Eskan
BAM · Jumeirah Village Circle
10%
17 Aug 2026
57%-47behind1 Oct 2027Jan 2040dubairealestateiq.com
Amazonia
Palladium Prime · Al Jadaf
1.4%
13 Oct 2026
48%-47behind30 Oct 2027under 10% built: too early to projectdubairealestateiq.com
Luzora Residences
D I A Homes · Palm Deira
43.5%
9 Nov 2026
91%-47behind6 Jan 2027Oct 2028dubairealestateiq.com
Azizi Venice 12
Azizi Developments · Madinat Al Mataar
21.6%
15 Oct 2026
69%-46.9behind25 Sept 2027Dec 2033 – Mar 2034dubairealestateiq.com
Haya On the Park
Nshama · Al Yelayiss 2
35.3%
10 Sept 2026
82%-46.9behind26 Feb 2027Aug 2030dubairealestateiq.com
Maison Elysee III by Pantheon
Pantheon · Jumeirah Village Circle
4.4%
25 Jun 2026
51%-46.9behind31 Oct 2027under 10% built: too early to projectdubairealestateiq.com
The Melgrano
The Melgrano · Jumeirah Second
42.8%
12 Oct 2026
90%-46.8behind31 Dec 2026Apr 2029dubairealestateiq.com
Palm Jebel Ali - Frond B
Nakheel · Palm Jabal Ali
10%
28 Sept 2026
57%-46.6behind17 Jan 2028Jan 2042 – Aug 2043dubairealestateiq.com
Knightsbridge Park
LEOS Developments · Majan
10.8%
5 Aug 2026
57%-46.6behind15 Nov 2027Oct 2040dubairealestateiq.com
Serenova
Pob1 Properties · Silicon Oasis (Nadd Hessa)
1.6%
12 Jun 2026
48%-46.6behind31 Mar 2028under 10% built: too early to projectdubairealestateiq.com
Nad Al Sheba Gardens Phase 7
Meraas · Nad Al Sheba First (Meydan)
4%
12 Aug 2026
50%-46.4behind15 Feb 2028under 10% built: too early to projectdubairealestateiq.com
Empire Livings
Empire · Dubai Science Park
13.3%
31 Jul 2026
60%-46.4behind30 Nov 2027Jun 2039dubairealestateiq.com
Dreamlife Residences
Nova Power · Palm Deira
31%
3 Sept 2026
77%-46.3behind15 Jan 2027Jun 2029dubairealestateiq.com
Verano by Prescott
Prescott · Dubai Studio City
41.1%
29 Sept 2026
87%-46.2behind31 Dec 2026Mar 2029dubairealestateiq.com
Bhuvi Residence
Bravima · Madinat Al Mataar
31.6%
6 Aug 2026
78%-46.2behind15 Dec 2026Apr 2029dubairealestateiq.com
DAMAC Lagoons - Lagoon Views 13
DAMAC Properties · Al Hebiah Fifth
6%
3 Jul 2026
52%-46.1behind31 Dec 2027under 10% built: too early to projectdubairealestateiq.com
Verdania
Object 1 · Dubai Land Residence Complex
30.9%
28 Oct 2026
77%-46.1behind30 Mar 2027Dec 2029dubairealestateiq.com
Legado by Prescott
Prescott · Jumeirah Village Circle
23.3%
30 Sept 2026
69%-46behind31 Aug 2027Jul 2033dubairealestateiq.com
SAMANA Ivy Gardens 2
SAMANA Developers · Dubai Land Residence Complex
20%
21 Oct 2026
66%-45.9behind31 Dec 2027Jan 2036 – Jan 2036dubairealestateiq.com
Claydon House by Ellington
Ellington Properties · Bukadra
15.7%
6 Aug 2026
61%-45.6behind31 Dec 2027Dec 2035 – Jul 2038dubairealestateiq.com
Augusta
Nshama · Al Yelayiss 2
5.3%
10 Sept 2026
51%-45.6behind14 Jan 2028under 10% built: too early to projectdubairealestateiq.com
DAMAC Riverside - Sage
DAMAC Properties · Dubai Investment Park Second
13.3%
26 Aug 2026
59%-45.5behind31 Dec 2027Mar 2039 – Jun 2040dubairealestateiq.com
One Park Central by Iman
Iman Developers · Jumeirah Village Circle
32.3%
28 Oct 2026
78%-45.4behind30 Jun 2027Sept 2031dubairealestateiq.com
Weybridge Gardens 5
LEOS Developments · Dubai Land Residence Complex
0%
6 Aug 2026
45%-45.3behind15 Sept 2027under 10% built: too early to projectdubairealestateiq.com
Enara by Omniyat
OMNIYAT · Business Bay
7.3%
12 Jun 2026
52%-44.9behind31 Dec 2027under 10% built: too early to projectdubairealestateiq.com
Palm Jebel Ali - Frond F
Nakheel · Palm Jabal Ali
11.8%
28 Sept 2026
57%-44.8behind17 Jan 2028Jun 2039 – Sept 2040dubairealestateiq.com
Omoria Hotel Residences
Innovate · Palm Deira
1.1%
11 Nov 2026
46%-44.7behind31 Jul 2028under 10% built: too early to projectdubairealestateiq.com
Bay Grove Residences
Nakheel · Dubai Islands
12.3%
23 Oct 2026
57%-44.6behind15 Mar 2028Dec 2039 – Jul 2041dubairealestateiq.com
Greygate Residences by Ade
A D E Properties L.L.C · Jumeirah Village Circle
10.9%
23 Oct 2026
55%-44.6behind31 Mar 2028Jun 2041dubairealestateiq.com
Avenue Residence 7 by Nabni
Nabni · Jabal Ali First
17.3%
1 Sept 2026
62%-44.6behind31 Oct 2027Sept 2035dubairealestateiq.com
The Watercrest
Ellington Properties · Mohammed Bin Rashid City
2.2%
24 Jul 2026
47%-44.5behind31 Mar 2028under 10% built: too early to projectdubairealestateiq.com
Parkway by Prestige One
Prestige The Parkway Real Estate Development L.L.C · Bukadra
10.9%
17 Aug 2026
55%-44.3behind31 Jan 2028Apr 2041dubairealestateiq.com
DAMAC Riverside Views
DAMAC Properties · Dubai Investments Park
5.8%
30 Sept 2026
50%-44.2behind31 May 2028under 10% built: too early to projectdubairealestateiq.com
Reportage Village 1
Reportage Properties · Wadi Al Safa 7
28%
11 Nov 2026
72%-44.2behind31 Dec 2027Jun 2034dubairealestateiq.com
Whitecliffs Residences
Agp Builders Real Estate Development L.L.C · Palm Deira
17.5%
26 Oct 2026
62%-44.1behind31 Dec 2027Sept 2035dubairealestateiq.com
Shoaq
Avenew · Palm Deira
16%
27 Oct 2026
60%-44behind30 Oct 2027Oct 2034dubairealestateiq.com
Takaya
Union Properties PJSC · Motor City
15.6%
5 Aug 2026
59%-43.8behind31 Dec 2027Aug 2029 – Sept 2037dubairealestateiq.com
Azha Downtown Residences
Azha Downtown Residences · Burj Khalifa
27%
23 Sept 2026
71%-43.7behind31 Aug 2027Nov 2032dubairealestateiq.com
Golf Point
Emaar Properties · Madinat Al Mataar
5.4%
4 Nov 2026
49%-43.6behind31 Oct 2028under 10% built: too early to projectdubairealestateiq.com
The Pier
LMD · Dubai Maritime City
48.4%
20 Oct 2026
92%-43.6behind31 Dec 2026Mar 2029dubairealestateiq.com
Evergrin House
Object 1 · Al Satwa
23.6%
7 Aug 2026
67%-43.5behind30 Dec 2026Mar 2029dubairealestateiq.com
The Central Downtown
Aqua Properties · Arjan
10.5%
21 Apr 2026
54%-43.2behind31 Mar 2028Jul 2045dubairealestateiq.com
California Residences
GFH · City of Arabia
1.7%
10 Sept 2026
45%-43.1behind1 Apr 2028under 10% built: too early to projectdubairealestateiq.com
Odessa
Nshama · Al Yelayiss 2
8%
13 Aug 2026
51%-43behind30 Dec 2027under 10% built: too early to projectdubairealestateiq.com
Arya Residences by Citi Developers
Citi Developers · Palm Deira
3%
15 Sept 2026
46%-43behind31 Dec 2027under 10% built: too early to projectdubairealestateiq.com

Next page

Method

Time elapsed = (inspection date minus construction start on the register) divided by (registered completion date minus construction start). When no start date is printed, the registration date is used.

Gap = % built at the inspection minus % of time elapsed at the same date, in percentage points. Behind = a gap below -10 points. Registered date passed = the inspection is after the completion date on the register and the project is not at 100%.

Projection, only for 10% to 99% built: the remaining % divided by the observed pace, where the pace is % built per day since the start date, since the registration date and between the last two inspections we hold (when it rose). The range runs from the earliest to the latest of these estimates.

Limits: Construction does not move in a straight line (a slow start, faster structure, slow finishing), so a straight line from an early reading tends to give later dates than the work will need, and a late reading can give earlier ones. The % built is the DLD inspection figure, not ours.

Source: the Dubai Land Department project register as mirrored per project with its inspection history, read by our register job; 985 DLD records, 28 with two or more dated inspections.

Files: /data/n35a/pace.json · /open/n35a-build.py · /registers/changes/