Home / Dubai / Construction pace against the registered date

Construction pace against the registered date

For Dubai projects with DLD inspection readings: % built against the share of time elapsed to the completion date on the register, and the completion range the observed pace points to. A projection, not a promise.

Updated 23 Nov 2026

A projection from the pace on the register, not a promise, and not a finding about the developer.

860projects compared (DLD % built and dates on the register)
82.7%more than 10 points behind the time elapsed (95% interval 80 to 85.1%)
-27median gap in points, % built minus % of time elapsed (95% interval -29.1 to -26)
452projects with a projected range (10% to 99% built)
86.7%of them projected after the registered date (95% interval 83.3 to 89.5%)
≤-6098-50119-40168-30186-20140-10940291013209303401
Projects by gap between % built and % of time elapsed, in 10-point bins
Show as a table
Gap (points)Projects
-60 … -5098
-50 … -40119
-40 … -30168
-30 … -20186
-20 … -10140
-10 … 094
0 … 1029
10 … 2013
20 … 309
30 … 403
40 … 501

Projects

Developer: iman-developers · All

7 projects, page 1
Project% built (inspection)Time elapsedGap (points)PaceRegistered completionProjected rangeRegister
One Park Central by Iman
Iman Developers · Jumeirah Village Circle
32.3%
28 Oct 2026
78%-45.4behind30 Jun 2027Sept 2031dubairealestateiq.com
One Sky Park by Iman
Iman Developers · Jumeirah Village Circle
21.7%
21 Oct 2026
58%-36.5behind30 Mar 2028Jan 2034dubairealestateiq.com
One Park Square by Iman
Iman Developers · Jumeirah Village Circle
20.1%
22 Sept 2026
48%-28.4behind30 Jun 2028May 2033dubairealestateiq.com
15 Cascade
Iman Developers · Al Hebiah First
5.5%
2 Jul 2026
32%-26.1behind30 Sept 2028under 10% built: too early to projectdubairealestateiq.com
Sierra by Iman
Iman Developers · Al Hebiah First
3.7%
10 Aug 2026
23%-18.8behind30 Jun 2029under 10% built: too early to projectdubairealestateiq.com
113 Residences
Iman Developers · Sufouh Gardens
0%
17 Jun 2026
--not comparable28 Feb 2029under 10% built: too early to projectdubairealestateiq.com
Oxford Cove
Iman Developers · Jumeirah Village Circle
0%
9 Feb 2026
--not comparable30 Mar 2029under 10% built: too early to projectdubairealestateiq.com

Method

Time elapsed = (inspection date minus construction start on the register) divided by (registered completion date minus construction start). When no start date is printed, the registration date is used.

Gap = % built at the inspection minus % of time elapsed at the same date, in percentage points. Behind = a gap below -10 points. Registered date passed = the inspection is after the completion date on the register and the project is not at 100%.

Projection, only for 10% to 99% built: the remaining % divided by the observed pace, where the pace is % built per day since the start date, since the registration date and between the last two inspections we hold (when it rose). The range runs from the earliest to the latest of these estimates.

Limits: Construction does not move in a straight line (a slow start, faster structure, slow finishing), so a straight line from an early reading tends to give later dates than the work will need, and a late reading can give earlier ones. The % built is the DLD inspection figure, not ours.

Source: the Dubai Land Department project register as mirrored per project with its inspection history, read by our register job; 985 DLD records, 28 with two or more dated inspections.

Files: /data/n35a/pace.json · /open/n35a-build.py · /registers/changes/