Construction pace against the registered date

For Dubai projects with DLD inspection readings: % built against the share of time elapsed to the completion date on the register, and the completion range the observed pace points to. A projection, not a promise.

Updated 23 Nov 2026

A projection from the pace on the register, not a promise, and not a finding about the developer.

860projects compared (DLD % built and dates on the register)
82.7%more than 10 points behind the time elapsed (95% interval 80 to 85.1%)
-27median gap in points, % built minus % of time elapsed (95% interval -29.1 to -26)
452projects with a projected range (10% to 99% built)
86.7%of them projected after the registered date (95% interval 83.3 to 89.5%)
≤-6098-50119-40168-30186-20140-10940291013209303401
Projects by gap between % built and % of time elapsed, in 10-point bins
Show as a table
Gap (points)Projects
-60 … -5098
-50 … -40119
-40 … -30168
-30 … -20186
-20 … -10140
-10 … 094
0 … 1029
10 … 2013
20 … 309
30 … 403
40 … 501

Projects

985 projects, page 16
Project% built (inspection)Time elapsedGap (points)PaceRegistered completionProjected rangeRegister
Evergreens (DAMAC Hills 2)
DAMAC Properties · DAMAC Hills 2
48.1%
30 Oct 2026
--not comparable-no projectiondubairealestateiq.com
Golf Gate 2 (DAMAC Hills)
DAMAC Properties · DAMAC Hills
80.4%
20 Jul 2026
--not comparable-no projectiondubairealestateiq.com
DAMAC Casa
DAMAC Properties · Al Sufouh
33.6%
18 Aug 2026
--not comparable-no projectiondubairealestateiq.com
DAMAC Bay 2 by Cavalli
DAMAC Properties · Dubai Harbour
30.3%
15 Jul 2026
--not comparable-no projectiondubairealestateiq.com
Sobha Skyparks
Sobha Realty · Business Bay
0%
23 Oct 2025
--not comparable31 Dec 2032under 10% built: too early to projectdubairealestateiq.com
Artistry Two Residences
Select Group · Zaabeel Second
0%
14 Jan 2026
--not comparable9 Feb 2029under 10% built: too early to projectdubairealestateiq.com
SAMANA Greenfield 2
SAMANA Developers · Al Warsan (International City Ph 2 & 3)
0%
18 May 2026
--not comparable31 Aug 2029under 10% built: too early to projectdubairealestateiq.com
SAMANA Ivy Gardens
SAMANA Developers · Dubai Land Residence Complex (DLRC)
40.7%
1 Oct 2026
--not comparable-no projectiondubairealestateiq.com
SAMANA South Haven
SAMANA Developers · Dubai South
0%
4 May 2026
--not comparable31 Dec 2028under 10% built: too early to projectdubairealestateiq.com
SAMANA South Haven 2
SAMANA Developers · Dubai South
0%
7 Jul 2026
--not comparable30 Jun 2029under 10% built: too early to projectdubairealestateiq.com
Golf Edge
Emaar Properties · Madinat Al Mataar
0%
5 Nov 2024
--not comparable28 Feb 2029under 10% built: too early to projectdubairealestateiq.com
Grand Polo - Equestra
Emaar Properties · Grand Polo Club, Dubai Investment Park Second
1%
4 May 2026
--not comparable31 Aug 2029under 10% built: too early to projectdubairealestateiq.com
Grove Ridge
Emaar Properties · Madinat Al Mataar
0%
4 Nov 2025
--not comparable30 Sept 2029under 10% built: too early to projectdubairealestateiq.com
Vista Ridge
Emaar Properties · Madinat Al Mataar
0%
4 Nov 2025
--not comparable30 Sept 2029under 10% built: too early to projectdubairealestateiq.com
Terra Woods
Emaar Properties · Madinat Al Mataar
0%
28 Jan 2026
--not comparable31 Mar 2030under 10% built: too early to projectdubairealestateiq.com
Fior 1
Emaar Properties · Dubai Maritime City
0%
11 Dec 2025
--not comparable31 Jul 2030under 10% built: too early to projectdubairealestateiq.com
Golf Trails
Emaar Properties · Madinat Al Mataar
0%
1 Jul 2026
--not comparable31 Oct 2030under 10% built: too early to projectdubairealestateiq.com
Palace by the Beach
Emaar Properties · Dubai Marina
0%
12 Jan 2026
--not comparable30 Nov 2031under 10% built: too early to projectdubairealestateiq.com
Azizi Abraham
Azizi Developments · Jabal Ali Industrial Second
2%
24 Mar 2026
--not comparable4 Aug 2027under 10% built: too early to projectdubairealestateiq.com
Azizi Gabriel
Azizi Developments · Jabal Ali Industrial Second
0%
17 Nov 2025
--not comparable4 Jul 2028under 10% built: too early to projectdubairealestateiq.com
Azizi Rose
Azizi Developments · Jabal Ali Industrial Second
0%
16 Feb 2026
--not comparable4 Jul 2028under 10% built: too early to projectdubairealestateiq.com
Raw District 2 by Imtiaz
Imtiaz Developments · Jabal Ali Industrial Second
0%
8 Jul 2026
--not comparable1 Dec 2029under 10% built: too early to projectdubairealestateiq.com
Bay Estate
Nakheel · Palm Deira
0%
20 Aug 2026
--not comparable15 Aug 2030under 10% built: too early to projectdubairealestateiq.com
Palm Central Private Residences - Frond N
Nakheel · Palm Jabal Ali
0%
27 Feb 2026
--not comparable13 Dec 2030under 10% built: too early to projectdubairealestateiq.com
The Greens at Sobha Sanctuary
Sobha Realty · Al Yufrah 1
0%
15 Jul 2026
--not comparable31 Aug 2030under 10% built: too early to projectdubairealestateiq.com
The Grove at Sobha Sanctuary
Sobha Realty · Al Yufrah 1
0%
20 May 2026
--not comparable31 Aug 2030under 10% built: too early to projectdubairealestateiq.com
The Woods
Sobha Realty · Al Yufrah 1
0%
21 May 2026
--not comparable30 Dec 2030under 10% built: too early to projectdubairealestateiq.com
Arancia Yards 2 by Beyond
Beyond Developments · City of Arabia
0%
9 Jul 2026
--not comparable30 Jan 2029under 10% built: too early to projectdubairealestateiq.com
Hado by Beyond
Beyond Developments · Palm Deira
0%
16 Jun 2026
--not comparable30 Jun 2029under 10% built: too early to projectdubairealestateiq.com
Cedarwood Estates
Wasl · Dubai Production City
0%
8 Jan 2026
--not comparable4 Oct 2028under 10% built: too early to projectdubairealestateiq.com
Pinewood Estate Homes
Wasl · Dubai Production City
0.3%
11 Mar 2026
--not comparable17 Nov 2028under 10% built: too early to projectdubairealestateiq.com
Cedarwood Estates-South
Wasl · Dubai Production City
0%
14 May 2026
--not comparable31 Jan 2029under 10% built: too early to projectdubairealestateiq.com
Avenue Park Towers II
Wasl · Al Kifaf
0%
8 Jun 2026
--not comparable6 Mar 2030under 10% built: too early to projectdubairealestateiq.com
1wood Residence 2
Object 1 · Jumeirah Village Circle
0%
3 Mar 2026
--not comparable20 Oct 2027under 10% built: too early to projectdubairealestateiq.com
Sky Level 1
Object 1 · Jumeirah Village Circle
0%
13 May 2026
--not comparable28 Feb 2029under 10% built: too early to projectdubairealestateiq.com
Inaura Hotels & Residences
Arada · Burj Khalifa
1.3%
1 Oct 2026
--not comparable14 Jun 2030under 10% built: too early to projectdubairealestateiq.com
Expo Valley Views
Expo City Dubai · Madinat Al Mataar
0%
14 Jul 2026
--not comparable31 Oct 2029under 10% built: too early to projectdubairealestateiq.com
113 Residences
Iman Developers · Sufouh Gardens
0%
17 Jun 2026
--not comparable28 Feb 2029under 10% built: too early to projectdubairealestateiq.com
Oxford Cove
Iman Developers · Jumeirah Village Circle
0%
9 Feb 2026
--not comparable30 Mar 2029under 10% built: too early to projectdubairealestateiq.com
Sera Gardens by Vision
Vision Developments · Dubai Production City
0%
7 Apr 2026
--not comparable1 Apr 2028under 10% built: too early to projectdubairealestateiq.com
Sky Line by Peace Homes
Peace Homes · Dubai Land Residence Complex
0%
14 Oct 2025
--not comparable30 May 2030under 10% built: too early to projectdubairealestateiq.com
Hadley Heights 2
LEOS Developments · Dubai Sports City
0%
4 Sept 2025
--not comparable20 Oct 2027under 10% built: too early to projectdubairealestateiq.com
Tresora by Wadan
Wadan · Jumeirah Village Circle
0%
17 Mar 2026
--not comparable30 Mar 2028under 10% built: too early to projectdubairealestateiq.com
Weston
Wadan · Dubai Land Residence Complex
0%
29 Jun 2026
--not comparable31 Dec 2028under 10% built: too early to projectdubairealestateiq.com
Sol Terra Casa I
SOL Properties · Jumeirah Village Circle
0%
2 Mar 2026
--not comparable15 Jun 2028under 10% built: too early to projectdubairealestateiq.com
Beverly Crown
HMB Homes · Jumeirah Village Circle
0%
25 Jun 2026
--not comparable31 Dec 2028under 10% built: too early to projectdubairealestateiq.com
The Community - Sports Arena
Aqua Properties · Dubai Sports City
22.4%
31 Oct 2024
--not comparable31 Oct 2027no projectiondubairealestateiq.com
Elanora by Zoya
Zoya · Dubai Industrial City (Saih Shuaib 2)
0%
16 Apr 2026
--not comparable31 Mar 2028under 10% built: too early to projectdubairealestateiq.com
Elinor
Zoya · Madinat Al Mataar
0%
1 Jul 2026
--not comparable30 Jun 2028under 10% built: too early to projectdubairealestateiq.com
Izel by Zoya
Zoya · Dubai Land Residence Complex
0%
10 Mar 2026
--not comparable15 Sept 2028under 10% built: too early to projectdubairealestateiq.com
SVN Residences
Metrical · Jumeirah Village Circle
0%
22 Jun 2026
--not comparable31 Dec 2028under 10% built: too early to projectdubairealestateiq.com
Rabdan Avenue
Rabdan · Nad Al Shiba First
0%
25 Jun 2026
--not comparable1 Mar 2029under 10% built: too early to projectdubairealestateiq.com
Island Living by Condor
Condor · Palm Deira
0%
20 Nov 2025
--not comparable10 Jan 2027under 10% built: too early to projectdubairealestateiq.com
J188
Jad Global · Al Jadaf
0%
11 Nov 2025
--not comparable30 Apr 2028under 10% built: too early to projectdubairealestateiq.com
Velor
Ginco · Business Bay
0%
12 Feb 2025
--not comparable1 Nov 2027under 10% built: too early to projectdubairealestateiq.com
Aum 99 Residences
Aum 99 Home · Dubai Land Residence Complex
0%
4 Aug 2025
--not comparable31 Mar 2029under 10% built: too early to projectdubairealestateiq.com
Tivanno Residence
AYS · Palm Deira
5.3%
1 Jun 2026
--not comparable31 Dec 2027under 10% built: too early to projectdubairealestateiq.com
The Wow Tower
Riviera · Dubai Land Residence Complex
0%
5 Oct 2026
--not comparable30 Sept 2029under 10% built: too early to projectdubairealestateiq.com
Arlington Park II by Majid
Majid Developments · Dubai Land Residence Complex
0%
4 Mar 2026
--not comparable1 Apr 2028under 10% built: too early to projectdubairealestateiq.com
Trevino
Avelon · Jumeirah Village Circle
0%
2 Jul 2025
--not comparable30 Jun 2027under 10% built: too early to projectdubairealestateiq.com

Next page

Method

Time elapsed = (inspection date minus construction start on the register) divided by (registered completion date minus construction start). When no start date is printed, the registration date is used.

Gap = % built at the inspection minus % of time elapsed at the same date, in percentage points. Behind = a gap below -10 points. Registered date passed = the inspection is after the completion date on the register and the project is not at 100%.

Projection, only for 10% to 99% built: the remaining % divided by the observed pace, where the pace is % built per day since the start date, since the registration date and between the last two inspections we hold (when it rose). The range runs from the earliest to the latest of these estimates.

Limits: Construction does not move in a straight line (a slow start, faster structure, slow finishing), so a straight line from an early reading tends to give later dates than the work will need, and a late reading can give earlier ones. The % built is the DLD inspection figure, not ours.

Source: the Dubai Land Department project register as mirrored per project with its inspection history, read by our register job; 985 DLD records, 28 with two or more dated inspections.

Files: /data/n35a/pace.json · /open/n35a-build.py · /registers/changes/