Home / Dubai / Construction pace against the registered date
Construction pace against the registered date
For Dubai projects with DLD inspection readings: % built against the share of time elapsed to the completion date on the register, and the completion range the observed pace points to. A projection, not a promise.
Updated 23 Nov 2026
A projection from the pace on the register, not a promise, and not a finding about the developer.
Show as a table
| Gap (points) | Projects |
|---|---|
| -60 … -50 | 98 |
| -50 … -40 | 119 |
| -40 … -30 | 168 |
| -30 … -20 | 186 |
| -20 … -10 | 140 |
| -10 … 0 | 94 |
| 0 … 10 | 29 |
| 10 … 20 | 13 |
| 20 … 30 | 9 |
| 30 … 40 | 3 |
| 40 … 50 | 1 |
Projects
| Project | % built (inspection) | Time elapsed | Gap (points) | Pace | Registered completion | Projected range | Register |
|---|---|---|---|---|---|---|---|
| Lawncrest by Zimaya Zimaya · Dubai Production City | 0% 8 Jun 2026 | - | - | not comparable | 14 Jun 2029 | under 10% built: too early to project | dubairealestateiq.com |
| Eira Neoterra Dpc · Dubai Production City | 0% 7 Apr 2026 | - | - | not comparable | 30 Jun 2029 | under 10% built: too early to project | dubairealestateiq.com |
| Timber Terrace Timber Terrace Development L.L.C · Madinat Al Mataar | 0% 11 Nov 2025 | - | - | not comparable | 31 Jul 2027 | under 10% built: too early to project | dubairealestateiq.com |
| Vivanti Residences by Meteora Meteora Elite · Jumeirah Village Circle | 0% 6 Feb 2025 | - | - | not comparable | 1 Jan 2028 | under 10% built: too early to project | dubairealestateiq.com |
| J-Haus Residences Jvc Hirat · Jumeirah Village Circle | 56.7% 27 May 2025 | - | - | not comparable | 30 Jun 2027 | no projection | dubairealestateiq.com |
| Firoza Ever Glory · Palm Deira | 0% 2 Sept 2025 | - | - | not comparable | 31 Oct 2027 | under 10% built: too early to project | dubairealestateiq.com |
| Zyra Hills Laraix · International City Ph 2 & 3 | 0% 25 Nov 2025 | - | - | not comparable | 30 Mar 2028 | under 10% built: too early to project | dubairealestateiq.com |
| Vedaire Residences Elton · Nad Al Shiba First | 0% 10 Apr 2025 | - | - | not comparable | 31 Mar 2028 | under 10% built: too early to project | dubairealestateiq.com |
| Havencia Ala · Dubai Land Residence Complex | 0% 3 Apr 2026 | - | - | not comparable | 31 Mar 2028 | under 10% built: too early to project | dubairealestateiq.com |
| Me Do Re Business Me Do Re · Jumeirah Lakes Towers | 24.5% 21 Nov 2024 | - | - | not comparable | 20 Sept 2029 | no projection | dubairealestateiq.com |
| The Hudson Crystal Prime · Jumeirah Village Circle | 0% 19 Jan 2026 | - | - | not comparable | 14 Feb 2029 | under 10% built: too early to project | dubairealestateiq.com |
| Squarex One Tasmeer Indigo · Jumeirah Village Circle | 0% 24 Dec 2025 | - | - | not comparable | 30 Jun 2028 | under 10% built: too early to project | dubairealestateiq.com |
| Bond Living Pearlshire Dirc · Dubai Land Residence Complex | 0% 10 Sept 2025 | - | - | not comparable | 30 Sept 2028 | under 10% built: too early to project | dubairealestateiq.com |
| Park Residency Park Residency · International City Ph 2 & 3 | 0% 9 Jan 2026 | - | - | not comparable | 20 Jul 2029 | under 10% built: too early to project | dubairealestateiq.com |
| Rose Gold Residences by Zee Development Zee · Jumeirah Village Circle | 0% 22 Apr 2025 | - | - | not comparable | 30 Jan 2028 | under 10% built: too early to project | dubairealestateiq.com |
| One by Preston Preston Properties L.L.C · Madinat Al Mataar | 0% 16 Dec 2024 | - | - | not comparable | 31 Dec 2027 | under 10% built: too early to project | dubairealestateiq.com |
| Listone Residence Lion Stone Properties L.L.C · International City Ph 1 | 0% 5 Feb 2026 | - | - | not comparable | 31 Aug 2027 | under 10% built: too early to project | dubairealestateiq.com |
| Manam Pearl Manam · Jabal Ali First | 0% 3 Jul 2025 | - | - | not comparable | 30 Jun 2028 | under 10% built: too early to project | dubairealestateiq.com |
| Oceara Parkview Residences Pps Properties L.L.C · Palm Deira | 0% 7 Aug 2026 | - | - | not comparable | 31 Oct 2028 | under 10% built: too early to project | dubairealestateiq.com |
| Sadaat Tower Gulab · International City Ph 2 & 3 | 32.1% 2 Jul 2026 | - | - | not comparable | 31 Jan 2027 | no projection | dubairealestateiq.com |
| Arib Collection Arib Properties For · Dubai Land Residence Complex | 0% 9 Jul 2025 | - | - | not comparable | 1 Dec 2027 | under 10% built: too early to project | dubairealestateiq.com |
| Eywa the Way of Water Revolution Palm · Business Bay | 0% 23 Oct 2025 | - | - | not comparable | 15 Oct 2028 | under 10% built: too early to project | dubairealestateiq.com |
| Lincoln Star Residence II Lincoln Rise · Madinat Al Mataar | 5.3% 9 Apr 2026 | - | - | not comparable | 31 Aug 2027 | under 10% built: too early to project | dubairealestateiq.com |
| X11 Bamx Eleven Real Estate Development L.L.C · Madinat Al Mataar | 0% 12 Aug 2026 | - | - | not comparable | 25 Dec 2028 | under 10% built: too early to project | dubairealestateiq.com |
| Maak Residence Maakdream Properties · Madinat Al Mataar | 0% 20 Nov 2025 | - | - | not comparable | 30 Nov 2027 | under 10% built: too early to project | dubairealestateiq.com |
Method
Time elapsed = (inspection date minus construction start on the register) divided by (registered completion date minus construction start). When no start date is printed, the registration date is used.
Gap = % built at the inspection minus % of time elapsed at the same date, in percentage points. Behind = a gap below -10 points. Registered date passed = the inspection is after the completion date on the register and the project is not at 100%.
Projection, only for 10% to 99% built: the remaining % divided by the observed pace, where the pace is % built per day since the start date, since the registration date and between the last two inspections we hold (when it rose). The range runs from the earliest to the latest of these estimates.
Limits: Construction does not move in a straight line (a slow start, faster structure, slow finishing), so a straight line from an early reading tends to give later dates than the work will need, and a late reading can give earlier ones. The % built is the DLD inspection figure, not ours.
Source: the Dubai Land Department project register as mirrored per project with its inspection history, read by our register job; 985 DLD records, 28 with two or more dated inspections.
Files: /data/n35a/pace.json · /open/n35a-build.py · /registers/changes/