Kolaboro / Data stories / Malaysia, November 2026
Malaysia off-plan data, November 2026
Monthly figures for 19 reviewed off-plan projects in Malaysia, computed from Kolaboro data. Every number links to its file.
Figures as of 7 Nov 2026. The edition of the current month updates with each data refresh until the month ends.
Delivery delays
Of 18 tracked projects in Malaysia with a handover date, 2 are past the first date on record (11.1%). Median: 0 months past that date. /data/delay-index.json
Dated promises
20 dated promises on record: 0 kept, 0 date passed and not done, 14 moved later, 6 still ahead, 0 passed with no evidence either way. /data/promises.json
Permits and deposit protection
14 of 19 reviewed projects publish a permit or licence number (74%). 8 state deposit protection (42%). /data/bali-cases.json
Advertised prices
Index of advertised "from" prices (chained, 1 Nov 2026 = 100): 100 on 1 Nov 2026, 100 on 5 Nov 2026, from 35 repeated price observations. /data/price-index.json
What changed on developer pages
4 changes found between dated copies of developer pages in Malaysia this month, in 1 projects. /data/promise-drift.json
- Crown Penang: Price from: +9.5% first seen 1 Nov 2026 ·
4698a9bf72c03beb→246dfe0b7fcc536b· compare copies - Crown Penang: Site or floor plans shown: no to yes first seen 1 Nov 2026 ·
4698a9bf72c03beb→246dfe0b7fcc536b· compare copies - Crown Penang: Permit or approval claimed: no to yes first seen 1 Nov 2026 ·
4698a9bf72c03beb→246dfe0b7fcc536b· compare copies - Crown Penang: Handover year: 2029 to 2028 first seen 1 Nov 2026 ·
4698a9bf72c03beb→246dfe0b7fcc536b· compare copies
Added to tracking this month
No project in Malaysia was added to tracking this month.
Every reviewed project in Malaysia
| Project | Handover on record | Months past first date | Permit number | Checks public | Last checked |
|---|---|---|---|---|---|
| 111 Menerung (One Eleven Menerung) | January 2027 | 11 | stated | 4/6 | 5 Nov 2026 |
| Aethera Residences | June 2030 | 0 | stated | 4/6 | 7 Nov 2026 |
| Amiba Bukit Bintang (formerly IBN Bukit Bintang) | December 2029 | 0 | stated | 5/6 | 6 Nov 2026 |
| Armani Hallson KLCC (Residensi Armani Hallson KLCC) | June 2030 | 0 | stated | 6/6 | 7 Nov 2026 |
| AVÉA @ Andaman Island | July 2030 | 0 | stated | 3/6 | 31 Oct 2026 |
| Branniganz Suites @ Bukit Bintang | January 2029 | 0 | stated | 6/6 | 6 Nov 2026 |
| CloutHaus Residences | 2029 | 0 | Not published | 3/6 | 6 Nov 2026 |
| Crown Penang | December 2028 | 0 | stated | 5/6 | 7 Nov 2026 |
| Divine KLCC | September 2032 | 0 | Not published | 2/6 | 7 Nov 2026 |
| Forest City | Not published | 0 | Not published | 2/6 | 6 Nov 2026 |
| KL360 @ Menara GD | December 2030 | 0 | stated | 5/6 | 6 Nov 2026 |
| Lumina Residence | Q4 2028 | 0 | Not published | 1/6 | 31 Oct 2026 |
| One Seputeh Residences | July 2030 | 0 | stated | 5/6 | 7 Nov 2026 |
| Pavilion Damansara Heights Phase 2 (Royal Suites and Imperial Residences) | August 2030 | 3 | stated | 6/6 | 6 Nov 2026 |
| Pavilion Square Kuala Lumpur (Luxury Residences) | Q3 2029 | 0 | stated | 4/6 | 7 Nov 2026 |
| R&F Princess Cove Phase 3, New Casa Suites (Mercu 3) | December 2029 | 0 | stated | 6/6 | 7 Nov 2026 |
| Skypark Kepler @ Lido Waterfront | Q4 2029 | 0 | Not published | 3/6 | 7 Nov 2026 |
| Sunway Velocity 3 (Towers A and B) | May 2028 | 0 | stated | 6/6 | 6 Nov 2026 |
| The Westin Residences Penang | 2028 | 0 | stated | 6/6 | 7 Nov 2026 |
How to cite
Kolaboro, Malaysia off-plan data, November 2026, https://kolaboro.com/stories/2026-11/malaysia/, data of 7 Nov 2026, CC BY 4.0.