Nov 9SHIPPEDFull working test of the site (checks, tools, accounts, feeds, API): a saved X-ray now shows in your dashboard, project pages have a Save to my list button again, and the update feed is currentNov 9SHIPPEDSecurity hardening: pages now refuse inline script handlers, links built from third-party data cannot run scripts, the map and text-reading libraries are pinned with integrity hashes, and payment-check lookups are rate limitedNov 9SHIPPEDSpeed: the browser no longer restyles the whole page after every small change, project and developer pages are answered from an edge copy before any data is read, sections far from the screen are drawn as you get near them, and the open numbers page keeps its figures for a minuteNov 9SHIPPEDLookalike websites: a daily watch for new websites whose names resemble the developer and project websites we track, with registration and certificate dates, on developer pages and at /watch/lookalikes/Nov 9DATASanctions lists: developer company names are screened daily against the entity entries of the OFAC, UK and UN lists; developer pages show the lists and date when there is no matchNov 9DATACorporate family on developer pages: parents and subsidiaries from the GLEIF register (CC0) for 39 developers matched by exact legal name, and a new family link type in the developer graphNov 9DATATwo Birmingham project pins corrected (they sat one degree too far north); their map-based sections stay hidden until the next monthly rebuild uses the new pinsNov 9SHIPPEDProtected land near the pin on 125 project pages: Natura 2000 sites within 2 km, England green belt and other designations, the Spanish coast law easements and mapped nature reserves, with distances and layer datesNov 9SHIPPEDThe map's own history at each plot: when the buildings, roads and land use within 150 m were first drawn in OpenStreetMap and last changed, as a small timeline on 125 project pagesNov 9SHIPPEDSite check on 560 page views and 3,078 links: the two account checks merged into one, clearer tool descriptions and jump links, a country search, an accessible pricing table and a tidier free check on phonesNov 9SHIPPEDShort-let reality check on 28 project pages: Inside Airbnb listings within 1 km, median nightly price and their occupancy estimate, next to any rental yield the page we track printsNov 9DATARecorded sale prices within 1 km on 14 project pages: HM Land Registry (England), DVF (France) and NYC rolling sales, medians and price per m2 next to the developer's own headline priceNov 9SHIPPEDProject and developer pages are easier to read: identical price copies merged into one row, the overdue date sits next to the date it is about, correct singular wording, Arabic names no longer flip punctuation, and the website-health method is translatedNov 9SHIPPEDAny plot from space: pin any spot and get one clear Sentinel-2 picture per quarter since 2017, made on demand, and turn it or a project's time machine into a shareable time-lapse GIFNov 8DATASatellite images back to January 2017: the monthly Sentinel-2 series on 125 project pages now covers almost ten yearsNov 8SHIPPEDSee the site: open street-level photos within 200 m of the pin on 59 project pages, and a 3D view with terrain and 12,328 mapped buildings on 125
Changelog →
Fictional example. The project, people and numbers are made up; the method, the checks and the evidence tools are exactly what our clients get. PDF version

Construction monitoring report · Milestone 3 of 6 · 28 Oct 2026

Villa Kenanga, Canggu, Bali

Prepared for Sample client · 3-bedroom villa · €240,000 · leasehold 30 + 20 years

Agent: Made S. · verified agent, 31 checksSenior review: passed · 2 correctionsCopilot: 5 flags · 3 closed, 2 in your to-do
Our adviceNo red flags at milestone 3

The evidence supports paying instalment 3 (€48,000) once the developer sends the revised schedule in writing.

73Trust Score

Your money vs what is built

Paid so far€96,00040% of the price
Verified built≈ 58%by our agent, 27 Oct
Your margin of safety+18 ptsbuilt ahead of paid
Paid40%
Built58%
3
Roof structure20% · €48,000 · due 4 Nov 2026
Evidence supports paying
4
Walls & MEP20% · €48,000 · after next visit
Locked until verified
5
Finishes15% · €36,000 · -
Locked until verified
6
Handover5% · €12,000 · after final inspection
Locked until verified

The nine checks

Each one with its evidence. Open any check to see what we looked at.

1Land title92Clear

Certificate SHM 04512 (fictional) checked at the land office. Owner matches the lessor in your contract. No mortgage or dispute registered.

  • 📎 Land office extract, 23 Oct 2026
  • 📎 Lease registered with notary (deed 118/2025)
2Building permit88Clear

PBG permit found in the official system. Plot, floor area (212 m²) and use (tourism accommodation) match the villa being built.

  • 📎 PBG record screenshot, 24 Oct 2026
  • 📎 Permit drawing set, 14 sheets
3Developer record64Watch

Two of three past projects handed over; one was 7 months late. No court cases found in the last 5 years.

  • 📎 Company registry extract
  • 📎 2 buyer interviews
4Progress vs plan81Clear

Milestone 3 (roof structure) complete. Measured roof span 11.96 m vs 12.00 m on the drawings.

  • 📎 14 GPS-stamped photos, 2 videos
  • 📎 Laser measurements, 6 points
5Where your money goes85Clear

Instalment 3 goes to the contracting company PT Kenanga Bangun (fictional), the same entity named in the contract and the permit.

  • 📎 Bank account letter
  • 📎 Contract clause 4.2
6Contract fairness58Watch

No penalty for late delivery and no refund clause if the permit is revoked. Ask for both before instalment 4.

  • 📎 Contract review, 9 pages
  • 📎 Suggested wording sent to you
7Transparency77Clear

Developer answered 11 of 12 questions in writing within 48 hours and shared the permit drawings.

  • 📎 Q&A log
8Buyer voice61Watch

3 buyers in this project contacted. Two satisfied; one reports slow answers on finishes.

  • 📎 3 calls, notes
9Realistic promises49Watch

Advertised 14% rental yield. Nearby comparable villas show 7 to 9% net after costs.

  • 📎 12 comparable listings
  • 📎 Occupancy data, last 12 months

Site visit, 27 Oct 2026

Every photo is stamped in our field app with GPS, accuracy and time, and fingerprinted with SHA-256 the moment it's taken. Press Verify: your browser recomputes the fingerprint of the file and checks it hasn't changed.

  • 09:38 Arrived. GPS lock ±4 m, inside plot boundary.
  • 09:41 to 10:21 14 photos, 2 videos, 6 laser measurements.
  • 10:30 Spoke with site manager (Wayan, contractor PT Kenanga Bangun).
  • 10:42 Permit board on site matches PBG number.
  • 11:05 Report draft uploaded; copilot cross-check run.
  • Next day Senior review: 2 corrections, approved.
📍 -8.64712, 115.13041 ±4 m · 27 Oct 2026 09:41 WITA
Wide shot from the access road: frame, three floors, roof structure in place.
SHA-256 141f25e22814…a8dbfc
📍 -8.64716, 115.13049 ±4 m · 27 Oct 2026 09:52 WITA
Column and slab detail, east side. Matches drawing S-03.
SHA-256 f943ea98b73b…9fa520
📍 -8.64709, 115.13044 ±4 m · 27 Oct 2026 10:04 WITA
Block walls, ground floor. Rendering not started, as scheduled.
SHA-256 ae93de0a5f2c…0ca18e
📍 -8.64688, 115.13072 ±4 m · 27 Oct 2026 10:21 WITA
Neighbouring finished villa by the same contractor: finish quality reference.
SHA-256 388b6acd365a…16d509

Illustrative photos (fictional project): Fitrah 9131 (CC BY 4.0); Isaacvp (CC BY-SA 4.0); Oscar J Duran (CC BY-SA 4.0); Jadi from Iran (CC BY 2.0), Wikimedia Commons. Fingerprints are real SHA-256 hashes of the files on this page.

Plan vs site

What the drawings say, what our agent measured.

ItemDrawingMeasuredMatch
Roof span12.00 m11.96 m✓
Ground floor height3.20 m3.18 m✓
Column grid4.00 m4.00 m✓
Built footprint212 m²209 m²✓
Pool shellMilestone 4Excavatedahead
Setback to road≥ 5.0 m5.4 m✓

What the copilot flagged before the visit

Our AI copilot read the brochure, the contract and the permit, and told the agent what to check. Every flag is closed with evidence or carried into "What to do".

Plot size

Brochure: "500 m² plot". Certificate: 480 m².

✓ Closed: the developer's new price list uses 480 m²; price unchanged. Noted in contract annex.
Permitted use

Brochure sells "rental villa". Permit use must be tourism accommodation, not private house.

✓ Closed: PBG lists "hunian wisata" (tourism accommodation).
Payee

Contract payee vs permit holder: same company?

✓ Closed: both PT Kenanga Bangun.
Delivery penalty

Contract has no penalty for late delivery.

→ Carried to What to do (1).
Advertised yield 14%

Comparable villas nearby: 7 to 9% net.

→ Carried to What to do (3).

What to do now

Before you pay instalment 3 on 4 November.

  1. Ask for a late-delivery penalty in writing.We sent you suggested wording: 0.1% of the price per week of delay, capped at 10%.
  2. Get the revised schedule signed.Milestone 3 was due 31 May; it was completed 5 months late. The new dates for milestones 4 to 6 should be in an annex.
  3. Pay only to PT Kenanga Bangun's account.Never a personal account, never a "new" account by message.
  4. Plan with 7 to 9% rental yield, not 14%.That's what comparable villas earn after costs.

Sign-off

Local agentMade S.Verified agent, Canggu · 31 checks · 0 material corrections in the last 10
Senior reviewApproved, 28 Oct 20262 corrections: wording of check 6, one photo caption
Evidence package14 photos · 2 videos · 9 documentsReport fingerprint 507ed4c003626e11…

Evidence, not a guarantee: this advice reflects what was verified on the date shown. A check lowers your risk; it can't remove it. Kolaboro gives independent verification and information, not legal or financial advice. Developers never pay Kolaboro.