Villa 7, Sample Residences, Canggu
Findings on site
| Item | Status | Notes |
|---|---|---|
| Foundations | Complete | Matches plan dimensions |
| Structure and walls | Complete | Columns and beams as drawn |
| Roof structure | Complete | Timber frame installed, covering pending |
| Electrical first fix | Not started | Scheduled for milestone 4 |
| Pool shell | Not started | Excavation only |
GPS-stamped photos
Against the contract
- Contract says milestone 3 is due by 31 May 2026. Verified complete on 21 Oct 2026: about 5 months late.
- The contract has no penalty for late delivery. Ask the developer for a written revised schedule before paying.
- Payment 3 (€48,000) is due to the contracting company's account. The account holder matches the contract.
Safe to pay milestone 3, with one condition
The work for this milestone exists and matches the plans. Pay once the developer sends the revised schedule in writing. We will check milestone 4 on site before your next payment.
Kolaboro gives independent verification and information, not legal or financial advice.