Kolaboro / By handover year / All places / Overdue handovers in Bali: November 2026 report
Overdue handovers in Bali: November 2026 report
Every project we track in Bali whose handover date on record has passed and that is not recorded as completed. Facts only, each with its source, no verdicts.
Projects past the handover date
| Project | Developer | Handover date on record | Months past | Stage, latest record | Last checked |
|---|---|---|---|---|---|
| Amari Villas III | Investland Bali | Q2 2026 investlandbali.com | 5 | Under construction | 10 Nov 2026 |
| Bingin Elements | Urban Escape | Q3 2026 urbanescape.id | 2 | Under construction | 11 Nov 2026 |
| Hidden City Ubud (Phase II apartments) | Hidden City Ubud | Q3 2026 hiddencityubud.com | 2 | Under construction | 10 Nov 2026 |
| Serenity Villas | Global Bali Home | September 2026 globalbalihome.com | 2 | Under construction | 9 Nov 2026 |
| Uluwatu Art Villas | Art Villas Bali | September 2026 uluwatuartvillas.com | 2 | Under construction | 5 Nov 2026 |
Data as of 11 Nov 2026 from our open files. named.json · promises.json · bali-cases.json
How this report is made
Rule: the handover date on record (the latest one we hold) ended before November 2026; a quarter or year counts from its last month. Projects recorded as completed, or whose handover promise is recorded as kept, are left out. A passed date is a fact about the published schedule, not a finding about the developer: ask them for the current schedule in writing.
How to cite this report
Kolaboro, "Overdue handovers in Bali: November 2026 report", https://kolaboro.com/handover/overdue/bali/, data as of 13 Nov 2026. Licence CC BY 4.0.
All placesHandover years in Bali:202620272028All projects in Bali
Questions
How many off-plan projects in Bali are past their handover date?
As of 13 Nov 2026: 5 of the 83 projects we track there with a handover date on record.
Which project in Bali is furthest past its handover date?
Amari Villas III: the handover date on record is Q2 2026, 5 months ago.
Does a passed handover date mean the project has failed?
No. It means the published date has passed and the sources we read do not record the project as completed. Ask the developer for the current schedule in writing.
Are you the developer? Send us documents for anything we missed and we add them after review.