Home / Dubai / Construction pace against the registered date
Construction pace against the registered date
For Dubai projects with DLD inspection readings: % built against the share of time elapsed to the completion date on the register, and the completion range the observed pace points to. A projection, not a promise.
Updated 23 Nov 2026
A projection from the pace on the register, not a promise, and not a finding about the developer.
Show as a table
| Gap (points) | Projects |
|---|---|
| -60 … -50 | 98 |
| -50 … -40 | 119 |
| -40 … -30 | 168 |
| -30 … -20 | 186 |
| -20 … -10 | 140 |
| -10 … 0 | 94 |
| 0 … 10 | 29 |
| 10 … 20 | 13 |
| 20 … 30 | 9 |
| 30 … 40 | 3 |
| 40 … 50 | 1 |
Projects
| Project | % built (inspection) | Time elapsed | Gap (points) | Pace | Registered completion | Projected range | Register |
|---|---|---|---|---|---|---|---|
| Aristo Oksa · Madinat Al Mataar | 0.1% 14 Jul 2026 | 19% | -18.5 | behind | 14 Dec 2028 | under 10% built: too early to project | dubairealestateiq.com |
| The Oasis - Lavita Emaar Properties · Me'Aisem Second | 20.1% 2 Jun 2026 | 39% | -18.3 | behind | 31 Jan 2029 | Jan 2033 – Apr 2033 | dubairealestateiq.com |
| Samana Rome Samana Developers · Meydan, MBR City | 38.7% 16 Sept 2026 | 57% | -18.2 | behind | 31 Dec 2027 | May 2029 – Aug 2029 | dubairealestateiq.com |
| The St. Regis Residences, Downtown Dubai Emaar Properties · Downtown Dubai | 76.1% 2 Jun 2026 | 94% | -18.2 | behind | 25 Dec 2026 | May 2029 – Jun 2029 | dubairealestateiq.com |
| The Valley - Kaia Emaar Properties · Al Yufrah 1 | 19.1% 9 Jun 2026 | 37% | -18.2 | behind | 31 Jul 2028 | Oct 2031 – Dec 2032 | dubairealestateiq.com |
| The Edit at D3 Dubai Holding Real Estate · Zaabeel Second | 0.2% 19 Aug 2026 | 19% | -18.2 | behind | 31 Jan 2030 | under 10% built: too early to project | dubairealestateiq.com |
| Mirdif Hills - Asayel Avenue Dubai Investments PJSC · Mirdif | 33.1% 8 May 2026 | 51% | -18.2 | behind | 5 May 2027 | Jun 2028 | dubairealestateiq.com |
| Hermina by Casagrand Gallantee Real Estate Casagrand Gallantee · Palm Deira | 4.7% 20 Oct 2026 | 23% | -18.2 | behind | 30 Oct 2029 | under 10% built: too early to project | dubairealestateiq.com |
| Sobha Seahaven Tower B & C Sobha Realty · Dubai Marina | 40.2% 18 Sept 2026 | 58% | -18.1 | behind | 31 Oct 2028 | Sept 2030 – Feb 2031 | dubairealestateiq.com |
| Villa Del Divos Residences Divo Home Real Estate Development L.L.C · Palm Deira | 51.9% 1 Oct 2026 | 70% | -18.1 | behind | 7 Jun 2027 | Mar 2028 | dubairealestateiq.com |
| DAMAC Sun City DAMAC Properties · Al Yelayiss 1 | 36.5% 24 Sept 2026 | 55% | -17.9 | behind | 30 Mar 2028 | Nov 2029 – Apr 2030 | dubairealestateiq.com |
| Verdana Reportage Properties · Dubai Investment Park First | 0.1% 28 Jul 2026 | 18% | -17.9 | behind | 30 Sept 2028 | under 10% built: too early to project | dubairealestateiq.com |
| Astra Residences Dugasta · Madinat Al Mataar | 15.3% 16 Jul 2026 | 33% | -17.9 | behind | 31 Aug 2027 | Aug 2029 | dubairealestateiq.com |
| Sera 2 Emaar Properties · Dubai Maritime City | 1.2% 11 Nov 2026 | 19% | -17.6 | behind | 30 Nov 2029 | under 10% built: too early to project | dubairealestateiq.com |
| White Opals Aizn · Majan | 1.1% 31 Mar 2026 | 19% | -17.5 | behind | 1 Sept 2028 | under 10% built: too early to project | dubairealestateiq.com |
| Palace Residences Hillside B Emaar Properties · Hadaeq Sheikh Mohammed Bin Rashid | 0% 30 Sept 2026 | 18% | -17.5 | behind | 31 Oct 2029 | under 10% built: too early to project | dubairealestateiq.com |
| Ellison Nshama · Al Yelayiss 2 | 40.2% 17 Sept 2026 | 58% | -17.4 | behind | 30 Nov 2027 | Feb 2029 | dubairealestateiq.com |
| Peace Avenue by Peace Homes Peace Homes · Jabal Ali Industrial Second | 3.5% 3 Sept 2026 | 21% | -17.4 | behind | 31 Jan 2029 | under 10% built: too early to project | dubairealestateiq.com |
| Nuve by Zoya Zoya · Dubai Land Residence Complex | 0.8% 20 Jul 2026 | 18% | -17.4 | behind | 30 Jun 2028 | under 10% built: too early to project | dubairealestateiq.com |
| Ayaan Heights I IGO · Bukadra | 20.3% 8 Jul 2026 | 38% | -17.4 | behind | 31 Mar 2028 | Aug 2030 | dubairealestateiq.com |
| Crystal Tower V H S · Burj Khalifa | 0.3% 1 Jul 2026 | 18% | -17.3 | behind | 1 Dec 2028 | under 10% built: too early to project | dubairealestateiq.com |
| Vue Doree Crystal Bay Azure · Palm Deira | 1.3% 10 Jun 2026 | 19% | -17.3 | behind | 14 Nov 2028 | under 10% built: too early to project | dubairealestateiq.com |
| Barari Palace Ary & Maz · Majan | 0% 22 Jun 2026 | 17% | -17.2 | behind | 30 Dec 2028 | under 10% built: too early to project | dubairealestateiq.com |
| DAMAC Riverside - Lush DAMAC Properties · Dubai Investment Park Second | 41.7% 26 Aug 2026 | 59% | -17.1 | behind | 31 Dec 2027 | May 2029 – Aug 2029 | dubairealestateiq.com |
| Binghatti Hillcrest Binghatti Developers · Arjan | 60% 17 Sept 2026 | 77% | -17 | behind | 31 Dec 2026 | Mar 2027 – May 2027 | dubairealestateiq.com |
| Barari Parks by Bahat Bahat · Majan | 0.9% 22 Jun 2026 | 18% | -16.9 | behind | 31 Mar 2028 | under 10% built: too early to project | dubairealestateiq.com |
| Zephyra Residences Arsenal East · Palm Deira | 30.5% 12 May 2026 | 47% | -16.8 | behind | 31 Dec 2027 | Sept 2029 | dubairealestateiq.com |
| Noore Eight Square · Majan | 15.9% 8 Jul 2026 | 33% | -16.8 | behind | 30 Jun 2027 | Jan 2029 | dubairealestateiq.com |
| Reem by Vision Vision Developments · Wadi Al Safa 2 | 70.4% 13 Oct 2026 | 87% | -16.7 | behind | 31 Dec 2026 | May 2027 | dubairealestateiq.com |
| The Oasis - Palace Villas - Ostra Emaar Properties · Me'Aisem Second | 6.5% 20 Jul 2026 | 23% | -16.5 | behind | 30 Sept 2029 | under 10% built: too early to project | dubairealestateiq.com |
| Cheval Residences Avenew · Palm Deira | 0% 15 Oct 2026 | 17% | -16.5 | behind | 31 Mar 2029 | under 10% built: too early to project | dubairealestateiq.com |
| Passo by Beyond Beyond Developments · Palm Jumeirah | 4.2% 28 Oct 2026 | 21% | -16.4 | behind | 31 Dec 2029 | under 10% built: too early to project | dubairealestateiq.com |
| Kaia Dyar Amwaj Real Estate Development L.L.C · Palm Deira | 0.2% 2 Sept 2026 | 17% | -16.4 | behind | 31 Dec 2028 | under 10% built: too early to project | dubairealestateiq.com |
| Hayat 4 (Hayat by Dubai South, Phase 4) Dubai South Properties · Dubai South (Golf District) | 4.5% 24 Sept 2026 | 21% | -16.3 | behind | 31 Jul 2028 | under 10% built: too early to project | dubairealestateiq.com |
| The Element at Sobha One Sobha Realty · Ras Al Khor Industrial First | 11.1% 11 Aug 2026 | 27% | -16.3 | behind | 31 Dec 2029 | Oct 2036 – Oct 2037 | dubairealestateiq.com |
| Azizi Noura Azizi Developments · Jabal Ali Industrial Second | 2.1% 16 Nov 2026 | 19% | -16.3 | behind | 4 Jul 2028 | under 10% built: too early to project | dubairealestateiq.com |
| Skyvue Sobha Realty · Bukadra | 16.1% 11 Nov 2026 | 32% | -16.1 | behind | 31 Mar 2030 | Mar 2035 – Sept 2035 | dubairealestateiq.com |
| Nirvana Residences I Meraki Developers · Dubai Production City (Me'aisem) | 0% 12 Aug 2026 | 16% | -15.8 | behind | 31 Dec 2028 | under 10% built: too early to project | dubairealestateiq.com |
| Sunset Bay 4 by Imtiaz Imtiaz Developments · Dubai Islands | 53% 29 Sept 2026 | 69% | -15.8 | behind | 15 May 2027 | Dec 2027 – Dec 2027 | dubairealestateiq.com |
| Shahrukhz Residences by Danube Danube Properties Development L.L.C · Dubai Maritime City | 1.9% 13 Aug 2026 | 18% | -15.7 | behind | 30 Jun 2029 | under 10% built: too early to project | dubairealestateiq.com |
| Azizi Riviera 49 Azizi Developments · Al Merkadh | 54.4% 7 Aug 2026 | 70% | -15.7 | behind | 13 Mar 2027 | May 2027 – Oct 2027 | dubairealestateiq.com |
| Mayfair Nexus by Seven Mayfair Seven Mayfair · Wadi Al Safa 7 | 0.6% 25 Mar 2026 | 16% | -15.6 | behind | 31 Dec 2028 | under 10% built: too early to project | dubairealestateiq.com |
| Miorah by Zoya Zoya · Madinat Al Mataar | 16.1% 20 Jul 2026 | 32% | -15.5 | behind | 31 Aug 2027 | Mar 2029 | dubairealestateiq.com |
| Liv Maritime L I V Maritime · Dubai Maritime City | 28.1% 7 Oct 2026 | 44% | -15.5 | behind | 30 Dec 2028 | Mar 2031 | dubairealestateiq.com |
| Harbour Lights de GRISOGONO DAMAC Properties · Dubai | 64.3% 9 Jul 2026 | 80% | -15.4 | behind | 21 May 2027 | May 2028 – Jul 2028 | dubairealestateiq.com |
| Evelyn On the Park Nshama · Al Yelayiss 2 | 0% 26 Jun 2026 | 15% | -15.3 | behind | 28 Feb 2029 | under 10% built: too early to project | dubairealestateiq.com |
| The Symphony by Imtiaz Imtiaz Developments · Mohammed Bin Rashid City | 6.3% 16 Sept 2026 | 22% | -15.2 | behind | 15 Jun 2029 | under 10% built: too early to project | dubairealestateiq.com |
| DAMAC District DAMAC Properties · DAMAC Hills | 4.1% 22 Sept 2026 | 19% | -15.2 | behind | 30 Mar 2029 | under 10% built: too early to project | dubairealestateiq.com |
| Palm Jebel Ali - Frond K Nakheel · Palm Jabal Ali | 58.3% 10 Nov 2026 | 74% | -15.2 | behind | 1 Dec 2027 | Dec 2028 – Apr 2029 | dubairealestateiq.com |
| Forum 2 K X G · Majan | 7% 10 Aug 2026 | 22% | -15.1 | behind | 15 Dec 2027 | under 10% built: too early to project | dubairealestateiq.com |
| Gate Eleven Residences Amwaj · Majan | 30.6% 9 Sept 2026 | 46% | -14.9 | behind | 31 Mar 2028 | Aug 2029 | dubairealestateiq.com |
| DWTN Residences (registered as Downtown Residences) Deyaar Development PJSC · Business Bay (Sheikh Zayed Road edge of Downtown) | 1.3% 24 Sept 2026 | 16% | -14.8 | behind | 30 Dec 2030 | under 10% built: too early to project | dubairealestateiq.com |
| Sunset Bay 3 by Imtiaz Imtiaz Developments · Dubai Islands | 60% 17 Sept 2026 | 75% | -14.8 | behind | 20 Mar 2027 | Aug 2027 – Sept 2027 | dubairealestateiq.com |
| Lunaya FIVE · Saih Shuaib 1 | 4.1% 9 Nov 2026 | 19% | -14.8 | behind | 31 Mar 2029 | under 10% built: too early to project | dubairealestateiq.com |
| Golf Terrace Residences by Asak Asak Real Estate Development L.L.C · Dubai Production City | 5.1% 7 May 2026 | 20% | -14.8 | behind | 2 Oct 2027 | under 10% built: too early to project | dubairealestateiq.com |
| City Walk Crestlane 4 Meraas · Al Wasl | 0% 6 Oct 2026 | 15% | -14.7 | behind | 25 Apr 2030 | under 10% built: too early to project | dubairealestateiq.com |
| City Walk Crestlane 5 Meraas · Al Wasl | 0% 6 Oct 2026 | 15% | -14.7 | behind | 25 Apr 2030 | under 10% built: too early to project | dubairealestateiq.com |
| Sunlight Homes Sunn And Sand · International City Ph 2 & 3 | 22.1% 1 Jun 2026 | 37% | -14.7 | behind | 30 Sept 2027 | Feb 2029 | dubairealestateiq.com |
| Greenway 2 Emaar Properties · Madinat Al Mataar | 34.4% 29 Jul 2026 | 49% | -14.6 | behind | 31 May 2028 | Dec 2029 – Aug 2030 | dubairealestateiq.com |
| Altan Emaar Properties · Dubai Creek Harbour (Green Gate) | 11.1% 2 Jul 2026 | 26% | -14.5 | behind | 31 Jul 2029 | Jan 2035 – Feb 2041 | dubairealestateiq.com |
Method
Time elapsed = (inspection date minus construction start on the register) divided by (registered completion date minus construction start). When no start date is printed, the registration date is used.
Gap = % built at the inspection minus % of time elapsed at the same date, in percentage points. Behind = a gap below -10 points. Registered date passed = the inspection is after the completion date on the register and the project is not at 100%.
Projection, only for 10% to 99% built: the remaining % divided by the observed pace, where the pace is % built per day since the start date, since the registration date and between the last two inspections we hold (when it rose). The range runs from the earliest to the latest of these estimates.
Limits: Construction does not move in a straight line (a slow start, faster structure, slow finishing), so a straight line from an early reading tends to give later dates than the work will need, and a late reading can give earlier ones. The % built is the DLD inspection figure, not ours.
Source: the Dubai Land Department project register as mirrored per project with its inspection history, read by our register job; 985 DLD records, 28 with two or more dated inspections.
Files: /data/n35a/pace.json · /open/n35a-build.py · /registers/changes/