Home / Dubai / Construction pace against the registered date

Construction pace against the registered date

For Dubai projects with DLD inspection readings: % built against the share of time elapsed to the completion date on the register, and the completion range the observed pace points to. A projection, not a promise.

Updated 23 Nov 2026

A projection from the pace on the register, not a promise, and not a finding about the developer.

860projects compared (DLD % built and dates on the register)
82.7%more than 10 points behind the time elapsed (95% interval 80 to 85.1%)
-27median gap in points, % built minus % of time elapsed (95% interval -29.1 to -26)
452projects with a projected range (10% to 99% built)
86.7%of them projected after the registered date (95% interval 83.3 to 89.5%)
≤-6098-50119-40168-30186-20140-10940291013209303401
Projects by gap between % built and % of time elapsed, in 10-point bins
Show as a table
Gap (points)Projects
-60 … -5098
-50 … -40119
-40 … -30168
-30 … -20186
-20 … -10140
-10 … 094
0 … 1029
10 … 2013
20 … 309
30 … 403
40 … 501

Projects

985 projects, page 11
Project% built (inspection)Time elapsedGap (points)PaceRegistered completionProjected rangeRegister
Aristo
Oksa · Madinat Al Mataar
0.1%
14 Jul 2026
19%-18.5behind14 Dec 2028under 10% built: too early to projectdubairealestateiq.com
The Oasis - Lavita
Emaar Properties · Me'Aisem Second
20.1%
2 Jun 2026
39%-18.3behind31 Jan 2029Jan 2033 – Apr 2033dubairealestateiq.com
Samana Rome
Samana Developers · Meydan, MBR City
38.7%
16 Sept 2026
57%-18.2behind31 Dec 2027May 2029 – Aug 2029dubairealestateiq.com
The St. Regis Residences, Downtown Dubai
Emaar Properties · Downtown Dubai
76.1%
2 Jun 2026
94%-18.2behind25 Dec 2026May 2029 – Jun 2029dubairealestateiq.com
The Valley - Kaia
Emaar Properties · Al Yufrah 1
19.1%
9 Jun 2026
37%-18.2behind31 Jul 2028Oct 2031 – Dec 2032dubairealestateiq.com
The Edit at D3
Dubai Holding Real Estate · Zaabeel Second
0.2%
19 Aug 2026
19%-18.2behind31 Jan 2030under 10% built: too early to projectdubairealestateiq.com
Mirdif Hills - Asayel Avenue
Dubai Investments PJSC · Mirdif
33.1%
8 May 2026
51%-18.2behind5 May 2027Jun 2028dubairealestateiq.com
Hermina by Casagrand Gallantee Real Estate
Casagrand Gallantee · Palm Deira
4.7%
20 Oct 2026
23%-18.2behind30 Oct 2029under 10% built: too early to projectdubairealestateiq.com
Sobha Seahaven Tower B & C
Sobha Realty · Dubai Marina
40.2%
18 Sept 2026
58%-18.1behind31 Oct 2028Sept 2030 – Feb 2031dubairealestateiq.com
Villa Del Divos Residences
Divo Home Real Estate Development L.L.C · Palm Deira
51.9%
1 Oct 2026
70%-18.1behind7 Jun 2027Mar 2028dubairealestateiq.com
DAMAC Sun City
DAMAC Properties · Al Yelayiss 1
36.5%
24 Sept 2026
55%-17.9behind30 Mar 2028Nov 2029 – Apr 2030dubairealestateiq.com
Verdana
Reportage Properties · Dubai Investment Park First
0.1%
28 Jul 2026
18%-17.9behind30 Sept 2028under 10% built: too early to projectdubairealestateiq.com
Astra Residences
Dugasta · Madinat Al Mataar
15.3%
16 Jul 2026
33%-17.9behind31 Aug 2027Aug 2029dubairealestateiq.com
Sera 2
Emaar Properties · Dubai Maritime City
1.2%
11 Nov 2026
19%-17.6behind30 Nov 2029under 10% built: too early to projectdubairealestateiq.com
White Opals
Aizn · Majan
1.1%
31 Mar 2026
19%-17.5behind1 Sept 2028under 10% built: too early to projectdubairealestateiq.com
Palace Residences Hillside B
Emaar Properties · Hadaeq Sheikh Mohammed Bin Rashid
0%
30 Sept 2026
18%-17.5behind31 Oct 2029under 10% built: too early to projectdubairealestateiq.com
Ellison
Nshama · Al Yelayiss 2
40.2%
17 Sept 2026
58%-17.4behind30 Nov 2027Feb 2029dubairealestateiq.com
Peace Avenue by Peace Homes
Peace Homes · Jabal Ali Industrial Second
3.5%
3 Sept 2026
21%-17.4behind31 Jan 2029under 10% built: too early to projectdubairealestateiq.com
Nuve by Zoya
Zoya · Dubai Land Residence Complex
0.8%
20 Jul 2026
18%-17.4behind30 Jun 2028under 10% built: too early to projectdubairealestateiq.com
Ayaan Heights I
IGO · Bukadra
20.3%
8 Jul 2026
38%-17.4behind31 Mar 2028Aug 2030dubairealestateiq.com
Crystal Tower
V H S · Burj Khalifa
0.3%
1 Jul 2026
18%-17.3behind1 Dec 2028under 10% built: too early to projectdubairealestateiq.com
Vue Doree
Crystal Bay Azure · Palm Deira
1.3%
10 Jun 2026
19%-17.3behind14 Nov 2028under 10% built: too early to projectdubairealestateiq.com
Barari Palace
Ary & Maz · Majan
0%
22 Jun 2026
17%-17.2behind30 Dec 2028under 10% built: too early to projectdubairealestateiq.com
DAMAC Riverside - Lush
DAMAC Properties · Dubai Investment Park Second
41.7%
26 Aug 2026
59%-17.1behind31 Dec 2027May 2029 – Aug 2029dubairealestateiq.com
Binghatti Hillcrest
Binghatti Developers · Arjan
60%
17 Sept 2026
77%-17behind31 Dec 2026Mar 2027 – May 2027dubairealestateiq.com
Barari Parks by Bahat
Bahat · Majan
0.9%
22 Jun 2026
18%-16.9behind31 Mar 2028under 10% built: too early to projectdubairealestateiq.com
Zephyra Residences
Arsenal East · Palm Deira
30.5%
12 May 2026
47%-16.8behind31 Dec 2027Sept 2029dubairealestateiq.com
Noore
Eight Square · Majan
15.9%
8 Jul 2026
33%-16.8behind30 Jun 2027Jan 2029dubairealestateiq.com
Reem by Vision
Vision Developments · Wadi Al Safa 2
70.4%
13 Oct 2026
87%-16.7behind31 Dec 2026May 2027dubairealestateiq.com
The Oasis - Palace Villas - Ostra
Emaar Properties · Me'Aisem Second
6.5%
20 Jul 2026
23%-16.5behind30 Sept 2029under 10% built: too early to projectdubairealestateiq.com
Cheval Residences
Avenew · Palm Deira
0%
15 Oct 2026
17%-16.5behind31 Mar 2029under 10% built: too early to projectdubairealestateiq.com
Passo by Beyond
Beyond Developments · Palm Jumeirah
4.2%
28 Oct 2026
21%-16.4behind31 Dec 2029under 10% built: too early to projectdubairealestateiq.com
Kaia
Dyar Amwaj Real Estate Development L.L.C · Palm Deira
0.2%
2 Sept 2026
17%-16.4behind31 Dec 2028under 10% built: too early to projectdubairealestateiq.com
Hayat 4 (Hayat by Dubai South, Phase 4)
Dubai South Properties · Dubai South (Golf District)
4.5%
24 Sept 2026
21%-16.3behind31 Jul 2028under 10% built: too early to projectdubairealestateiq.com
The Element at Sobha One
Sobha Realty · Ras Al Khor Industrial First
11.1%
11 Aug 2026
27%-16.3behind31 Dec 2029Oct 2036 – Oct 2037dubairealestateiq.com
Azizi Noura
Azizi Developments · Jabal Ali Industrial Second
2.1%
16 Nov 2026
19%-16.3behind4 Jul 2028under 10% built: too early to projectdubairealestateiq.com
Skyvue
Sobha Realty · Bukadra
16.1%
11 Nov 2026
32%-16.1behind31 Mar 2030Mar 2035 – Sept 2035dubairealestateiq.com
Nirvana Residences I
Meraki Developers · Dubai Production City (Me'aisem)
0%
12 Aug 2026
16%-15.8behind31 Dec 2028under 10% built: too early to projectdubairealestateiq.com
Sunset Bay 4 by Imtiaz
Imtiaz Developments · Dubai Islands
53%
29 Sept 2026
69%-15.8behind15 May 2027Dec 2027 – Dec 2027dubairealestateiq.com
Shahrukhz Residences by Danube
Danube Properties Development L.L.C · Dubai Maritime City
1.9%
13 Aug 2026
18%-15.7behind30 Jun 2029under 10% built: too early to projectdubairealestateiq.com
Azizi Riviera 49
Azizi Developments · Al Merkadh
54.4%
7 Aug 2026
70%-15.7behind13 Mar 2027May 2027 – Oct 2027dubairealestateiq.com
Mayfair Nexus by Seven Mayfair
Seven Mayfair · Wadi Al Safa 7
0.6%
25 Mar 2026
16%-15.6behind31 Dec 2028under 10% built: too early to projectdubairealestateiq.com
Miorah by Zoya
Zoya · Madinat Al Mataar
16.1%
20 Jul 2026
32%-15.5behind31 Aug 2027Mar 2029dubairealestateiq.com
Liv Maritime
L I V Maritime · Dubai Maritime City
28.1%
7 Oct 2026
44%-15.5behind30 Dec 2028Mar 2031dubairealestateiq.com
Harbour Lights de GRISOGONO
DAMAC Properties · Dubai
64.3%
9 Jul 2026
80%-15.4behind21 May 2027May 2028 – Jul 2028dubairealestateiq.com
Evelyn On the Park
Nshama · Al Yelayiss 2
0%
26 Jun 2026
15%-15.3behind28 Feb 2029under 10% built: too early to projectdubairealestateiq.com
The Symphony by Imtiaz
Imtiaz Developments · Mohammed Bin Rashid City
6.3%
16 Sept 2026
22%-15.2behind15 Jun 2029under 10% built: too early to projectdubairealestateiq.com
DAMAC District
DAMAC Properties · DAMAC Hills
4.1%
22 Sept 2026
19%-15.2behind30 Mar 2029under 10% built: too early to projectdubairealestateiq.com
Palm Jebel Ali - Frond K
Nakheel · Palm Jabal Ali
58.3%
10 Nov 2026
74%-15.2behind1 Dec 2027Dec 2028 – Apr 2029dubairealestateiq.com
Forum 2
K X G · Majan
7%
10 Aug 2026
22%-15.1behind15 Dec 2027under 10% built: too early to projectdubairealestateiq.com
Gate Eleven Residences
Amwaj · Majan
30.6%
9 Sept 2026
46%-14.9behind31 Mar 2028Aug 2029dubairealestateiq.com
DWTN Residences (registered as Downtown Residences)
Deyaar Development PJSC · Business Bay (Sheikh Zayed Road edge of Downtown)
1.3%
24 Sept 2026
16%-14.8behind30 Dec 2030under 10% built: too early to projectdubairealestateiq.com
Sunset Bay 3 by Imtiaz
Imtiaz Developments · Dubai Islands
60%
17 Sept 2026
75%-14.8behind20 Mar 2027Aug 2027 – Sept 2027dubairealestateiq.com
Lunaya
FIVE · Saih Shuaib 1
4.1%
9 Nov 2026
19%-14.8behind31 Mar 2029under 10% built: too early to projectdubairealestateiq.com
Golf Terrace Residences by Asak
Asak Real Estate Development L.L.C · Dubai Production City
5.1%
7 May 2026
20%-14.8behind2 Oct 2027under 10% built: too early to projectdubairealestateiq.com
City Walk Crestlane 4
Meraas · Al Wasl
0%
6 Oct 2026
15%-14.7behind25 Apr 2030under 10% built: too early to projectdubairealestateiq.com
City Walk Crestlane 5
Meraas · Al Wasl
0%
6 Oct 2026
15%-14.7behind25 Apr 2030under 10% built: too early to projectdubairealestateiq.com
Sunlight Homes
Sunn And Sand · International City Ph 2 & 3
22.1%
1 Jun 2026
37%-14.7behind30 Sept 2027Feb 2029dubairealestateiq.com
Greenway 2
Emaar Properties · Madinat Al Mataar
34.4%
29 Jul 2026
49%-14.6behind31 May 2028Dec 2029 – Aug 2030dubairealestateiq.com
Altan
Emaar Properties · Dubai Creek Harbour (Green Gate)
11.1%
2 Jul 2026
26%-14.5behind31 Jul 2029Jan 2035 – Feb 2041dubairealestateiq.com

Next page

Method

Time elapsed = (inspection date minus construction start on the register) divided by (registered completion date minus construction start). When no start date is printed, the registration date is used.

Gap = % built at the inspection minus % of time elapsed at the same date, in percentage points. Behind = a gap below -10 points. Registered date passed = the inspection is after the completion date on the register and the project is not at 100%.

Projection, only for 10% to 99% built: the remaining % divided by the observed pace, where the pace is % built per day since the start date, since the registration date and between the last two inspections we hold (when it rose). The range runs from the earliest to the latest of these estimates.

Limits: Construction does not move in a straight line (a slow start, faster structure, slow finishing), so a straight line from an early reading tends to give later dates than the work will need, and a late reading can give earlier ones. The % built is the DLD inspection figure, not ours.

Source: the Dubai Land Department project register as mirrored per project with its inspection history, read by our register job; 985 DLD records, 28 with two or more dated inspections.