Construction pace against the registered date

For Dubai projects with DLD inspection readings: % built against the share of time elapsed to the completion date on the register, and the completion range the observed pace points to. A projection, not a promise.

Updated 23 Nov 2026

A projection from the pace on the register, not a promise, and not a finding about the developer.

860projects compared (DLD % built and dates on the register)
82.7%more than 10 points behind the time elapsed (95% interval 80 to 85.1%)
-27median gap in points, % built minus % of time elapsed (95% interval -29.1 to -26)
452projects with a projected range (10% to 99% built)
86.7%of them projected after the registered date (95% interval 83.3 to 89.5%)
≤-6098-50119-40168-30186-20140-10940291013209303401
Projects by gap between % built and % of time elapsed, in 10-point bins
Show as a table
Gap (points)Projects
-60 … -5098
-50 … -40119
-40 … -30168
-30 … -20186
-20 … -10140
-10 … 094
0 … 1029
10 … 2013
20 … 309
30 … 403
40 … 501

Projects

985 projects, page 12
Project% built (inspection)Time elapsedGap (points)PaceRegistered completionProjected rangeRegister
Sanctuary by Prestige One
Prestige Sanctuary Real Estate Development L.L.C · Bukadra
0%
16 Oct 2026
15%-14.5behind31 Aug 2029under 10% built: too early to projectdubairealestateiq.com
Windsor House II
Ellington Properties · Madinat Al Mataar
0.6%
20 Aug 2026
15%-14.3behind31 Jul 2029under 10% built: too early to projectdubairealestateiq.com
Lusin Residences by Ermax Development
Ermax · International City Ph 1
35%
18 Jun 2026
49%-14.3behind15 Dec 2026May 2027dubairealestateiq.com
SAMANA Business Hub
SAMANA Developers · Jabal Ali Industrial Second
0.8%
28 Sept 2026
15%-14.2behind30 Sept 2029under 10% built: too early to projectdubairealestateiq.com
Empire Gardens
Empire · Dubai Land Residence Complex
0%
1 Jul 2026
14%-14.2behind31 Dec 2028under 10% built: too early to projectdubairealestateiq.com
Linea by Holm
Holm Avenue · Al Satwa
18%
3 Nov 2026
32%-14.1behind15 Jun 2028Apr 2030dubairealestateiq.com
Sukoon by Nuri
Nuri · Nad Al Shiba First
46.8%
30 Jun 2026
61%-14.1behind31 Dec 2026May 2027dubairealestateiq.com
The Wilds Residences
Dubai Holding Real Estate · Majan
0%
13 Oct 2026
14%-14behind30 Jun 2030under 10% built: too early to projectdubairealestateiq.com
District One West Phase 2
Meydan · Ghadeer Al tair
51%
15 Oct 2026
65%-14behind19 Nov 2027Sept 2028dubairealestateiq.com
Aurea
Emaar Properties · Dubai Maritime City
0.4%
9 Nov 2026
14%-13.9behind30 Jun 2030under 10% built: too early to projectdubairealestateiq.com
Vincitore Wellness Estate
Vincitore Realty · Majan
0%
14 Jul 2026
14%-13.9behind15 Feb 2030under 10% built: too early to projectdubairealestateiq.com
The Cape
Al Barari · Majan
0.7%
2 Jul 2026
15%-13.9behind31 Dec 2028under 10% built: too early to projectdubairealestateiq.com
Longford Residences by Devan Real Estate Development
Devan · International City Ph 1
32.7%
12 Oct 2026
47%-13.9behind1 May 2028Jul 2029dubairealestateiq.com
Mr.C Residences Downtown
Alta Real Estate Development L.L.C · Al Wasl
80.5%
2 Nov 2026
94%-13.9behind27 Jan 2027Oct 2027dubairealestateiq.com
DAMAC Riverside - Olive
DAMAC Properties · Dubai Investment Park Second
5.5%
11 Apr 2026
19%-13.7behind30 Jun 2028under 10% built: too early to projectdubairealestateiq.com
Dar Al Aiham One
Dar Al Aiham Properties L.L.C · International City Ph 2 & 3
20.8%
3 Aug 2026
35%-13.7behind30 Jun 2027May 2028dubairealestateiq.com
Greenfield Living
Greenfield · Madinat Al Mataar
33.3%
17 Apr 2026
47%-13.6behind31 Dec 2026Jul 2027dubairealestateiq.com
Bayview Boulevard
Ab · Palm Deira
55.2%
11 Sept 2026
68%-13.2behind30 Apr 2027Oct 2027dubairealestateiq.com
Barari Parkview by Al Mawared
Almawared Properties · Majan
44.7%
13 Aug 2026
58%-13.1behind20 Dec 2027Nov 2028dubairealestateiq.com
Albero
Emaar Properties · Al Khairan First
11%
2 Jul 2026
24%-13behind30 Sept 2029Oct 2034 – Oct 2036dubairealestateiq.com
The Oasis - Palmiera Collective
Emaar Properties · Me'Aisem Second
1.3%
16 Jun 2026
14%-12.9behind28 Feb 2029under 10% built: too early to projectdubairealestateiq.com
Rosehill
Emaar Properties · Dubai Hills Estate
7.8%
2 Jun 2026
21%-12.8behind30 Jun 2029under 10% built: too early to projectdubairealestateiq.com
The Promise Villas
H N B Vision · Jumeirah Village Circle
28.5%
13 Oct 2026
41%-12.7behind31 Dec 2027Dec 2028dubairealestateiq.com
Il Vento
Kora Properties · Dubai Maritime City
1.2%
12 May 2026
14%-12.5behind30 Sept 2029under 10% built: too early to projectdubairealestateiq.com
Grand Polo - Selvara
Emaar Properties · Grand Polo Club, Dubai Investment Park Second
2.8%
14 May 2026
15%-12.3behind30 Apr 2029under 10% built: too early to projectdubairealestateiq.com
Villa Del Gavi Residences
Mr Eight Real Estate Development L.L.C · Palm Deira
37.6%
28 Sept 2026
50%-12.2behind25 Dec 2027Oct 2028dubairealestateiq.com
Wellington Ocean Walk
Wellington · Palm Deira
20.8%
22 Oct 2026
33%-12.1behind16 Dec 2028Oct 2030dubairealestateiq.com
Parkwood
Emaar Properties · Hadaeq Sheikh Mohammed Bin Rashid
15%
7 May 2026
27%-12behind31 Jan 2029Feb 2032 – Aug 2033dubairealestateiq.com
Kanyon by Beyond
Beyond Developments · Dubai Maritime City
4.1%
9 Nov 2026
16%-11.9behind30 Sept 2028under 10% built: too early to projectdubairealestateiq.com
Terra Gardens
Emaar Properties · Madinat Al Mataar
3.6%
4 Nov 2026
16%-11.9behind31 Oct 2029under 10% built: too early to projectdubairealestateiq.com
Cresswell Views
Adev Properties · Madinat Al Mataar
60.2%
22 Jul 2026
72%-11.8behind30 Dec 2026Apr 2027dubairealestateiq.com
Windsor House
Ellington Properties · Dubai South (Residential District)
3.1%
17 Jun 2026
15%-11.7behind31 Jul 2029under 10% built: too early to projectdubairealestateiq.com
Sunset Bay 5 by Imtiaz
Imtiaz Developments · Dubai Islands
44.5%
5 Oct 2026
56%-11.5behind15 Oct 2027Apr 2028 – May 2028dubairealestateiq.com
Vida Residences Hillside
Emaar Properties · Hadaeq Sheikh Mohammed Bin Rashid
10%
4 May 2026
22%-11.5behind31 May 2029Dec 2033 – May 2037dubairealestateiq.com
Aeternitas Tower
London Gate · Dubai Marina
57.9%
25 Sept 2026
69%-11.5behind11 Dec 2027Sept 2028dubairealestateiq.com
Greencrest
Emaar Properties · Hadaeq Sheikh Mohammed Bin Rashid
1.2%
7 May 2026
13%-11.4behind30 Jun 2029under 10% built: too early to projectdubairealestateiq.com
Silva
Emaar Properties · Al Khairan First
10.2%
19 Jul 2026
22%-11.4behind30 Sept 2029May 2034 – Apr 2037dubairealestateiq.com
Grand Polo - Selvara 4
Emaar Properties · Grand Polo Club, Dubai Investment Park Second
2.9%
6 May 2026
14%-11.3behind31 May 2029under 10% built: too early to projectdubairealestateiq.com
Grand Polo - Selvara 3
Emaar Properties · Grand Polo Club, Dubai Investment Park Second
3%
6 May 2026
14%-11.2behind31 May 2029under 10% built: too early to projectdubairealestateiq.com
Floarea Grande
Mashriq Elite · Arjan
48.2%
14 Aug 2026
59%-11.2behind14 Aug 2027Mar 2028dubairealestateiq.com
Sensia
OMNIYAT · Dubai Maritime City
17.5%
1 Oct 2026
29%-11.1behind30 Mar 2029Jun 2031 – Mar 2034dubairealestateiq.com
Grand Polo - Selvara 2
Emaar Properties · Grand Polo Club, Dubai Investment Park Second
4%
14 May 2026
15%-11.1behind30 Apr 2029under 10% built: too early to projectdubairealestateiq.com
Akala Hotels & Residences
Arada · DIFC / Zabeel
1.9%
13 Oct 2026
13%-11behind31 Oct 2029under 10% built: too early to projectdubairealestateiq.com
The Residences at the Dubai Beach Edition
Shamal · Dubai Marina
0.2%
21 May 2026
11%-10.9behind30 Nov 2029under 10% built: too early to projectdubairealestateiq.com
Eden House the Park
H&H Development · Al Wasl
63.6%
30 Jul 2026
74%-10.8behind25 Feb 2027Jul 2027dubairealestateiq.com
Golf Hills 2
Emaar Properties · Madinat Al Mataar
4.2%
20 Jul 2026
15%-10.6behind30 Sept 2029under 10% built: too early to projectdubairealestateiq.com
Palm Jebel Ali - Frond O
Nakheel · Palm Jabal Ali
67.5%
10 Nov 2026
78%-10.6behind29 Sept 2027May 2028 – Jul 2028dubairealestateiq.com
Haven by Aldar
Dubai Holding Real Estate · Dubai Land Residence Complex
61%
21 Oct 2026
72%-10.4behind28 Nov 2027Jul 2028dubairealestateiq.com
Serenz by Danube
Danube Properties · Jumeirah Village Circle
4%
9 Nov 2026
14%-10.3behind31 Dec 2029under 10% built: too early to projectdubairealestateiq.com
Val by Kasco
Kasco · Al Jadaf
72.6%
19 Aug 2026
83%-10.3behind30 Dec 2026Apr 2027dubairealestateiq.com
The Valley - Alva
Emaar Properties · Al Yufrah 1
0%
27 Aug 2026
10%-10.2behind31 Mar 2030under 10% built: too early to projectdubairealestateiq.com
Palm Beach Towers
Dubai Holding Real Estate · Palm Jumeirah
81.6%
12 Aug 2026
91%-9.8on pace or ahead31 Dec 2026Jul 2027dubairealestateiq.com
Soul by Vision
Vision Developments · Dubai Production City
77%
12 Oct 2026
87%-9.7on pace or ahead31 Dec 2026Mar 2027dubairealestateiq.com
South Lofts by Premier Choice
P C I Real Estate Developers L.L.C · Dubai Industrial City (Saih Shuaib 2)
0%
2 Jul 2026
10%-9.5on pace or ahead30 Jan 2029under 10% built: too early to projectdubairealestateiq.com
Cresswell Homes
Abdulwahed Faqeeh Properties · Madinat Al Mataar
61.4%
5 Nov 2026
71%-9.4on pace or ahead31 Dec 2026Jan 2027dubairealestateiq.com
Bulgari Lighthouse Dubai
Dubai Holding Real Estate · Jumeira Bay
80%
8 Oct 2026
89%-9.3on pace or ahead27 Mar 2027Sept 2027dubairealestateiq.com
German Supreme Tower 2
Uniestate · Jumeirah Village Circle
45%
28 Oct 2026
54%-9.3on pace or ahead22 Jan 2029Jan 2030dubairealestateiq.com
The Meriva Collection (Meriva Gardens / Meriva Signature)
Ellington Properties · Dubai Islands
0.1%
15 Oct 2026
9%-9.2on pace or ahead31 Dec 2031under 10% built: too early to projectdubairealestateiq.com
Palm Jebel Ali - Frond A Villas
Nakheel · Palm Jebel Ali
51.3%
10 Nov 2026
61%-9.2on pace or ahead17 Jan 2028Jan 2027 – Sept 2028dubairealestateiq.com
Address Residences L Dubai Hills Estate
Emaar Properties · Hadaeq Sheikh Mohammed Bin Rashid
26.5%
10 Jun 2026
36%-9.2on pace or ahead28 Feb 2029Aug 2030 – Jun 2031dubairealestateiq.com

Next page

Method

Time elapsed = (inspection date minus construction start on the register) divided by (registered completion date minus construction start). When no start date is printed, the registration date is used.

Gap = % built at the inspection minus % of time elapsed at the same date, in percentage points. Behind = a gap below -10 points. Registered date passed = the inspection is after the completion date on the register and the project is not at 100%.

Projection, only for 10% to 99% built: the remaining % divided by the observed pace, where the pace is % built per day since the start date, since the registration date and between the last two inspections we hold (when it rose). The range runs from the earliest to the latest of these estimates.

Limits: Construction does not move in a straight line (a slow start, faster structure, slow finishing), so a straight line from an early reading tends to give later dates than the work will need, and a late reading can give earlier ones. The % built is the DLD inspection figure, not ours.

Source: the Dubai Land Department project register as mirrored per project with its inspection history, read by our register job; 985 DLD records, 28 with two or more dated inspections.

Files: /data/n35a/pace.json · /open/n35a-build.py · /registers/changes/