Construction pace against the registered date
For Dubai projects with DLD inspection readings: % built against the share of time elapsed to the completion date on the register, and the completion range the observed pace points to. A projection, not a promise.
Updated 23 Nov 2026
A projection from the pace on the register, not a promise, and not a finding about the developer.
Show as a table
| Gap (points) | Projects |
|---|---|
| -60 … -50 | 98 |
| -50 … -40 | 119 |
| -40 … -30 | 168 |
| -30 … -20 | 186 |
| -20 … -10 | 140 |
| -10 … 0 | 94 |
| 0 … 10 | 29 |
| 10 … 20 | 13 |
| 20 … 30 | 9 |
| 30 … 40 | 3 |
| 40 … 50 | 1 |
Projects
| Project | % built (inspection) | Time elapsed | Gap (points) | Pace | Registered completion | Projected range | Register |
|---|---|---|---|---|---|---|---|
| Sanctuary by Prestige One Prestige Sanctuary Real Estate Development L.L.C · Bukadra | 0% 16 Oct 2026 | 15% | -14.5 | behind | 31 Aug 2029 | under 10% built: too early to project | dubairealestateiq.com |
| Windsor House II Ellington Properties · Madinat Al Mataar | 0.6% 20 Aug 2026 | 15% | -14.3 | behind | 31 Jul 2029 | under 10% built: too early to project | dubairealestateiq.com |
| Lusin Residences by Ermax Development Ermax · International City Ph 1 | 35% 18 Jun 2026 | 49% | -14.3 | behind | 15 Dec 2026 | May 2027 | dubairealestateiq.com |
| SAMANA Business Hub SAMANA Developers · Jabal Ali Industrial Second | 0.8% 28 Sept 2026 | 15% | -14.2 | behind | 30 Sept 2029 | under 10% built: too early to project | dubairealestateiq.com |
| Empire Gardens Empire · Dubai Land Residence Complex | 0% 1 Jul 2026 | 14% | -14.2 | behind | 31 Dec 2028 | under 10% built: too early to project | dubairealestateiq.com |
| Linea by Holm Holm Avenue · Al Satwa | 18% 3 Nov 2026 | 32% | -14.1 | behind | 15 Jun 2028 | Apr 2030 | dubairealestateiq.com |
| Sukoon by Nuri Nuri · Nad Al Shiba First | 46.8% 30 Jun 2026 | 61% | -14.1 | behind | 31 Dec 2026 | May 2027 | dubairealestateiq.com |
| The Wilds Residences Dubai Holding Real Estate · Majan | 0% 13 Oct 2026 | 14% | -14 | behind | 30 Jun 2030 | under 10% built: too early to project | dubairealestateiq.com |
| District One West Phase 2 Meydan · Ghadeer Al tair | 51% 15 Oct 2026 | 65% | -14 | behind | 19 Nov 2027 | Sept 2028 | dubairealestateiq.com |
| Aurea Emaar Properties · Dubai Maritime City | 0.4% 9 Nov 2026 | 14% | -13.9 | behind | 30 Jun 2030 | under 10% built: too early to project | dubairealestateiq.com |
| Vincitore Wellness Estate Vincitore Realty · Majan | 0% 14 Jul 2026 | 14% | -13.9 | behind | 15 Feb 2030 | under 10% built: too early to project | dubairealestateiq.com |
| The Cape Al Barari · Majan | 0.7% 2 Jul 2026 | 15% | -13.9 | behind | 31 Dec 2028 | under 10% built: too early to project | dubairealestateiq.com |
| Longford Residences by Devan Real Estate Development Devan · International City Ph 1 | 32.7% 12 Oct 2026 | 47% | -13.9 | behind | 1 May 2028 | Jul 2029 | dubairealestateiq.com |
| Mr.C Residences Downtown Alta Real Estate Development L.L.C · Al Wasl | 80.5% 2 Nov 2026 | 94% | -13.9 | behind | 27 Jan 2027 | Oct 2027 | dubairealestateiq.com |
| DAMAC Riverside - Olive DAMAC Properties · Dubai Investment Park Second | 5.5% 11 Apr 2026 | 19% | -13.7 | behind | 30 Jun 2028 | under 10% built: too early to project | dubairealestateiq.com |
| Dar Al Aiham One Dar Al Aiham Properties L.L.C · International City Ph 2 & 3 | 20.8% 3 Aug 2026 | 35% | -13.7 | behind | 30 Jun 2027 | May 2028 | dubairealestateiq.com |
| Greenfield Living Greenfield · Madinat Al Mataar | 33.3% 17 Apr 2026 | 47% | -13.6 | behind | 31 Dec 2026 | Jul 2027 | dubairealestateiq.com |
| Bayview Boulevard Ab · Palm Deira | 55.2% 11 Sept 2026 | 68% | -13.2 | behind | 30 Apr 2027 | Oct 2027 | dubairealestateiq.com |
| Barari Parkview by Al Mawared Almawared Properties · Majan | 44.7% 13 Aug 2026 | 58% | -13.1 | behind | 20 Dec 2027 | Nov 2028 | dubairealestateiq.com |
| Albero Emaar Properties · Al Khairan First | 11% 2 Jul 2026 | 24% | -13 | behind | 30 Sept 2029 | Oct 2034 – Oct 2036 | dubairealestateiq.com |
| The Oasis - Palmiera Collective Emaar Properties · Me'Aisem Second | 1.3% 16 Jun 2026 | 14% | -12.9 | behind | 28 Feb 2029 | under 10% built: too early to project | dubairealestateiq.com |
| Rosehill Emaar Properties · Dubai Hills Estate | 7.8% 2 Jun 2026 | 21% | -12.8 | behind | 30 Jun 2029 | under 10% built: too early to project | dubairealestateiq.com |
| The Promise Villas H N B Vision · Jumeirah Village Circle | 28.5% 13 Oct 2026 | 41% | -12.7 | behind | 31 Dec 2027 | Dec 2028 | dubairealestateiq.com |
| Il Vento Kora Properties · Dubai Maritime City | 1.2% 12 May 2026 | 14% | -12.5 | behind | 30 Sept 2029 | under 10% built: too early to project | dubairealestateiq.com |
| Grand Polo - Selvara Emaar Properties · Grand Polo Club, Dubai Investment Park Second | 2.8% 14 May 2026 | 15% | -12.3 | behind | 30 Apr 2029 | under 10% built: too early to project | dubairealestateiq.com |
| Villa Del Gavi Residences Mr Eight Real Estate Development L.L.C · Palm Deira | 37.6% 28 Sept 2026 | 50% | -12.2 | behind | 25 Dec 2027 | Oct 2028 | dubairealestateiq.com |
| Wellington Ocean Walk Wellington · Palm Deira | 20.8% 22 Oct 2026 | 33% | -12.1 | behind | 16 Dec 2028 | Oct 2030 | dubairealestateiq.com |
| Parkwood Emaar Properties · Hadaeq Sheikh Mohammed Bin Rashid | 15% 7 May 2026 | 27% | -12 | behind | 31 Jan 2029 | Feb 2032 – Aug 2033 | dubairealestateiq.com |
| Kanyon by Beyond Beyond Developments · Dubai Maritime City | 4.1% 9 Nov 2026 | 16% | -11.9 | behind | 30 Sept 2028 | under 10% built: too early to project | dubairealestateiq.com |
| Terra Gardens Emaar Properties · Madinat Al Mataar | 3.6% 4 Nov 2026 | 16% | -11.9 | behind | 31 Oct 2029 | under 10% built: too early to project | dubairealestateiq.com |
| Cresswell Views Adev Properties · Madinat Al Mataar | 60.2% 22 Jul 2026 | 72% | -11.8 | behind | 30 Dec 2026 | Apr 2027 | dubairealestateiq.com |
| Windsor House Ellington Properties · Dubai South (Residential District) | 3.1% 17 Jun 2026 | 15% | -11.7 | behind | 31 Jul 2029 | under 10% built: too early to project | dubairealestateiq.com |
| Sunset Bay 5 by Imtiaz Imtiaz Developments · Dubai Islands | 44.5% 5 Oct 2026 | 56% | -11.5 | behind | 15 Oct 2027 | Apr 2028 – May 2028 | dubairealestateiq.com |
| Vida Residences Hillside Emaar Properties · Hadaeq Sheikh Mohammed Bin Rashid | 10% 4 May 2026 | 22% | -11.5 | behind | 31 May 2029 | Dec 2033 – May 2037 | dubairealestateiq.com |
| Aeternitas Tower London Gate · Dubai Marina | 57.9% 25 Sept 2026 | 69% | -11.5 | behind | 11 Dec 2027 | Sept 2028 | dubairealestateiq.com |
| Greencrest Emaar Properties · Hadaeq Sheikh Mohammed Bin Rashid | 1.2% 7 May 2026 | 13% | -11.4 | behind | 30 Jun 2029 | under 10% built: too early to project | dubairealestateiq.com |
| Silva Emaar Properties · Al Khairan First | 10.2% 19 Jul 2026 | 22% | -11.4 | behind | 30 Sept 2029 | May 2034 – Apr 2037 | dubairealestateiq.com |
| Grand Polo - Selvara 4 Emaar Properties · Grand Polo Club, Dubai Investment Park Second | 2.9% 6 May 2026 | 14% | -11.3 | behind | 31 May 2029 | under 10% built: too early to project | dubairealestateiq.com |
| Grand Polo - Selvara 3 Emaar Properties · Grand Polo Club, Dubai Investment Park Second | 3% 6 May 2026 | 14% | -11.2 | behind | 31 May 2029 | under 10% built: too early to project | dubairealestateiq.com |
| Floarea Grande Mashriq Elite · Arjan | 48.2% 14 Aug 2026 | 59% | -11.2 | behind | 14 Aug 2027 | Mar 2028 | dubairealestateiq.com |
| Sensia OMNIYAT · Dubai Maritime City | 17.5% 1 Oct 2026 | 29% | -11.1 | behind | 30 Mar 2029 | Jun 2031 – Mar 2034 | dubairealestateiq.com |
| Grand Polo - Selvara 2 Emaar Properties · Grand Polo Club, Dubai Investment Park Second | 4% 14 May 2026 | 15% | -11.1 | behind | 30 Apr 2029 | under 10% built: too early to project | dubairealestateiq.com |
| Akala Hotels & Residences Arada · DIFC / Zabeel | 1.9% 13 Oct 2026 | 13% | -11 | behind | 31 Oct 2029 | under 10% built: too early to project | dubairealestateiq.com |
| The Residences at the Dubai Beach Edition Shamal · Dubai Marina | 0.2% 21 May 2026 | 11% | -10.9 | behind | 30 Nov 2029 | under 10% built: too early to project | dubairealestateiq.com |
| Eden House the Park H&H Development · Al Wasl | 63.6% 30 Jul 2026 | 74% | -10.8 | behind | 25 Feb 2027 | Jul 2027 | dubairealestateiq.com |
| Golf Hills 2 Emaar Properties · Madinat Al Mataar | 4.2% 20 Jul 2026 | 15% | -10.6 | behind | 30 Sept 2029 | under 10% built: too early to project | dubairealestateiq.com |
| Palm Jebel Ali - Frond O Nakheel · Palm Jabal Ali | 67.5% 10 Nov 2026 | 78% | -10.6 | behind | 29 Sept 2027 | May 2028 – Jul 2028 | dubairealestateiq.com |
| Haven by Aldar Dubai Holding Real Estate · Dubai Land Residence Complex | 61% 21 Oct 2026 | 72% | -10.4 | behind | 28 Nov 2027 | Jul 2028 | dubairealestateiq.com |
| Serenz by Danube Danube Properties · Jumeirah Village Circle | 4% 9 Nov 2026 | 14% | -10.3 | behind | 31 Dec 2029 | under 10% built: too early to project | dubairealestateiq.com |
| Val by Kasco Kasco · Al Jadaf | 72.6% 19 Aug 2026 | 83% | -10.3 | behind | 30 Dec 2026 | Apr 2027 | dubairealestateiq.com |
| The Valley - Alva Emaar Properties · Al Yufrah 1 | 0% 27 Aug 2026 | 10% | -10.2 | behind | 31 Mar 2030 | under 10% built: too early to project | dubairealestateiq.com |
| Palm Beach Towers Dubai Holding Real Estate · Palm Jumeirah | 81.6% 12 Aug 2026 | 91% | -9.8 | on pace or ahead | 31 Dec 2026 | Jul 2027 | dubairealestateiq.com |
| Soul by Vision Vision Developments · Dubai Production City | 77% 12 Oct 2026 | 87% | -9.7 | on pace or ahead | 31 Dec 2026 | Mar 2027 | dubairealestateiq.com |
| South Lofts by Premier Choice P C I Real Estate Developers L.L.C · Dubai Industrial City (Saih Shuaib 2) | 0% 2 Jul 2026 | 10% | -9.5 | on pace or ahead | 30 Jan 2029 | under 10% built: too early to project | dubairealestateiq.com |
| Cresswell Homes Abdulwahed Faqeeh Properties · Madinat Al Mataar | 61.4% 5 Nov 2026 | 71% | -9.4 | on pace or ahead | 31 Dec 2026 | Jan 2027 | dubairealestateiq.com |
| Bulgari Lighthouse Dubai Dubai Holding Real Estate · Jumeira Bay | 80% 8 Oct 2026 | 89% | -9.3 | on pace or ahead | 27 Mar 2027 | Sept 2027 | dubairealestateiq.com |
| German Supreme Tower 2 Uniestate · Jumeirah Village Circle | 45% 28 Oct 2026 | 54% | -9.3 | on pace or ahead | 22 Jan 2029 | Jan 2030 | dubairealestateiq.com |
| The Meriva Collection (Meriva Gardens / Meriva Signature) Ellington Properties · Dubai Islands | 0.1% 15 Oct 2026 | 9% | -9.2 | on pace or ahead | 31 Dec 2031 | under 10% built: too early to project | dubairealestateiq.com |
| Palm Jebel Ali - Frond A Villas Nakheel · Palm Jebel Ali | 51.3% 10 Nov 2026 | 61% | -9.2 | on pace or ahead | 17 Jan 2028 | Jan 2027 – Sept 2028 | dubairealestateiq.com |
| Address Residences L Dubai Hills Estate Emaar Properties · Hadaeq Sheikh Mohammed Bin Rashid | 26.5% 10 Jun 2026 | 36% | -9.2 | on pace or ahead | 28 Feb 2029 | Aug 2030 – Jun 2031 | dubairealestateiq.com |
Method
Time elapsed = (inspection date minus construction start on the register) divided by (registered completion date minus construction start). When no start date is printed, the registration date is used.
Gap = % built at the inspection minus % of time elapsed at the same date, in percentage points. Behind = a gap below -10 points. Registered date passed = the inspection is after the completion date on the register and the project is not at 100%.
Projection, only for 10% to 99% built: the remaining % divided by the observed pace, where the pace is % built per day since the start date, since the registration date and between the last two inspections we hold (when it rose). The range runs from the earliest to the latest of these estimates.
Limits: Construction does not move in a straight line (a slow start, faster structure, slow finishing), so a straight line from an early reading tends to give later dates than the work will need, and a late reading can give earlier ones. The % built is the DLD inspection figure, not ours.
Source: the Dubai Land Department project register as mirrored per project with its inspection history, read by our register job; 985 DLD records, 28 with two or more dated inspections.