Nov 1DATAAll 646 projects re-verified: 6,419 developer claims tested against registers, courts and pressNov 1DATAMalaysia TEDUH and Philippines DHSUD licence checks: expired licences and approved delays foundNov 1DATAThailand ONEP register: 2 condos found selling before environmental approvalNov 1DATAMexico PROFECO contract register checks: one sales registration belonged to a laundryNov 1DATAAbu Dhabi ADREC inspections and RAK RERA permit list added: % built straight from the regulatorNov 1SHIPPEDNew stage filter: completed but still sellingNov 1SHIPPEDPublic database page: verification levels, disclosure distribution, every marketNov 1DATA+212 projects in one day, round 3: USA, Caribbean, Gulf, Africa, Japan, AustraliaNov 1SHIPPEDStage on every case: off-plan or under constructionOct 31SHIPPEDVerification level per check on every case card: registry, independent, developer, contradicted
Changelog →

Kolaboro / Rankings / Most delayed / Dubai

Most delayed off-plan projects in Dubai

Projects furthest past the first handover date on record, from advertised dates we track every day.

8 tracked off-plan projects are past the first handover date we have on record in Dubai, UAE; the furthest by 50 months, the median by 11 months. Month of reference: November 2026.

The first handover date on record is the date the developer first advertised, before any later moves we recorded. Where only a year is public we assume December, which can only understate lateness.

#ProjectMarketFirst handover date on recordHandover date advertised nowMonths past the first dateStatus
1Aykon City 3Dubai, UAESeptember 2022December 202750under construction
2Azizi GrandDubai, UAEDecember 2024September 202623under construction
3Expo Valley (villas and townhouses)Dubai, UAEJune 2025March 202617under construction
4Mar CasaDubai, UAEDecember 2025December 202611under construction
5Armani Beach Residences at Palm JumeirahDubai, UAEDecember 2025December 202611under construction
6Azizi Venice 14Dubai, UAEJanuary 2026June 202610under construction
7Viewz 2 by DanubeDubai, UAEFebruary 2026June 20269under construction
8ORLA, Dorchester CollectionDubai, UAEJune 2026December 20265under construction

Method and source: delivery-delay index, /data/on-time.json. A project can be late for reasons outside the developer's control; the dates are as advertised.