Kolaboro / Rankings / Most delayed / Dubai
Most delayed off-plan projects in Dubai
Projects furthest past the first handover date on record, from advertised dates we track every day.
8 tracked off-plan projects are past the first handover date we have on record in Dubai, UAE; the furthest by 50 months, the median by 11 months. Month of reference: November 2026.
The first handover date on record is the date the developer first advertised, before any later moves we recorded. Where only a year is public we assume December, which can only understate lateness.
| # | Project | Market | First handover date on record | Handover date advertised now | Months past the first date | Status |
|---|---|---|---|---|---|---|
| 1 | Aykon City 3 | Dubai, UAE | September 2022 | December 2027 | 50 | under construction |
| 2 | Azizi Grand | Dubai, UAE | December 2024 | September 2026 | 23 | under construction |
| 3 | Expo Valley (villas and townhouses) | Dubai, UAE | June 2025 | March 2026 | 17 | under construction |
| 4 | Mar Casa | Dubai, UAE | December 2025 | December 2026 | 11 | under construction |
| 5 | Armani Beach Residences at Palm Jumeirah | Dubai, UAE | December 2025 | December 2026 | 11 | under construction |
| 6 | Azizi Venice 14 | Dubai, UAE | January 2026 | June 2026 | 10 | under construction |
| 7 | Viewz 2 by Danube | Dubai, UAE | February 2026 | June 2026 | 9 | under construction |
| 8 | ORLA, Dorchester Collection | Dubai, UAE | June 2026 | December 2026 | 5 | under construction |
Method and source: delivery-delay index, /data/on-time.json. A project can be late for reasons outside the developer's control; the dates are as advertised.
By market#