Nov 1DATAAll 646 projects re-verified: 6,419 developer claims tested against registers, courts and pressNov 1DATAMalaysia TEDUH and Philippines DHSUD licence checks: expired licences and approved delays foundNov 1DATAThailand ONEP register: 2 condos found selling before environmental approvalNov 1DATAMexico PROFECO contract register checks: one sales registration belonged to a laundryNov 1DATAAbu Dhabi ADREC inspections and RAK RERA permit list added: % built straight from the regulatorNov 1SHIPPEDNew stage filter: completed but still sellingNov 1SHIPPEDPublic database page: verification levels, disclosure distribution, every marketNov 1DATA+212 projects in one day, round 3: USA, Caribbean, Gulf, Africa, Japan, AustraliaNov 1SHIPPEDStage on every case: off-plan or under constructionOct 31SHIPPEDVerification level per check on every case card: registry, independent, developer, contradicted
Changelog →

Kolaboro / Rankings / Most delayed / Croatia

Most delayed off-plan projects in Croatia

Projects furthest past the first handover date on record, from advertised dates we track every day.

4 tracked off-plan projects are past the first handover date we have on record in Croatia, Croatia; the furthest by 20 months, the median by 15 months. Month of reference: November 2026.

The first handover date on record is the date the developer first advertised, before any later moves we recorded. Where only a year is public we assume December, which can only understate lateness.

#ProjectMarketFirst handover date on recordHandover date advertised nowMonths past the first dateStatus
1Molum Hotel & ResidencesCroatia, CroatiaMarch 2025December 202520completed
2Top Hill Residence I & IICroatia, CroatiaAugust 2025December 202515completed
3Luxury residential complex, Vidal (Novigrad)Croatia, CroatiaAugust 2025December 202515completed
4Mövenpick Hotel & Residences Kvarner BayCroatia, CroatiaSeptember 2026September 20262under construction

Method and source: delivery-delay index, /data/on-time.json. A project can be late for reasons outside the developer's control; the dates are as advertised.