Home / Dubai / Construction pace against the registered date
Construction pace against the registered date
For Dubai projects with DLD inspection readings: % built against the share of time elapsed to the completion date on the register, and the completion range the observed pace points to. A projection, not a promise.
Updated 23 Nov 2026
A projection from the pace on the register, not a promise, and not a finding about the developer.
Show as a table
| Gap (points) | Projects |
|---|---|
| -60 … -50 | 98 |
| -50 … -40 | 119 |
| -40 … -30 | 168 |
| -30 … -20 | 186 |
| -20 … -10 | 140 |
| -10 … 0 | 94 |
| 0 … 10 | 29 |
| 10 … 20 | 13 |
| 20 … 30 | 9 |
| 30 … 40 | 3 |
| 40 … 50 | 1 |
Projects
| Project | % built (inspection) | Time elapsed | Gap (points) | Pace | Registered completion | Projected range | Register |
|---|---|---|---|---|---|---|---|
| Muraba Veil Muraba Properties · Al Wasl | 7.6% 28 Sept 2026 | 51% | -42.9 | behind | 31 Dec 2028 | under 10% built: too early to project | dubairealestateiq.com |
| Aurelia Residence Object 1 · Dubai Sports City | 4.5% 28 Oct 2026 | 47% | -42.7 | behind | 30 Mar 2028 | under 10% built: too early to project | dubairealestateiq.com |
| Aman Residences Dubai Blackwood · Jumeirah Second | 2.9% 6 Nov 2026 | 45% | -42.5 | behind | 31 Dec 2028 | under 10% built: too early to project | dubairealestateiq.com |
| Golf Greens (DAMAC Hills) DAMAC Properties · DAMAC Hills | 40.5% 8 Sept 2026 | 83% | -42.4 | behind | 30 Mar 2027 | Aug 2030 – Nov 2030 | dubairealestateiq.com |
| Bellavion by Sunrise Sunrise Capital · Jabal Ali First | 18.6% 12 Nov 2026 | 61% | -42.4 | behind | 1 Dec 2027 | Jan 2034 | dubairealestateiq.com |
| Treppan Serenique Residences Fakhruddin · Palm Deira | 5.2% 23 Jul 2026 | 48% | -42.3 | behind | 15 Oct 2027 | under 10% built: too early to project | dubairealestateiq.com |
| Arlington Park by Majid Majid Developments · Dubai Land Residence Complex | 5.7% 10 Sept 2026 | 48% | -42.3 | behind | 31 Dec 2027 | under 10% built: too early to project | dubairealestateiq.com |
| The Willows Residences Scc Vertex Property · Majan | 0.7% 14 Apr 2026 | 43% | -42.3 | behind | 30 Jun 2027 | under 10% built: too early to project | dubairealestateiq.com |
| Symbolic Zen Residences Moizziyah Developers L.L.C · Jabal Ali First | 2.1% 17 Apr 2026 | 44% | -42.2 | behind | 15 Jun 2027 | under 10% built: too early to project | dubairealestateiq.com |
| Azizi Venice 11 Azizi Developments · Madinat Al Mataar | 25.9% 9 Sept 2026 | 68% | -42.1 | behind | 30 Aug 2027 | Jun 2032 – Aug 2032 | dubairealestateiq.com |
| Agua Residences by Citi Developers - Tower Citi Developers · Palm Deira | 3.1% 15 Sept 2026 | 45% | -42.1 | behind | 31 Dec 2027 | under 10% built: too early to project | dubairealestateiq.com |
| Octa Isle Interiors by Missoni Octa Di · Palm Deira | 6.2% 1 Sept 2026 | 48% | -42.1 | behind | 30 Sept 2027 | under 10% built: too early to project | dubairealestateiq.com |
| SAMANA Resorts SAMANA Developers · Dubai Production City | 5.9% 22 Oct 2026 | 48% | -42 | behind | 30 May 2028 | under 10% built: too early to project | dubairealestateiq.com |
| Saba 4 Saba · Jumeirah Lakes Towers | 30.4% 31 Jul 2026 | 72% | -41.9 | behind | 1 Jun 2027 | Jul 2031 | dubairealestateiq.com |
| Solara Tower Dubai SOL Properties · Burj Khalifa | 20.7% 30 Jun 2026 | 63% | -41.8 | behind | 15 Aug 2027 | Sept 2033 | dubairealestateiq.com |
| Beverly Park HMB Homes · Dubai Land Residence Complex | 6.8% 29 Sept 2026 | 49% | -41.8 | behind | 31 Oct 2027 | under 10% built: too early to project | dubairealestateiq.com |
| 171 Garden Heights Jad Global · Al Satwa | 33.7% 8 Jun 2026 | 76% | -41.8 | behind | 31 Dec 2026 | Nov 2029 | dubairealestateiq.com |
| Nineteen Riviera Lagoon Riviera · Majan | 34.1% 25 Jun 2026 | 76% | -41.8 | behind | 12 Feb 2027 | May 2030 | dubairealestateiq.com |
| Arka Enclave Residences Manodev · Palm Deira | 3.5% 2 Sept 2026 | 45% | -41.7 | behind | 31 Dec 2027 | under 10% built: too early to project | dubairealestateiq.com |
| Tomorrow 166 Tomorrow World · Palm Deira | 1.7% 1 Apr 2026 | 43% | -41.6 | behind | 31 May 2027 | under 10% built: too early to project | dubairealestateiq.com |
| Taiyo Residences LMD · Jabal Ali First | 12.1% 20 Oct 2026 | 54% | -41.4 | behind | 31 Dec 2027 | Oct 2036 | dubairealestateiq.com |
| Valencia (DAMAC Lagoons District) DAMAC Properties · DAMAC Lagoons | 5.2% 20 May 2026 | 46% | -41.2 | behind | 28 Feb 2028 | under 10% built: too early to project | dubairealestateiq.com |
| Butterfly Al Sayyah · Arjan | 8.2% 4 Nov 2026 | 49% | -41.2 | behind | 31 Jan 2029 | under 10% built: too early to project | dubairealestateiq.com |
| Celestara Residences Aldhana · Jumeirah Village Circle | 6.2% 5 Nov 2026 | 47% | -41.1 | behind | 19 May 2028 | under 10% built: too early to project | dubairealestateiq.com |
| Seaside by Prestige One Prestige The Seaside Real Estate Development L.L.C · Palm Deira | 53% 2 Nov 2026 | 94% | -41.1 | behind | 25 Dec 2026 | Nov 2028 | dubairealestateiq.com |
| Rixos Bay Residences, Dubai Islands Nakheel · Dubai Islands (Palm Deira) | 47.9% 22 Jun 2026 | 89% | -40.8 | behind | 15 Oct 2026 | Mar 2029 – Aug 2029 | dubairealestateiq.com |
| Orise OMNIYAT · Dubai Maritime City | 17.6% 7 Oct 2026 | 58% | -40.7 | behind | 30 Nov 2027 | Apr 2034 – May 2035 | dubairealestateiq.com |
| Saray Prime Residence Unique Saray Properties · Dubai Land Residence Complex | 2.2% 21 Sept 2026 | 43% | -40.7 | behind | 31 Oct 2027 | under 10% built: too early to project | dubairealestateiq.com |
| Ag Aum Residence Agp Assets Real Estate Developments L.L.C · Dubai Land Residence Complex | 8.1% 28 Oct 2026 | 49% | -40.7 | behind | 30 Nov 2028 | under 10% built: too early to project | dubairealestateiq.com |
| Berkeley Square by Prestige One Prestige Luxe Real Estate Development L.L.C · Jumeirah Village Circle | 3% 24 Sept 2026 | 44% | -40.5 | behind | 30 Mar 2028 | under 10% built: too early to project | dubairealestateiq.com |
| Canal Crown de GRISOGONO DAMAC Properties · Business Bay | 42.2% 15 Jul 2026 | 83% | -40.4 | behind | 28 Feb 2027 | Aug 2030 – Nov 2030 | dubairealestateiq.com |
| Rabdan Gates Rabdan · Majan | 5.2% 27 Oct 2026 | 46% | -40.4 | behind | 30 Jun 2028 | under 10% built: too early to project | dubairealestateiq.com |
| The Lx Mulk Properties · Arjan | 4.9% 4 Jun 2026 | 45% | -40.3 | behind | 30 Aug 2027 | under 10% built: too early to project | dubairealestateiq.com |
| One River Point Ellington Properties · Business Bay | 35.4% 21 Jul 2026 | 76% | -40.2 | behind | 9 Jun 2027 | Jan 2031 – Jul 2031 | dubairealestateiq.com |
| Future Residence True Future · Bukadra | 0% 23 Jun 2026 | 40% | -40.2 | behind | 30 Jun 2027 | under 10% built: too early to project | dubairealestateiq.com |
| Rove Home Dubai Marina IRTH Group · Dubai Marina | 7.8% 6 Jul 2026 | 48% | -40.1 | behind | 31 Mar 2028 | under 10% built: too early to project | dubairealestateiq.com |
| Flora Shore by Calgary Properties Calgary Properties · Palm Deira | 2.2% 8 Jul 2026 | 42% | -40.1 | behind | 30 Sept 2027 | under 10% built: too early to project | dubairealestateiq.com |
| Cove Grand by Imtiaz Imtiaz Developments · Dubailand Residence Complex | 13.4% 8 Oct 2026 | 53% | -40 | behind | 15 Dec 2027 | May 2031 – Jul 2035 | dubairealestateiq.com |
| South Garden A Wasl · Jabal Ali First | 16.2% 7 Sept 2026 | 56% | -40 | behind | 31 Dec 2027 | May 2035 – Dec 2036 | dubairealestateiq.com |
| South Garden B Wasl · Jabal Ali First | 16.2% 7 Sept 2026 | 56% | -40 | behind | 31 Dec 2027 | May 2035 – Dec 2036 | dubairealestateiq.com |
| South Garden C Wasl · Jabal Ali First | 16.2% 7 Sept 2026 | 56% | -40 | behind | 31 Dec 2027 | May 2035 – Dec 2036 | dubairealestateiq.com |
| Vestoria Bay Ahmadyar · Palm Deira | 3.6% 2 Oct 2026 | 44% | -39.9 | behind | 25 Nov 2027 | under 10% built: too early to project | dubairealestateiq.com |
| Veda by Aum One Real Estate Development Aum One · Jumeirah Village Circle | 6.4% 9 Nov 2026 | 46% | -39.8 | behind | 30 Apr 2028 | under 10% built: too early to project | dubairealestateiq.com |
| Nautis Residences Stamn · Palm Deira | 0.9% 28 Apr 2026 | 41% | -39.7 | behind | 30 Aug 2027 | under 10% built: too early to project | dubairealestateiq.com |
| Al Waleed W.S 1 Al Waleed · Dubai Land Residence Complex | 18.3% 18 Jun 2026 | 58% | -39.7 | behind | 28 Feb 2027 | Oct 2030 | dubairealestateiq.com |
| The Elysian New M F O U R · Al Satwa | 4.5% 9 Jul 2026 | 44% | -39.6 | behind | 31 Aug 2027 | under 10% built: too early to project | dubairealestateiq.com |
| Meriden Beach by Green Horizon Green Horizon · Palm Deira | 7.8% 2 Nov 2026 | 47% | -39.4 | behind | 10 Dec 2027 | under 10% built: too early to project | dubairealestateiq.com |
| Binghatti Cullinan Binghatti Developers · Al Jaddaf | 18.3% 28 Oct 2026 | 58% | -39.2 | behind | 30 Jun 2027 | Jul 2030 – Nov 2030 | dubairealestateiq.com |
| Verdes by Haven Dubai Holding Real Estate · Dubai Land Residence Complex | 17.7% 21 Oct 2026 | 57% | -39.1 | behind | 31 May 2028 | Aug 2036 | dubairealestateiq.com |
| Al Vista Dubai Investments PJSC · Bukadra | 9.5% 28 Oct 2026 | 49% | -39.1 | behind | 20 Oct 2027 | under 10% built: too early to project | dubairealestateiq.com |
| Cotier House by Imtiaz Imtiaz Developments · Dubai Islands Marina | 51.7% 10 Nov 2026 | 91% | -38.9 | behind | 15 Jan 2027 | Jun 2028 | dubairealestateiq.com |
| The Baltimore Nshama · Al Yelayiss 2 | 26.3% 7 Oct 2026 | 65% | -38.9 | behind | 30 Sept 2027 | Nov 2031 | dubairealestateiq.com |
| Verde by Vision Vision Developments · Dubai Sports City | 12% 12 Oct 2026 | 51% | -38.8 | behind | 30 Sept 2027 | Feb 2034 | dubairealestateiq.com |
| The Chedi Private Residences Alseeb · Barsha Heights | 2.6% 8 Sept 2026 | 41% | -38.7 | behind | 28 Feb 2029 | under 10% built: too early to project | dubairealestateiq.com |
| Azizi Milan Heights Azizi Developments · City of Arabia | 0% 5 Nov 2026 | 39% | -38.6 | behind | 8 Sept 2028 | under 10% built: too early to project | dubairealestateiq.com |
| Essenlife Residence Object 1 · Jumeirah Village Triangle | 7.2% 16 Sept 2026 | 46% | -38.6 | behind | 30 Mar 2028 | under 10% built: too early to project | dubairealestateiq.com |
| Sky Gate Tower Tiger Properties · Jumeirah Village Triangle | 4.7% 7 Oct 2026 | 43% | -38.5 | behind | 29 Feb 2028 | under 10% built: too early to project | dubairealestateiq.com |
| Address Grand Downtown Nshama · Burj Khalifa | 10.8% 7 Oct 2026 | 49% | -38.5 | behind | 10 Jun 2028 | Apr 2040 | dubairealestateiq.com |
| Laya Courtyard Laya · Dubai Studio City | 50.6% 15 Sept 2026 | 89% | -38.5 | behind | 26 Dec 2026 | Dec 2028 | dubairealestateiq.com |
| The Tides by Amis Amis Aurum Real Estate Development L.L.C · Palm Deira | 0.4% 3 Nov 2026 | 39% | -38.4 | behind | 30 Apr 2028 | under 10% built: too early to project | dubairealestateiq.com |
Method
Time elapsed = (inspection date minus construction start on the register) divided by (registered completion date minus construction start). When no start date is printed, the registration date is used.
Gap = % built at the inspection minus % of time elapsed at the same date, in percentage points. Behind = a gap below -10 points. Registered date passed = the inspection is after the completion date on the register and the project is not at 100%.
Projection, only for 10% to 99% built: the remaining % divided by the observed pace, where the pace is % built per day since the start date, since the registration date and between the last two inspections we hold (when it rose). The range runs from the earliest to the latest of these estimates.
Limits: Construction does not move in a straight line (a slow start, faster structure, slow finishing), so a straight line from an early reading tends to give later dates than the work will need, and a late reading can give earlier ones. The % built is the DLD inspection figure, not ours.
Source: the Dubai Land Department project register as mirrored per project with its inspection history, read by our register job; 985 DLD records, 28 with two or more dated inspections.