Construction pace against the registered date

For Dubai projects with DLD inspection readings: % built against the share of time elapsed to the completion date on the register, and the completion range the observed pace points to. A projection, not a promise.

Updated 23 Nov 2026

A projection from the pace on the register, not a promise, and not a finding about the developer.

860projects compared (DLD % built and dates on the register)
82.7%more than 10 points behind the time elapsed (95% interval 80 to 85.1%)
-27median gap in points, % built minus % of time elapsed (95% interval -29.1 to -26)
452projects with a projected range (10% to 99% built)
86.7%of them projected after the registered date (95% interval 83.3 to 89.5%)
≤-6098-50119-40168-30186-20140-10940291013209303401
Projects by gap between % built and % of time elapsed, in 10-point bins
Show as a table
Gap (points)Projects
-60 … -5098
-50 … -40119
-40 … -30168
-30 … -20186
-20 … -10140
-10 … 094
0 … 1029
10 … 2013
20 … 309
30 … 403
40 … 501

Projects

711 projects, page 5
Project% built (inspection)Time elapsedGap (points)PaceRegistered completionProjected rangeRegister
Amaal 8
Amaal · Ras Al Khor Industrial First
11.3%
28 Oct 2026
50%-38.3behind31 Dec 2028Sept 2043dubairealestateiq.com
Violet 4 (DAMAC Hills 2)
DAMAC Properties · DAMAC Hills 2
14.2%
13 May 2026
52%-38.1behind30 Aug 2027Dec 2034 – Jul 2035dubairealestateiq.com
Vista by Vision
Vision Developments · Dubai Production City
12.2%
12 Oct 2026
50%-38.1behind1 Sept 2027Mar 2033dubairealestateiq.com
Binghatti Luxuria
Binghatti Developers · Jumeirah Village Triangle
7%
17 Sept 2026
45%-38behind30 Jul 2027under 10% built: too early to projectdubairealestateiq.com
DAMAC Hills - Ivory
DAMAC Properties · DAMAC Hills
3.5%
4 Nov 2026
42%-38behind30 Jun 2028under 10% built: too early to projectdubairealestateiq.com
La Boutique
LMD · Al Jadaf
52.5%
12 Oct 2026
91%-38behind31 Dec 2026Sept 2028dubairealestateiq.com
Stax
PashaOne · Jumeirah Village Circle
5.7%
27 Oct 2026
44%-37.9behind31 Mar 2028under 10% built: too early to projectdubairealestateiq.com
Avion Residence
Sky View · Madinat Al Mataar
35.8%
1 Oct 2026
74%-37.9behind31 Mar 2027Mar 2029dubairealestateiq.com
Rosewood Residences Dubai
Agarwood Properties · Jumeirah Second
0%
10 Aug 2026
38%-37.9behind31 Dec 2028under 10% built: too early to projectdubairealestateiq.com
Burj Capital
Centurion · Business Bay
2.6%
9 Nov 2026
40%-37.8behind22 Dec 2028under 10% built: too early to projectdubairealestateiq.com
Mak I'Sola Bella
MAK Developers · Jumeirah Village Circle
27.2%
20 Aug 2026
65%-37.8behind5 Sept 2027Oct 2031dubairealestateiq.com
La Cle by Maaia Developers
Maaia Prime · Jabal Ali First
34.6%
29 Jun 2026
72%-37.8behind14 Jan 2027Mar 2029dubairealestateiq.com
Raffi by Azizi
Azizi Developments · Jabal Ali First
2%
25 Mar 2026
40%-37.6behind15 Jan 2028under 10% built: too early to projectdubairealestateiq.com
Arian by Azizi
Azizi Developments · Jabal Ali Industrial Second
2%
24 Mar 2026
40%-37.5behind16 Jan 2028under 10% built: too early to projectdubairealestateiq.com
Peace Lagoons II by Peace Homes
Peace Homes · Dubai Land Residence Complex
5.7%
11 Nov 2026
43%-37.5behind1 Jan 2029under 10% built: too early to projectdubairealestateiq.com
Rena
Avenew · Palm Deira
31.8%
31 Aug 2026
69%-37.3behind15 May 2027Jan 2030dubairealestateiq.com
Silena Residences
Avenew · Palm Deira
5.7%
3 Nov 2026
43%-37.3behind30 May 2028under 10% built: too early to projectdubairealestateiq.com
La Tilia at Villanova Phase 2
Dubai Properties · Dubai Land Residence Complex
10.6%
5 Oct 2026
48%-37behind21 Aug 2028Mar 2041 – Nov 2041dubairealestateiq.com
Tonino Lamborghini Residences
Gulf Land · Nad Al Shiba First
60%
21 Sept 2026
97%-37behind31 Dec 2026Sept 2032dubairealestateiq.com
Volta Tower
DAMAC Properties · Downtown Dubai
29.3%
18 Aug 2026
66%-36.9behind31 Dec 2027Feb 2033 – Sept 2033dubairealestateiq.com
Royal Regency Suites
Alseeb · Business Bay
57.2%
27 Oct 2026
94%-36.8behind31 Dec 2026Nov 2028dubairealestateiq.com
Alton
Nshama · Al Yelayiss 2
5.2%
18 Aug 2026
42%-36.7behind31 May 2028under 10% built: too early to projectdubairealestateiq.com
Golf Grove by Regent
Regent Star · Dubai Production City
8.7%
10 Jun 2026
45%-36.7behind2 Jan 2028under 10% built: too early to projectdubairealestateiq.com
Signature Lifestyle Residences
Signature Developers · Jumeirah Lakes Towers
8.1%
24 Aug 2026
45%-36.7behind31 Dec 2028under 10% built: too early to projectdubairealestateiq.com
One Sky Park by Iman
Iman Developers · Jumeirah Village Circle
21.7%
21 Oct 2026
58%-36.5behind30 Mar 2028Jan 2034dubairealestateiq.com
Peninsula Dubai Residences - Tower 1
Dubai Peninsula · Jumeirah Second
5.6%
10 Sept 2026
42%-36.5behind8 Jan 2029under 10% built: too early to projectdubairealestateiq.com
Golf Dale
Emaar · Emaar South
4.3%
9 Nov 2026
41%-36.3behind31 Dec 2028under 10% built: too early to projectdubairealestateiq.com
Rivo
Grovy Homes · Dubai Land Residence Complex
10.4%
9 Nov 2026
47%-36.2behind31 Dec 2027Jun 2035dubairealestateiq.com
Avida Residences
Serene Marina · Palm Deira
6.8%
25 Aug 2026
43%-36.1behind1 Dec 2027under 10% built: too early to projectdubairealestateiq.com
Peninsula Dubai Residences - Tower 2
Dubai Peninsula · Jumeirah Second
6.3%
12 Nov 2026
42%-36.1behind8 Jan 2029under 10% built: too early to projectdubairealestateiq.com
Samana Ocean Crest
Samana Developers · Dubai Islands
1.4%
22 Sept 2026
37%-36behind30 Jun 2028under 10% built: too early to projectdubairealestateiq.com
Cove Edition 5 by Imtiaz
Imtiaz Developments · Dubailand (Dubai Land Residence Complex)
26.3%
18 Aug 2026
62%-36behind20 May 2027Feb 2030 – Feb 2030dubairealestateiq.com
Project Maybach
Binghatti Developers · Nad Al Shiba First
19.1%
3 Nov 2026
55%-36behind30 Jun 2027Mar 2030 – Apr 2030dubairealestateiq.com
Symbolic Altus
Symbolic · Wadi Al Safa 2
1.3%
8 May 2026
37%-36behind1 May 2027under 10% built: too early to projectdubairealestateiq.com
Azizi Sikander
Azizi Developments · Jabal Ali First
2%
18 Mar 2026
38%-35.5behind17 Jun 2027under 10% built: too early to projectdubairealestateiq.com
Jumeirah Residences - Asora Bay - Ocean Mansions
Dubai Holding Real Estate · La Mer
0.5%
12 Aug 2026
36%-35.5behind31 Mar 2029under 10% built: too early to projectdubairealestateiq.com
City View Dubai Hills Residences
City View · Hadaeq Sheikh Mohammed Bin Rashid
38.8%
4 Aug 2026
74%-35.5behind31 Mar 2027Jul 2029dubairealestateiq.com
Tetris Tower
Le Luminous · Jumeirah Village Circle
12.2%
16 Nov 2026
48%-35.5behind30 Sept 2027Jul 2032dubairealestateiq.com
Ananda Residences
Tiger Properties · Al Hebiah First
3.2%
7 Oct 2026
39%-35.4behind31 May 2028under 10% built: too early to projectdubairealestateiq.com
Samana Sky Views
Samana Developers · Dubai Production City (IMPZ)
4.4%
28 Oct 2026
40%-35.3behind31 Jul 2028under 10% built: too early to projectdubairealestateiq.com
SAMANA Barari Lagoons
SAMANA Developers · Majan, Dubailand
16.5%
20 Oct 2026
52%-35.3behind31 Mar 2028Aug 2034 – Feb 2036dubairealestateiq.com
Waada - Cascada
BT Properties · Madinat Al Mataar
1.6%
24 Aug 2026
37%-35.3behind31 Oct 2028under 10% built: too early to projectdubairealestateiq.com
Azizi Amir
Azizi Developments · Jabal Ali First
2.4%
18 Mar 2026
38%-35.2behind17 Jun 2027under 10% built: too early to projectdubairealestateiq.com
Belmore Residences
Ellington Properties · Bukadra
6.5%
6 Aug 2026
42%-35behind31 Dec 2027under 10% built: too early to projectdubairealestateiq.com
Saria
OMNIYAT · Dubai Maritime City
31%
1 Oct 2026
66%-34.7behind1 Oct 2027Jan 2031 – Apr 2031dubairealestateiq.com
Savannah
Nshama · Al Yelayiss 2
43.5%
17 Sept 2026
78%-34.7behind30 Apr 2027Aug 2029dubairealestateiq.com
House of Well
Well Concept · Palm Deira
6.7%
24 Jun 2026
41%-34.7behind30 May 2027under 10% built: too early to projectdubairealestateiq.com
Ag Ark Tower
Agp Ark Real Estate Development L.L.C · Dubai Land Residence Complex
14.1%
28 Oct 2026
49%-34.7behind30 Nov 2028Dec 2038dubairealestateiq.com
The Hillgate
Ellington Properties · Dubai Silicon Oasis
3.1%
4 Jun 2026
38%-34.6behind30 Jun 2028under 10% built: too early to projectdubairealestateiq.com
DAMAC Islands
DAMAC Properties · Dubailand
6.6%
12 Oct 2026
41%-34.6behind31 Dec 2028under 10% built: too early to projectdubairealestateiq.com
Azizi Neila
Azizi Developments · Jabal Ali First
38.5%
5 Oct 2026
73%-34.4behind30 Jul 2027Feb 2030 – Apr 2030dubairealestateiq.com
Wasl by Azizi
Azizi Developments · Palm Deira
2%
18 Mar 2026
36%-34.4behind12 Feb 2028under 10% built: too early to projectdubairealestateiq.com
The Acres 2 & Estates 2
Dubai Holding Real Estate · Wadi Al Safa 7
14.9%
30 Sept 2026
49%-34.4behind3 May 2028Aug 2035dubairealestateiq.com
Altair 52
Acube Abodes · Madinat Al Mataar
10.1%
24 Sept 2026
45%-34.4behind31 Dec 2027Oct 2035dubairealestateiq.com
Vincitore Aqua Flora
Vincitore Realty · Dubai Science Park (Al Barsha South)
1.3%
30 Mar 2026
36%-34.2behind30 Jun 2028under 10% built: too early to projectdubairealestateiq.com
SAMANA Ocean Bay
SAMANA Developers · Dubai Islands
3.2%
22 Sept 2026
37%-34.2behind30 Jun 2028under 10% built: too early to projectdubairealestateiq.com
City Walk Crestlane 3
Meraas · Al Wasl
4.6%
15 Sept 2026
39%-34.2behind10 Dec 2028under 10% built: too early to projectdubairealestateiq.com
Ivy at Park Five
Deyaar Development PJSC · Dubai Production City
6.3%
17 Sept 2026
41%-34.2behind31 Dec 2027under 10% built: too early to projectdubairealestateiq.com
Camden
Nshama · Al Yelayiss 2
7.2%
18 Aug 2026
42%-34.2behind31 Mar 2028under 10% built: too early to projectdubairealestateiq.com
Hills View at Wasl Gate
Suncrest · Jabal Ali First
9.1%
24 Sept 2026
43%-34.2behind30 Jun 2028under 10% built: too early to projectdubairealestateiq.com

Next page

Method

Time elapsed = (inspection date minus construction start on the register) divided by (registered completion date minus construction start). When no start date is printed, the registration date is used.

Gap = % built at the inspection minus % of time elapsed at the same date, in percentage points. Behind = a gap below -10 points. Registered date passed = the inspection is after the completion date on the register and the project is not at 100%.

Projection, only for 10% to 99% built: the remaining % divided by the observed pace, where the pace is % built per day since the start date, since the registration date and between the last two inspections we hold (when it rose). The range runs from the earliest to the latest of these estimates.

Limits: Construction does not move in a straight line (a slow start, faster structure, slow finishing), so a straight line from an early reading tends to give later dates than the work will need, and a late reading can give earlier ones. The % built is the DLD inspection figure, not ours.

Source: the Dubai Land Department project register as mirrored per project with its inspection history, read by our register job; 985 DLD records, 28 with two or more dated inspections.