Kolaboro / By handover year / All places / Overdue handovers in Costa del Sol: November 2026 report
Overdue handovers in Costa del Sol: November 2026 report
Every project we track in Costa del Sol whose handover date on record has passed and that is not recorded as completed. Facts only, each with its source, no verdicts.
Projects past the handover date
| Project | Developer | Handover date on record | Months past | Stage, latest record | Last checked |
|---|---|---|---|---|---|
| Idilia Terram | AEDAS Homes | Q1 2026 aedashomes.com | 8 | Under construction | 17 Nov 2026 |
| Salvia | Grupo ABU and NVOGA Marbella Realty | Q1 2026 lucasfox.com | 8 | Under construction | 31 Oct 2026 |
| Zenity Indigo | AEDAS Homes | Q1 2026 aedashomes.com | 8 | Under construction | 17 Nov 2026 |
| Mare (Nueva Alcántara) | Taylor Wimpey España | July 2026 taylorwimpeyspain.com | 4 | Under construction | 17 Nov 2026 |
| Zenity Blau | AEDAS Homes | July 2026 aedashomes.com | 4 | Under construction | 17 Nov 2026 |
| Australy Aures | AEDAS Homes | Q3 2026 aedashomes.com | 2 | Under construction | 17 Nov 2026 |
| Zenity Cyan | AEDAS Homes | Q3 2026 aedashomes.com | 2 | Under construction | 17 Nov 2026 |
| South Sand | AEDAS Homes | October 2026 aedashomes.com | 1 | Under construction | 17 Nov 2026 |
Data as of 17 Nov 2026 from our open files. named.json · promises.json · bali-cases.json
How this report is made
Rule: the handover date on record (the latest one we hold) ended before November 2026; a quarter or year counts from its last month. Projects recorded as completed, or whose handover promise is recorded as kept, are left out. A passed date is a fact about the published schedule, not a finding about the developer: ask them for the current schedule in writing.
How to cite this report
Kolaboro, "Overdue handovers in Costa del Sol: November 2026 report", https://kolaboro.com/handover/overdue/costa-del-sol/, data as of 18 Nov 2026. Licence CC BY 4.0.
All placesHandover years in Costa del Sol:202620272028All projects in Costa del Sol
Questions
How many off-plan projects in Costa del Sol are past their handover date?
As of 18 Nov 2026: 8 of the 30 projects we track there with a handover date on record.
Which project in Costa del Sol is furthest past its handover date?
Idilia Terram: the handover date on record is Q1 2026, 8 months ago.
Does a passed handover date mean the project has failed?
No. It means the published date has passed and the sources we read do not record the project as completed. Ask the developer for the current schedule in writing.
Are you the developer? Send us documents for anything we missed and we add them after review.