Kolaboro / By handover year / All places / Overdue handovers in Costa del Sol: November 2026 report

Overdue handovers in Costa del Sol: November 2026 report

Every project we track in Costa del Sol whose handover date on record has passed and that is not recorded as completed. Facts only, each with its source, no verdicts.

8Past the date on record
30Projects with a handover date
4Median months past
8Longest, months

Projects past the handover date

ProjectDeveloperHandover date on recordMonths pastStage, latest recordLast checked
Idilia TerramAEDAS HomesQ1 2026 aedashomes.com8Under construction17 Nov 2026
SalviaGrupo ABU and NVOGA Marbella RealtyQ1 2026 lucasfox.com8Under construction31 Oct 2026
Zenity IndigoAEDAS HomesQ1 2026 aedashomes.com8Under construction17 Nov 2026
Mare (Nueva Alcántara)Taylor Wimpey EspañaJuly 2026 taylorwimpeyspain.com4Under construction17 Nov 2026
Zenity BlauAEDAS HomesJuly 2026 aedashomes.com4Under construction17 Nov 2026
Australy AuresAEDAS HomesQ3 2026 aedashomes.com2Under construction17 Nov 2026
Zenity CyanAEDAS HomesQ3 2026 aedashomes.com2Under construction17 Nov 2026
South SandAEDAS HomesOctober 2026 aedashomes.com1Under construction17 Nov 2026

Data as of 17 Nov 2026 from our open files. named.json · promises.json · bali-cases.json

How this report is made

Rule: the handover date on record (the latest one we hold) ended before November 2026; a quarter or year counts from its last month. Projects recorded as completed, or whose handover promise is recorded as kept, are left out. A passed date is a fact about the published schedule, not a finding about the developer: ask them for the current schedule in writing.

How to cite this report

Kolaboro, "Overdue handovers in Costa del Sol: November 2026 report", https://kolaboro.com/handover/overdue/costa-del-sol/, data as of 18 Nov 2026. Licence CC BY 4.0.

All placesHandover years in Costa del Sol:202620272028All projects in Costa del Sol

Questions

How many off-plan projects in Costa del Sol are past their handover date?

As of 18 Nov 2026: 8 of the 30 projects we track there with a handover date on record.

Which project in Costa del Sol is furthest past its handover date?

Idilia Terram: the handover date on record is Q1 2026, 8 months ago.

Does a passed handover date mean the project has failed?

No. It means the published date has passed and the sources we read do not record the project as completed. Ask the developer for the current schedule in writing.

Are you the developer? Send us documents for anything we missed and we add them after review.