Kolaboro / By handover year / All places / Overdue handovers in Algarve: November 2026 report
Overdue handovers in Algarve: November 2026 report
Every project we track in Algarve whose handover date on record has passed and that is not recorded as completed. Facts only, each with its source, no verdicts.
Projects past the handover date
| Project | Developer | Handover date on record | Months past | Stage, latest record | Last checked |
|---|---|---|---|---|---|
| Ribamar | AEDAS Homes | Q2 2026 obranueva.aedashomes.com | 5 | Off-plan | 11 Nov 2026 |
| Signature Apartments II | Palmares Ocean Living & Golf | June 2026 palmaresliving.com | 5 | Under construction | 8 Nov 2026 |
Data as of 11 Nov 2026 from our open files. named.json · promises.json · bali-cases.json
How this report is made
Rule: the handover date on record (the latest one we hold) ended before November 2026; a quarter or year counts from its last month. Projects recorded as completed, or whose handover promise is recorded as kept, are left out. A passed date is a fact about the published schedule, not a finding about the developer: ask them for the current schedule in writing.
How to cite this report
Kolaboro, "Overdue handovers in Algarve: November 2026 report", https://kolaboro.com/handover/overdue/algarve/, data as of 13 Nov 2026. Licence CC BY 4.0.
All placesHandover years in Algarve:20272028All projects in Algarve
Questions
How many off-plan projects in Algarve are past their handover date?
As of 13 Nov 2026: 2 of the 8 projects we track there with a handover date on record.
Which project in Algarve is furthest past its handover date?
Ribamar: the handover date on record is Q2 2026, 5 months ago.
Does a passed handover date mean the project has failed?
No. It means the published date has passed and the sources we read do not record the project as completed. Ask the developer for the current schedule in writing.
Are you the developer? Send us documents for anything we missed and we add them after review.