Home / Dubai / Construction pace against the registered date
Construction pace against the registered date
For Dubai projects with DLD inspection readings: % built against the share of time elapsed to the completion date on the register, and the completion range the observed pace points to. A projection, not a promise.
Updated 23 Nov 2026
A projection from the pace on the register, not a promise, and not a finding about the developer.
Show as a table
| Gap (points) | Projects |
|---|---|
| -60 … -50 | 98 |
| -50 … -40 | 119 |
| -40 … -30 | 168 |
| -30 … -20 | 186 |
| -20 … -10 | 140 |
| -10 … 0 | 94 |
| 0 … 10 | 29 |
| 10 … 20 | 13 |
| 20 … 30 | 9 |
| 30 … 40 | 3 |
| 40 … 50 | 1 |
Projects
| Project | % built (inspection) | Time elapsed | Gap (points) | Pace | Registered completion | Projected range | Register |
|---|---|---|---|---|---|---|---|
| Villa Dell Arte Amberton Residences · Palm Deira | 0% 8 Jul 2026 | 25% | -25.2 | behind | 27 Dec 2027 | under 10% built: too early to project | dubairealestateiq.com |
| Vivida Residences N A M O · Madinat Al Mataar | 0.8% 17 Aug 2026 | 26% | -25.2 | behind | 30 Sept 2027 | under 10% built: too early to project | dubairealestateiq.com |
| Expo City Sidr Residences Expo City Dubai · Madinat Al Mataar | 25% 18 Aug 2026 | 50% | -25.1 | behind | 31 Mar 2028 | Jul 2031 – Jan 2032 | dubairealestateiq.com |
| Floarea Skies Mashriq Elite · Jumeirah Village Circle | 4.5% 6 Jul 2026 | 30% | -25.1 | behind | 31 Dec 2028 | under 10% built: too early to project | dubairealestateiq.com |
| South Garden E Wasl · Jabal Ali First | 8% 7 Sept 2026 | 33% | -25 | behind | 31 May 2028 | under 10% built: too early to project | dubairealestateiq.com |
| Park Boulevard by Meteora Meteora · Jumeirah Village Circle | 30% 10 Mar 2026 | 55% | -25 | behind | 31 Jul 2027 | Feb 2030 | dubairealestateiq.com |
| Grand Polo - Chevalia Estate Emaar Properties · Grand Polo Club, Dubai Investment Park Second | 2.3% 21 Apr 2026 | 27% | -24.9 | behind | 28 Feb 2029 | under 10% built: too early to project | dubairealestateiq.com |
| Pier Point 1 Emaar Properties · Dubai Maritime City | 8.3% 14 May 2026 | 33% | -24.8 | behind | 31 Oct 2028 | under 10% built: too early to project | dubairealestateiq.com |
| Grand Polo - Montura 3 Emaar Properties · Grand Polo Club, Dubai Investment Park Second | 1.1% 21 Apr 2026 | 26% | -24.7 | behind | 30 Jun 2029 | under 10% built: too early to project | dubairealestateiq.com |
| Bararigate by Ade A D E Properties L.L.C · Majan | 1.7% 20 Oct 2026 | 26% | -24.7 | behind | 31 Dec 2028 | under 10% built: too early to project | dubairealestateiq.com |
| Ryze by Aum Aum · International City Ph 1 | 0.1% 10 Aug 2026 | 25% | -24.7 | behind | 30 Jun 2028 | under 10% built: too early to project | dubairealestateiq.com |
| Pier Point 2 Emaar Properties · Dubai Maritime City | 8.5% 14 May 2026 | 33% | -24.6 | behind | 31 Oct 2028 | under 10% built: too early to project | dubairealestateiq.com |
| Avenue Park Towers Wasl · Al Kifaf | 7.7% 8 Sept 2026 | 32% | -24.6 | behind | 31 Dec 2028 | under 10% built: too early to project | dubairealestateiq.com |
| Elaris Axis Object 1 · Jumeirah Village Triangle | 4.2% 9 Nov 2026 | 29% | -24.6 | behind | 30 Nov 2028 | under 10% built: too early to project | dubairealestateiq.com |
| Elmora Neoterra · Al Satwa | 0% 7 May 2026 | 25% | -24.6 | behind | 15 Feb 2028 | under 10% built: too early to project | dubairealestateiq.com |
| Seapoint Residences Emaar Properties · Emaar Beachfront | 36.8% 24 Jun 2026 | 61% | -24.4 | behind | 31 Mar 2028 | Apr 2031 – Jan 2032 | dubairealestateiq.com |
| Art House Hills by Adaan and Tuscany Art House Hills Residences · Arjan | 0.2% 29 Sept 2026 | 25% | -24.4 | behind | 1 Dec 2028 | under 10% built: too early to project | dubairealestateiq.com |
| Sobha Seahaven Tower A Sobha Realty · Dubai Marina | 45.2% 9 Nov 2026 | 70% | -24.3 | behind | 30 Apr 2028 | Dec 2030 – Mar 2031 | dubairealestateiq.com |
| Oasiz 2 by Danube Danube Properties · Silicon Oasis (Nadd Hessa) | 31% 29 Jul 2026 | 55% | -24.3 | behind | 30 Nov 2027 | Apr 2030 – Aug 2030 | dubairealestateiq.com |
| 241 Waterside Legacy Star Real Estate Development L.L.C · Palm Deira | 0% 29 Jun 2026 | 24% | -24.3 | behind | 15 Jun 2028 | under 10% built: too early to project | dubairealestateiq.com |
| Liora Jaiedco · Palm Deira | 0% 22 Jun 2026 | 24% | -24.3 | behind | 1 Jan 2028 | under 10% built: too early to project | dubairealestateiq.com |
| Azizi Leily Azizi Developments · Al Jadaf | 2% 5 Nov 2026 | 26% | -24.1 | behind | 30 Sept 2028 | under 10% built: too early to project | dubairealestateiq.com |
| DAMAC Hills (2) - Violet 2 DAMAC Properties · Madinat Hind 4 | 57.6% 22 Sept 2026 | 82% | -24 | behind | 27 Feb 2027 | Feb 2028 | dubairealestateiq.com |
| Grand Polo - Montura 2 Emaar Properties · Grand Polo Club, Dubai Investment Park Second | 5% 6 Jul 2026 | 29% | -23.9 | behind | 31 May 2029 | under 10% built: too early to project | dubairealestateiq.com |
| The First Collection at Dubai Studio City The First Group · Dubai Studio City | 31.9% 12 Oct 2026 | 56% | -23.9 | behind | 31 Jan 2028 | Apr 2030 | dubairealestateiq.com |
| Terra Heights Emaar Properties · Madinat Al Mataar | 9.1% 31 Jul 2026 | 33% | -23.8 | behind | 31 Mar 2029 | under 10% built: too early to project | dubairealestateiq.com |
| Nexara Tower Seventh Key Gateway · Jumeirah Village Circle | 20% 15 Sept 2026 | 44% | -23.7 | behind | 16 Apr 2028 | Aug 2031 | dubairealestateiq.com |
| SAMANA Hills South 3 SAMANA Developers · Dubai South | 15% 28 Oct 2026 | 39% | -23.6 | behind | 31 Aug 2028 | Nov 2031 – May 2033 | dubairealestateiq.com |
| Azizi Venice 13 Azizi Developments · Madinat Al Mataar | 45.9% 14 Oct 2026 | 69% | -23.4 | behind | 16 Sept 2027 | Mar 2029 – Mar 2029 | dubairealestateiq.com |
| Binghatti Skyflame 1 Binghatti Developers · Majan | 15.3% 28 Oct 2026 | 39% | -23.3 | behind | 31 Dec 2027 | Feb 2030 – Nov 2030 | dubairealestateiq.com |
| Beach Walk Residences 4 by Imtiaz Imtiaz Developments · Dubai Islands | 54.1% 5 Nov 2026 | 77% | -23.2 | behind | 20 Apr 2027 | Oct 2027 – Feb 2028 | dubairealestateiq.com |
| Omya Residences Pantheon · Jabal Ali First | 0% 15 Oct 2026 | 23% | -23.2 | behind | 30 Jun 2028 | under 10% built: too early to project | dubairealestateiq.com |
| The Eighty Three Oksa · Madinat Al Mataar | 60% 11 Aug 2026 | 83% | -23.2 | behind | 14 Dec 2026 | Sept 2027 | dubairealestateiq.com |
| Sapphire 32 by Dar Alkarama Dar Al Karama · Jumeirah Village Circle | 73.9% 10 Nov 2026 | 97% | -23.1 | behind | 15 Dec 2026 | Dec 2027 | dubairealestateiq.com |
| Chelsea Residences by DAMAC DAMAC Properties · Dubai Maritime City | 6.5% 11 Nov 2026 | 30% | -23 | behind | 31 Dec 2029 | under 10% built: too early to project | dubairealestateiq.com |
| Aquora by Casa Vista Development Casa Vista · Palm Deira | 2.7% 21 Jul 2026 | 26% | -23 | behind | 11 Oct 2028 | under 10% built: too early to project | dubairealestateiq.com |
| Alta View Skyhomes Object 1 · Jumeirah Village Circle | 5.8% 16 Sept 2026 | 29% | -22.9 | behind | 30 Jun 2029 | under 10% built: too early to project | dubairealestateiq.com |
| Breez by Danube Danube Properties · Dubai Maritime City | 0.7% 28 Oct 2026 | 24% | -22.8 | behind | 30 Jun 2029 | under 10% built: too early to project | dubairealestateiq.com |
| Grand Polo - Chevalia Fields Emaar Properties · Grand Polo Club, Dubai Investment Park Second | 10% 21 Jul 2026 | 33% | -22.8 | behind | 30 Apr 2029 | Sept 2037 – Sept 2038 | dubairealestateiq.com |
| Waada - Altura BT Properties · Madinat Al Mataar | 7.2% 20 Oct 2026 | 30% | -22.8 | behind | 14 Mar 2029 | under 10% built: too early to project | dubairealestateiq.com |
| Mirdad Union Properties PJSC · Al Hebiah First | 6% 28 Sept 2026 | 29% | -22.8 | behind | 31 Dec 2028 | under 10% built: too early to project | dubairealestateiq.com |
| Antalya by Karma Karma · Dubai Sports City | 0.1% 14 Apr 2026 | 23% | -22.7 | behind | 30 Sept 2028 | under 10% built: too early to project | dubairealestateiq.com |
| Aspirz Danube Properties · Dubai Sports City | 8.6% 28 Oct 2026 | 31% | -22.6 | behind | 31 Dec 2028 | under 10% built: too early to project | dubairealestateiq.com |
| Sunset Bay Grand by Imtiaz Imtiaz Developments · Dubai Islands | 23.1% 9 Nov 2026 | 46% | -22.6 | behind | 15 Feb 2028 | May 2030 – Jul 2030 | dubairealestateiq.com |
| R Home Mh Bukadra · Bukadra | 1.8% 21 Oct 2026 | 24% | -22.6 | behind | 31 Aug 2029 | under 10% built: too early to project | dubairealestateiq.com |
| Celeste Heights by Zimaya Properties Zimaya · Jabal Ali First | 41.2% 20 Oct 2026 | 64% | -22.6 | behind | 30 Sept 2027 | Mar 2029 | dubairealestateiq.com |
| Sakura Gardens by HRE HRE Development · Wadi Al Safa 2 | 3.6% 21 Sept 2026 | 26% | -22.4 | behind | 30 Jun 2029 | under 10% built: too early to project | dubairealestateiq.com |
| Pearl House 4 by Imtiaz Imtiaz Developments · Jumeirah Village Circle (JVC) | 17.9% 7 Oct 2026 | 40% | -22.2 | behind | 29 Feb 2028 | Jan 2031 – Apr 2031 | dubairealestateiq.com |
| The Oasis - Address Villas - Tierra Emaar Properties · Me'Aisem Second | 6.8% 21 Jul 2026 | 29% | -22.2 | behind | 30 Jun 2029 | under 10% built: too early to project | dubairealestateiq.com |
| Rise by Athlon Dubai Holding Real Estate · Dubai Land Residence Complex | 3.7% 22 Oct 2026 | 26% | -22.2 | behind | 30 Dec 2029 | under 10% built: too early to project | dubairealestateiq.com |
| Reef Reef Luxury Development · Dubai Land Residence Complex | 67.2% 5 Oct 2026 | 89% | -22.2 | behind | 30 Dec 2026 | Sept 2027 | dubairealestateiq.com |
| Divine Al Barari Takmeel · Majan | 20.3% 20 Oct 2026 | 43% | -22.2 | behind | 31 Mar 2028 | Dec 2030 | dubairealestateiq.com |
| Zenith Residences Art Of Amber · International City Ph 2 & 3 | 24.1% 7 Oct 2026 | 46% | -22.2 | behind | 1 Mar 2028 | Jul 2030 | dubairealestateiq.com |
| DAMAC Lagoons - Lagoon Views 11 DAMAC Properties · Al Hebiah Fifth | 42.6% 17 Jul 2026 | 65% | -22.1 | behind | 30 Jun 2027 | Nov 2028 – Mar 2029 | dubairealestateiq.com |
| Golf Residences by Prestige One Prestige Golf Residences · Dubai Sports City | 35.7% 10 Aug 2026 | 58% | -21.9 | behind | 16 Feb 2028 | Apr 2030 | dubairealestateiq.com |
| Timez by Danube Danube Properties · Dubai Silicon Oasis | 21.5% 9 Sept 2026 | 43% | -21.8 | behind | 31 Jul 2028 | Dec 2031 – Jun 2032 | dubairealestateiq.com |
| Dg1 Living Dar Global · Business Bay | 65% 5 Oct 2026 | 87% | -21.7 | behind | 15 Apr 2027 | Aug 2028 | dubairealestateiq.com |
| Solaya (4,6) La Mer Central Property · La Mer | 0% 28 Sept 2026 | 22% | -21.7 | behind | 30 Sept 2029 | under 10% built: too early to project | dubairealestateiq.com |
| Solaya (5,7) La Mer Central Property · La Mer | 0% 28 Sept 2026 | 22% | -21.7 | behind | 30 Sept 2029 | under 10% built: too early to project | dubairealestateiq.com |
| Royal Yacht Club Residence Azimuth · Palm Deira | 25.3% 20 Oct 2026 | 47% | -21.7 | behind | 10 Nov 2027 | Jul 2029 | dubairealestateiq.com |
Method
Time elapsed = (inspection date minus construction start on the register) divided by (registered completion date minus construction start). When no start date is printed, the registration date is used.
Gap = % built at the inspection minus % of time elapsed at the same date, in percentage points. Behind = a gap below -10 points. Registered date passed = the inspection is after the completion date on the register and the project is not at 100%.
Projection, only for 10% to 99% built: the remaining % divided by the observed pace, where the pace is % built per day since the start date, since the registration date and between the last two inspections we hold (when it rose). The range runs from the earliest to the latest of these estimates.
Limits: Construction does not move in a straight line (a slow start, faster structure, slow finishing), so a straight line from an early reading tends to give later dates than the work will need, and a late reading can give earlier ones. The % built is the DLD inspection figure, not ours.
Source: the Dubai Land Department project register as mirrored per project with its inspection history, read by our register job; 985 DLD records, 28 with two or more dated inspections.
Files: /data/n35a/pace.json · /open/n35a-build.py · /registers/changes/