Home / Dubai / Construction pace against the registered date
Construction pace against the registered date
For Dubai projects with DLD inspection readings: % built against the share of time elapsed to the completion date on the register, and the completion range the observed pace points to. A projection, not a promise.
Updated 23 Nov 2026
A projection from the pace on the register, not a promise, and not a finding about the developer.
Show as a table
| Gap (points) | Projects |
|---|---|
| -60 … -50 | 98 |
| -50 … -40 | 119 |
| -40 … -30 | 168 |
| -30 … -20 | 186 |
| -20 … -10 | 140 |
| -10 … 0 | 94 |
| 0 … 10 | 29 |
| 10 … 20 | 13 |
| 20 … 30 | 9 |
| 30 … 40 | 3 |
| 40 … 50 | 1 |
Projects
| Project | % built (inspection) | Time elapsed | Gap (points) | Pace | Registered completion | Projected range | Register |
|---|---|---|---|---|---|---|---|
| Floarea Breeze Mashriq Elite · Palm Deira | 3.8% 26 Oct 2026 | 35% | -31.5 | behind | 30 Jun 2028 | under 10% built: too early to project | dubairealestateiq.com |
| Elaris Rise Object 1 · Jumeirah Village Triangle | 3.6% 29 Oct 2026 | 35% | -31.4 | behind | 30 Sept 2028 | under 10% built: too early to project | dubairealestateiq.com |
| Liv Oceanside LIV · Palm Deira | 14.1% 22 Oct 2026 | 46% | -31.4 | behind | 30 Nov 2027 | Jun 2032 | dubairealestateiq.com |
| Avant Garde Residences II by Skyline Skyline Builders · Jumeirah Village Circle | 8.9% 5 Nov 2026 | 40% | -31.4 | behind | 30 Sept 2028 | under 10% built: too early to project | dubairealestateiq.com |
| City Walk Crestlane Meraas · City Walk | 1.5% 9 Nov 2026 | 33% | -31.3 | behind | 30 Sept 2029 | under 10% built: too early to project | dubairealestateiq.com |
| Purvanchal Triana Residences Purvanchal · Al Satwa | 26.4% 3 Aug 2026 | 58% | -31.3 | behind | 1 Mar 2027 | Oct 2028 | dubairealestateiq.com |
| Athlon by Al Dar Dubai Holding Real Estate · Dubai Land Residence Complex | 27.3% 22 Oct 2026 | 59% | -31.2 | behind | 31 May 2028 | Nov 2032 | dubairealestateiq.com |
| Provenza Residences I K R · Jumeirah Village Circle | 20.3% 6 Aug 2026 | 52% | -31.2 | behind | 30 Sept 2027 | May 2031 | dubairealestateiq.com |
| Eden House Dubai Hills Sunrise Valley · Hadaeq Sheikh Mohammed Bin Rashid | 0.1% 13 Aug 2026 | 31% | -31.2 | behind | 1 Dec 2027 | under 10% built: too early to project | dubairealestateiq.com |
| Divine Elements Takmeel · Madinat Al Mataar | 0% 8 Jul 2026 | 31% | -31 | behind | 31 Dec 2027 | under 10% built: too early to project | dubairealestateiq.com |
| Khk 31 Khk · Dubai Land Residence Complex | 25.8% 31 Aug 2026 | 57% | -30.9 | behind | 22 Mar 2027 | Oct 2028 | dubairealestateiq.com |
| SAMANA Barari Avenue SAMANA Developers · Majan, Dubailand | 6% 23 Sept 2026 | 37% | -30.8 | behind | 31 Oct 2028 | under 10% built: too early to project | dubairealestateiq.com |
| Sola Residences Centurion Properties / Royal Centurion · Wasl Gate / Al Furjan side (DLD district Jabal Ali First) | 35.4% 9 Nov 2026 | 66% | -30.7 | behind | 15 Sept 2027 | Nov 2029 – Jan 2030 | dubairealestateiq.com |
| Elire Qube · Business Bay | 12% 16 Nov 2026 | 43% | -30.7 | behind | 15 Dec 2028 | Mar 2038 | dubairealestateiq.com |
| Binghatti Flare 02 Binghatti Developers · Jumeirah Village Triangle | 17.8% 19 Jun 2026 | 48% | -30.6 | behind | 15 Jun 2027 | Feb 2030 – Sept 2030 | dubairealestateiq.com |
| The Borough Iconic Vista · Jumeirah Village Circle | 5.5% 11 Aug 2026 | 36% | -30.6 | behind | 31 Mar 2028 | under 10% built: too early to project | dubairealestateiq.com |
| Reportage Hills (R. Hills) Reportage Properties · Dubailand (Al Hebiah Fifth) | 0.4% 4 Jun 2026 | 31% | -30.5 | behind | 30 Jun 2028 | under 10% built: too early to project | dubairealestateiq.com |
| DAMAC Lagoons - Lagoon Views 9 DAMAC Properties · Al Hebiah Fifth | 47.3% 1 Sept 2026 | 78% | -30.5 | behind | 31 Mar 2027 | Dec 2028 – Jan 2029 | dubairealestateiq.com |
| Sobha Solis Sobha Realty · Motor City | 17.9% 22 Oct 2026 | 48% | -30.4 | behind | 31 Dec 2028 | Nov 2034 – Mar 2036 | dubairealestateiq.com |
| DAMAC Lagoons - Lagoon Views 10 DAMAC Properties · Al Hebiah Fifth | 47.4% 1 Sept 2026 | 78% | -30.4 | behind | 31 Mar 2027 | Dec 2028 – Jan 2029 | dubairealestateiq.com |
| Cybele by Wadan Wadan · Dubai Land Residence Complex | 2% 27 Jul 2026 | 32% | -30.3 | behind | 30 Dec 2027 | under 10% built: too early to project | dubairealestateiq.com |
| Cove Living Residence by Imtiaz Imtiaz Developments · Dubai Land Residence Complex | 47.2% 11 Aug 2026 | 77% | -30.2 | behind | 15 Apr 2027 | Feb 2029 – Mar 2029 | dubairealestateiq.com |
| Olbia Nshama · Al Yelayiss 2 | 0% 25 Apr 2026 | 30% | -30.2 | behind | 31 May 2028 | under 10% built: too early to project | dubairealestateiq.com |
| Lia Avenew · Palm Deira | 4.1% 2 Oct 2026 | 34% | -30.1 | behind | 20 May 2028 | under 10% built: too early to project | dubairealestateiq.com |
| Lumina Yehiaco · Um Hurair Second | 11.4% 22 Jul 2026 | 42% | -30.1 | behind | 1 Apr 2028 | Nov 2035 | dubairealestateiq.com |
| Wynwood by Imtiaz Imtiaz Developments · Dubai Islands | 26.3% 6 Oct 2026 | 56% | -30 | behind | 30 Sept 2027 | Apr 2030 | dubairealestateiq.com |
| Atelis at D3 Dubai Holding Real Estate · Zaabeel Second | 1.4% 8 Oct 2026 | 31% | -30 | behind | 14 Aug 2029 | under 10% built: too early to project | dubairealestateiq.com |
| Villa Del Brunello Residences Divo Home Real Estate Development L.L.C · Palm Deira | 2.2% 16 Jun 2026 | 32% | -30 | behind | 30 Nov 2027 | under 10% built: too early to project | dubairealestateiq.com |
| Samana Greenfield Samana Developers · Al Warsan 4, International City Phase 2 | 3.2% 28 Oct 2026 | 33% | -29.8 | behind | 31 Oct 2028 | under 10% built: too early to project | dubairealestateiq.com |
| Bayz 102 Danube Properties · Business Bay | 6.5% 6 Oct 2026 | 36% | -29.8 | behind | 31 Dec 2029 | under 10% built: too early to project | dubairealestateiq.com |
| Sobha Orbis Sobha Realty · Motor City | 18.2% 13 Aug 2026 | 48% | -29.8 | behind | 31 Dec 2028 | Jan 2036 – Jun 2036 | dubairealestateiq.com |
| Samana Business Park 2 SAMANA Developers · Majan | 3.2% 28 Oct 2026 | 33% | -29.8 | behind | 31 Oct 2028 | under 10% built: too early to project | dubairealestateiq.com |
| The Cube Quarter Residences Amwaj · Majan | 57% 15 Sept 2026 | 87% | -29.7 | behind | 31 Dec 2026 | Feb 2028 | dubairealestateiq.com |
| D Villas Dar Global · Dubai Production City | 9.1% 10 Sept 2026 | 39% | -29.6 | behind | 31 Dec 2028 | under 10% built: too early to project | dubairealestateiq.com |
| 368 Park Ln Tabeer · Jumeirah Village Circle | 1.7% 9 Nov 2026 | 31% | -29.5 | behind | 31 Aug 2028 | under 10% built: too early to project | dubairealestateiq.com |
| Belle Vie by Zimaya Zimaya · Silicon Oasis (Nadd Hessa) | 11% 9 Sept 2026 | 41% | -29.5 | behind | 31 Mar 2028 | Apr 2035 | dubairealestateiq.com |
| Parkgreen Residences by Alishaan Alishaan · Wadi Al Safa 2 | 4.3% 13 Oct 2026 | 34% | -29.5 | behind | 30 Jun 2028 | under 10% built: too early to project | dubairealestateiq.com |
| Palm Jebel Ali - Frond P Nakheel · Palm Jabal Ali | 48.8% 10 Nov 2026 | 78% | -29.3 | behind | 29 Sept 2027 | Mar 2030 – Jul 2030 | dubairealestateiq.com |
| Luxury Canal Residences Royal Centurion · Palm Deira | 28.9% 8 Oct 2026 | 58% | -29.1 | behind | 30 Nov 2027 | Aug 2030 | dubairealestateiq.com |
| Azha Millennium Residences Azha J V T Residences · Jumeirah Village Triangle | 30.1% 29 Sept 2026 | 59% | -29.1 | behind | 1 Sept 2027 | Nov 2029 | dubairealestateiq.com |
| Cove Boulevard by Imtiaz Imtiaz Developments · Dubailand (Dubai Land Residence Complex) | 10.5% 30 Sept 2026 | 39% | -28.9 | behind | 30 Oct 2028 | Mar 2038 – Apr 2038 | dubairealestateiq.com |
| Helvetia Marine D H G Property Development L.L.C · Palm Deira | 0% 27 Jul 2026 | 29% | -28.9 | behind | 15 Mar 2028 | under 10% built: too early to project | dubairealestateiq.com |
| Golden Woods Albab Views A G W · Madinat Al Mataar | 30.1% 11 Jun 2026 | 59% | -28.9 | behind | 28 Feb 2027 | Nov 2028 | dubairealestateiq.com |
| Dubai Harbour Residences Shamal · Dubai Marina | 30.3% 11 Aug 2026 | 59% | -28.7 | behind | 14 Jan 2028 | Apr 2031 | dubairealestateiq.com |
| Serenia District - West Palma Holding · Jumeirah Lakes Towers | 2.8% 11 May 2026 | 32% | -28.7 | behind | 31 Dec 2028 | under 10% built: too early to project | dubairealestateiq.com |
| Nest Andi · International City Ph 2 & 3 | 0.8% 14 May 2026 | 29% | -28.6 | behind | 1 Apr 2027 | under 10% built: too early to project | dubairealestateiq.com |
| Bianca Reportage Properties · Wadi Al Safa 2 | 56.1% 3 Jun 2026 | 85% | -28.5 | behind | 31 Dec 2026 | Nov 2028 | dubairealestateiq.com |
| Arisha Terraces Qube · Dubai Studio City | 34% 19 Aug 2026 | 63% | -28.5 | behind | 1 Oct 2027 | Mar 2030 | dubairealestateiq.com |
| Yigo26 Yangtze International · International City Ph 1 | 1.1% 21 Jul 2026 | 30% | -28.5 | behind | 31 Dec 2027 | under 10% built: too early to project | dubairealestateiq.com |
| Dusit Princess Rijas Aces · Jumeirah Village Circle | 64.1% 6 Aug 2026 | 93% | -28.5 | behind | 30 Apr 2027 | Sept 2031 | dubairealestateiq.com |
| One Park Square by Iman Iman Developers · Jumeirah Village Circle | 20.1% 22 Sept 2026 | 48% | -28.4 | behind | 30 Jun 2028 | May 2033 | dubairealestateiq.com |
| Distrikt Majid Al Futtaim · City of Arabia | 8.4% 17 Aug 2026 | 37% | -28.4 | behind | 30 Sept 2028 | under 10% built: too early to project | dubairealestateiq.com |
| Porto View Emaar Properties · Dubai Maritime City | 6.3% 2 Jun 2026 | 35% | -28.3 | behind | 31 Oct 2028 | under 10% built: too early to project | dubairealestateiq.com |
| The Wilds Dubai Holding Real Estate · Majan | 7.5% 14 Sept 2026 | 36% | -28.2 | behind | 31 Jan 2029 | under 10% built: too early to project | dubairealestateiq.com |
| The Orchard Place - Towers D&E Peak Summit Real Estate Development L.L.C · Jumeirah Village Circle | 0.8% 16 Mar 2026 | 29% | -28.1 | behind | 21 Mar 2028 | under 10% built: too early to project | dubairealestateiq.com |
| Avenue Residence 8 Nabni Almustaqbal · Jabal Ali First | 17.8% 17 Sept 2026 | 46% | -28.1 | behind | 30 Jun 2028 | Sept 2033 | dubairealestateiq.com |
| Binghatti Etherea Binghatti Developers · Jumeirah Village Circle | 7.2% 15 Sept 2026 | 35% | -28 | behind | 31 Dec 2027 | under 10% built: too early to project | dubairealestateiq.com |
| 27 East End Garden Residences by Mirha Homes Real Estate Development Mirha Homes · International City Ph 2 & 3 | 40.3% 10 Aug 2026 | 68% | -28 | behind | 31 Jan 2027 | Feb 2028 | dubairealestateiq.com |
| Wadi Villas by Arista Pbg · Majan | 60.4% 2 Sept 2026 | 88% | -27.9 | behind | 31 Dec 2026 | Apr 2028 | dubairealestateiq.com |
| SAMANA ParkVille SAMANA Developers · Dubai Land Residence Complex (DLRC) | 13.9% 21 Oct 2026 | 42% | -27.8 | behind | 30 Sept 2028 | Apr 2035 – Jun 2035 | dubairealestateiq.com |
Method
Time elapsed = (inspection date minus construction start on the register) divided by (registered completion date minus construction start). When no start date is printed, the registration date is used.
Gap = % built at the inspection minus % of time elapsed at the same date, in percentage points. Behind = a gap below -10 points. Registered date passed = the inspection is after the completion date on the register and the project is not at 100%.
Projection, only for 10% to 99% built: the remaining % divided by the observed pace, where the pace is % built per day since the start date, since the registration date and between the last two inspections we hold (when it rose). The range runs from the earliest to the latest of these estimates.
Limits: Construction does not move in a straight line (a slow start, faster structure, slow finishing), so a straight line from an early reading tends to give later dates than the work will need, and a late reading can give earlier ones. The % built is the DLD inspection figure, not ours.
Source: the Dubai Land Department project register as mirrored per project with its inspection history, read by our register job; 985 DLD records, 28 with two or more dated inspections.