Construction pace against the registered date
For Dubai projects with DLD inspection readings: % built against the share of time elapsed to the completion date on the register, and the completion range the observed pace points to. A projection, not a promise.
Updated 23 Nov 2026
A projection from the pace on the register, not a promise, and not a finding about the developer.
Show as a table
| Gap (points) | Projects |
|---|---|
| -60 … -50 | 98 |
| -50 … -40 | 119 |
| -40 … -30 | 168 |
| -30 … -20 | 186 |
| -20 … -10 | 140 |
| -10 … 0 | 94 |
| 0 … 10 | 29 |
| 10 … 20 | 13 |
| 20 … 30 | 9 |
| 30 … 40 | 3 |
| 40 … 50 | 1 |
Projects
| Project | % built (inspection) | Time elapsed | Gap (points) | Pace | Registered completion | Projected range | Register |
|---|---|---|---|---|---|---|---|
| Iconic Mered · Site A | 34.9% 11 Aug 2026 | 63% | -27.8 | behind | 28 Feb 2028 | Jun 2031 | dubairealestateiq.com |
| Eltiera Heights Ellington Properties · Jumeirah Islands | 3% 20 Jul 2026 | 31% | -27.7 | behind | 31 Dec 2028 | under 10% built: too early to project | dubairealestateiq.com |
| Seraph by Wadan Wadan · Dubai Land Residence Complex | 20.9% 27 Oct 2026 | 49% | -27.7 | behind | 15 Dec 2027 | Nov 2030 | dubairealestateiq.com |
| The Autograph-I Series Green Group · Jumeirah Village Circle | 4% 23 Apr 2026 | 32% | -27.7 | behind | 31 Aug 2028 | under 10% built: too early to project | dubairealestateiq.com |
| South Garden D Wasl · Jabal Ali First | 5.7% 7 Sept 2026 | 33% | -27.3 | behind | 31 May 2028 | under 10% built: too early to project | dubairealestateiq.com |
| 77s 77 Shades Of Green · Business Bay | 13.7% 10 Sept 2026 | 41% | -27.3 | behind | 31 Dec 2028 | Oct 2036 | dubairealestateiq.com |
| Azizi Lina Azizi Developments · Jabal Ali Industrial Second | 2.4% 16 Nov 2026 | 30% | -27.1 | behind | 30 Sept 2028 | under 10% built: too early to project | dubairealestateiq.com |
| Villa Del Garda Residences Riviera · Palm Deira | 0% 28 Sept 2026 | 27% | -27.1 | behind | 4 Mar 2028 | under 10% built: too early to project | dubairealestateiq.com |
| Linden Residences Black Soil · International City Ph 2 & 3 | 26.8% 4 Sept 2026 | 54% | -27.1 | behind | 30 Dec 2027 | Nov 2030 | dubairealestateiq.com |
| The Valley - Farm Grove 2 Emaar Properties · Al Yufrah 1 | 9.8% 6 Jul 2026 | 37% | -27 | behind | 31 Oct 2028 | under 10% built: too early to project | dubairealestateiq.com |
| Marina Views Emaar Properties · Dubai Maritime City | 7.1% 5 May 2026 | 34% | -27 | behind | 31 Dec 2028 | under 10% built: too early to project | dubairealestateiq.com |
| DAMAC Lagoons - Lagoon Views 12 DAMAC Properties · Al Hebiah Fifth | 36.5% 17 Jul 2026 | 64% | -27 | behind | 30 Jun 2027 | Jun 2029 – Dec 2029 | dubairealestateiq.com |
| Ocean Views Emaar Properties · Dubai Maritime City | 6.2% 21 Apr 2026 | 33% | -26.9 | behind | 30 Sept 2028 | under 10% built: too early to project | dubairealestateiq.com |
| Longfor International Center Star Lang · International City Ph 1 | 1.6% 15 Oct 2026 | 29% | -26.9 | behind | 30 Dec 2027 | under 10% built: too early to project | dubairealestateiq.com |
| Oasiz 1 by Danube Danube Properties · Silicon Oasis (Nadd Hessa) | 38.2% 12 Nov 2026 | 65% | -26.8 | behind | 30 Nov 2027 | Jan 2030 – May 2030 | dubairealestateiq.com |
| The Weave The Weave · Jumeirah Village Circle | 7.6% 13 Aug 2026 | 34% | -26.8 | behind | 1 Sept 2028 | under 10% built: too early to project | dubairealestateiq.com |
| Golf Acres Emaar Properties · Madinat Al Mataar | 3.5% 23 Jun 2026 | 30% | -26.6 | behind | 31 Dec 2028 | under 10% built: too early to project | dubairealestateiq.com |
| Samana Business Park SAMANA Developers · Majan | 12.8% 24 Sept 2026 | 39% | -26.6 | behind | 30 Sept 2028 | Apr 2035 – Aug 2035 | dubairealestateiq.com |
| Leven Residences Metrical · Jumeirah Village Triangle | 23.3% 6 Aug 2026 | 50% | -26.6 | behind | 15 Nov 2027 | Oct 2030 | dubairealestateiq.com |
| Binghatti Flare Binghatti Developers · Jumeirah Village Triangle | 20% 19 Jun 2026 | 47% | -26.5 | behind | 14 Jul 2027 | Oct 2029 – Mar 2030 | dubairealestateiq.com |
| The Collective Bold Living · Madinat Al Mataar | 5.7% 20 Aug 2026 | 32% | -26.5 | behind | 31 Mar 2028 | under 10% built: too early to project | dubairealestateiq.com |
| Rabdan Square Rabdan · Nad Al Shiba First | 1.2% 7 Oct 2026 | 28% | -26.4 | behind | 1 Mar 2028 | under 10% built: too early to project | dubairealestateiq.com |
| La Vue Parc Maaia Prime · Nad Al Shiba First | 15.4% 1 Jul 2026 | 42% | -26.4 | behind | 15 Sept 2027 | Apr 2031 | dubairealestateiq.com |
| Binghatti Skyflame 2 Binghatti Developers · Majan | 12.2% 28 Oct 2026 | 39% | -26.3 | behind | 31 Dec 2027 | Feb 2031 – Feb 2032 | dubairealestateiq.com |
| The Valley - Vindera Emaar Properties · Al Yufrah 1 | 2% 20 Jan 2026 | 28% | -26.3 | behind | 31 Dec 2028 | under 10% built: too early to project | dubairealestateiq.com |
| Burj Azizi Azizi Developments · Trade Center First | 7.5% 3 Sept 2026 | 34% | -26.3 | behind | 30 Aug 2030 | under 10% built: too early to project | dubairealestateiq.com |
| Palm Jebel Ali - the Beach and Coral Collection - Frond D Nakheel · Palm Jabal Ali | 2.2% 13 Oct 2026 | 29% | -26.3 | behind | 4 Dec 2028 | under 10% built: too early to project | dubairealestateiq.com |
| Waada - Rayhan 1 BT Properties · Madinat Al Mataar | 15.1% 20 Oct 2026 | 42% | -26.3 | behind | 31 Oct 2028 | Nov 2034 | dubairealestateiq.com |
| Sol Levante SOL Properties · Jumeirah Village Triangle | 7.2% 6 Jul 2026 | 34% | -26.3 | behind | 15 Sept 2028 | under 10% built: too early to project | dubairealestateiq.com |
| Pristine by Zoya Zoya · Jabal Ali First | 58.4% 20 Aug 2026 | 85% | -26.3 | behind | 1 Jan 2027 | Jan 2028 | dubairealestateiq.com |
| Montage Key Mavens · Al Jadaf | 40% 15 Oct 2026 | 66% | -26.2 | behind | 31 Aug 2027 | May 2029 | dubairealestateiq.com |
| Samana Hills South 2 SAMANA Developers · Dubai Industrial City (Saih Shuaib 2) | 12.4% 28 Oct 2026 | 39% | -26.1 | behind | 31 Aug 2028 | Nov 2034 – Dec 2034 | dubairealestateiq.com |
| Palm Jebel Ali - Frond M Nakheel · Palm Jabal Ali | 51.3% 10 Nov 2026 | 77% | -26.1 | behind | 8 Oct 2027 | Oct 2029 – Feb 2030 | dubairealestateiq.com |
| Palm Jebel Ali - the Beach and Coral Collection Nakheel · Palm Jabal Ali | 2.4% 13 Oct 2026 | 29% | -26.1 | behind | 4 Dec 2028 | under 10% built: too early to project | dubairealestateiq.com |
| 15 Cascade Iman Developers · Al Hebiah First | 5.5% 2 Jul 2026 | 32% | -26.1 | behind | 30 Sept 2028 | under 10% built: too early to project | dubairealestateiq.com |
| Binghatti Skyblade Binghatti Developers · Downtown Dubai | 17.1% 21 Apr 2026 | 43% | -26 | behind | 30 Nov 2027 | Jul 2029 – Mar 2032 | dubairealestateiq.com |
| Palm Jebel Ali - the Beach and Coral Collection - Frond F Nakheel · Palm Jabal Ali | 2.5% 13 Oct 2026 | 29% | -26 | behind | 4 Dec 2028 | under 10% built: too early to project | dubairealestateiq.com |
| Coastal Haven by Prestige Harbour Real Estate Development Royal Centurion · Palm Deira | 33% 8 Oct 2026 | 59% | -26 | behind | 30 Nov 2027 | Feb 2030 | dubairealestateiq.com |
| Stories by Mirfa Mirfa · Madinat Al Mataar | 0.5% 1 Oct 2026 | 27% | -26 | behind | 31 Mar 2028 | under 10% built: too early to project | dubairealestateiq.com |
| Palm Jebel Ali - the Beach and Coral Collection - Frond E Nakheel · Palm Jabal Ali | 2.6% 13 Oct 2026 | 29% | -25.9 | behind | 4 Dec 2028 | under 10% built: too early to project | dubairealestateiq.com |
| Wellington Ocean by Ank Motiwala Developments A N K · Palm Deira | 33.1% 22 Oct 2026 | 59% | -25.9 | behind | 19 Dec 2027 | Mar 2030 | dubairealestateiq.com |
| The Valley - Farm Grove Emaar Properties · Al Yufrah 1 | 10% 15 Jul 2026 | 36% | -25.8 | behind | 31 Dec 2028 | Nov 2038 – Jan 2041 | dubairealestateiq.com |
| Palm Jebel Ali - the Beach and Coral Collection - Frond B Nakheel · Palm Jabal Ali | 2.7% 13 Oct 2026 | 29% | -25.8 | behind | 4 Dec 2028 | under 10% built: too early to project | dubairealestateiq.com |
| Palm Jebel Ali - the Beach and Coral Collection - Frond C Nakheel · Palm Jabal Ali | 2.8% 13 Oct 2026 | 29% | -25.8 | behind | 4 Dec 2028 | under 10% built: too early to project | dubairealestateiq.com |
| Avana Residences by Deca Real Estate Development Deca · Jumeirah Village Circle | 3% 21 Apr 2026 | 29% | -25.8 | behind | 30 Nov 2027 | under 10% built: too early to project | dubairealestateiq.com |
| Emerge Residences N A A S Real Estate Development L.L.C · Nad Al Shiba First | 21.1% 2 Sept 2026 | 47% | -25.8 | behind | 1 Nov 2027 | Jul 2030 | dubairealestateiq.com |
| Beach Walk Grand by Imtiaz Imtiaz Developments · Dubai Islands | 68% 9 Nov 2026 | 94% | -25.7 | behind | 25 Dec 2026 | Sept 2027 – Sept 2027 | dubairealestateiq.com |
| Alder at Park Five Deyaar Development PJSC · Dubai Production City | 6.1% 30 Sept 2026 | 32% | -25.7 | behind | 31 Dec 2027 | under 10% built: too early to project | dubairealestateiq.com |
| Veona by Gutti Gutti · Dubai Land Residence Complex | 21.7% 14 Oct 2026 | 47% | -25.7 | behind | 31 Dec 2027 | Sept 2030 | dubairealestateiq.com |
| Nourelle Dubai Holding Real Estate · Um Suqaim Third | 6.3% 3 Nov 2026 | 32% | -25.6 | behind | 1 Mar 2029 | under 10% built: too early to project | dubairealestateiq.com |
| Avenew888 - Modo Avenew · Madinat Al Mataar | 21.2% 8 Oct 2026 | 47% | -25.6 | behind | 15 Mar 2028 | Jun 2031 | dubairealestateiq.com |
| Floarea Oasis Mashriq Elite · Dubai Land Residence Complex | 12.6% 15 Sept 2026 | 38% | -25.6 | behind | 30 Dec 2028 | Jul 2036 | dubairealestateiq.com |
| Beach Walk Grand 2 by Imtiaz Imtiaz Developments · Dubai Islands | 23.5% 14 Sept 2026 | 49% | -25.5 | behind | 15 Dec 2027 | Jul 2030 – Aug 2030 | dubairealestateiq.com |
| Sea View Residence by Sama Mayas Sama Mayas · Palm Deira | 12.7% 1 Jun 2026 | 38% | -25.5 | behind | 30 Sept 2027 | Jan 2032 | dubairealestateiq.com |
| Aero 1 Bithaus · Madinat Al Mataar | 35.6% 29 Sept 2026 | 61% | -25.5 | behind | 15 Jul 2027 | Dec 2028 | dubairealestateiq.com |
| Marina Place 2 Emaar Properties · Dubai Maritime City | 1.5% 21 Apr 2026 | 27% | -25.4 | behind | 31 Dec 2028 | under 10% built: too early to project | dubairealestateiq.com |
| Ashwood Estates Wasl · Dubai Production City | 0.1% 1 Jun 2026 | 25% | -25.3 | behind | 18 Sept 2028 | under 10% built: too early to project | dubairealestateiq.com |
| 09 Life Residences Deniz · Dubai Land Residence Complex | 6.8% 26 Aug 2026 | 32% | -25.3 | behind | 1 Dec 2027 | under 10% built: too early to project | dubairealestateiq.com |
| Marquis Horizon Marquis · Madinat Al Mataar | 0% 10 Nov 2026 | 25% | -25.2 | behind | 5 Sept 2028 | under 10% built: too early to project | dubairealestateiq.com |
| The Autograph-S Series Green Group · Jumeirah Village Circle | 18.5% 14 Apr 2026 | 44% | -25.2 | behind | 31 Dec 2027 | Feb 2032 | dubairealestateiq.com |
Method
Time elapsed = (inspection date minus construction start on the register) divided by (registered completion date minus construction start). When no start date is printed, the registration date is used.
Gap = % built at the inspection minus % of time elapsed at the same date, in percentage points. Behind = a gap below -10 points. Registered date passed = the inspection is after the completion date on the register and the project is not at 100%.
Projection, only for 10% to 99% built: the remaining % divided by the observed pace, where the pace is % built per day since the start date, since the registration date and between the last two inspections we hold (when it rose). The range runs from the earliest to the latest of these estimates.
Limits: Construction does not move in a straight line (a slow start, faster structure, slow finishing), so a straight line from an early reading tends to give later dates than the work will need, and a late reading can give earlier ones. The % built is the DLD inspection figure, not ours.
Source: the Dubai Land Department project register as mirrored per project with its inspection history, read by our register job; 985 DLD records, 28 with two or more dated inspections.
Files: /data/n35a/pace.json · /open/n35a-build.py · /registers/changes/