Home / Dubai / Construction pace against the registered date

Construction pace against the registered date

For Dubai projects with DLD inspection readings: % built against the share of time elapsed to the completion date on the register, and the completion range the observed pace points to. A projection, not a promise.

Updated 23 Nov 2026

A projection from the pace on the register, not a promise, and not a finding about the developer.

860projects compared (DLD % built and dates on the register)
82.7%more than 10 points behind the time elapsed (95% interval 80 to 85.1%)
-27median gap in points, % built minus % of time elapsed (95% interval -29.1 to -26)
452projects with a projected range (10% to 99% built)
86.7%of them projected after the registered date (95% interval 83.3 to 89.5%)
≤-6098-50119-40168-30186-20140-10940291013209303401
Projects by gap between % built and % of time elapsed, in 10-point bins
Show as a table
Gap (points)Projects
-60 … -5098
-50 … -40119
-40 … -30168
-30 … -20186
-20 … -10140
-10 … 094
0 … 1029
10 … 2013
20 … 309
30 … 403
40 … 501

Projects

711 projects, page 8
Project% built (inspection)Time elapsedGap (points)PaceRegistered completionProjected rangeRegister
Iconic
Mered · Site A
34.9%
11 Aug 2026
63%-27.8behind28 Feb 2028Jun 2031dubairealestateiq.com
Eltiera Heights
Ellington Properties · Jumeirah Islands
3%
20 Jul 2026
31%-27.7behind31 Dec 2028under 10% built: too early to projectdubairealestateiq.com
Seraph by Wadan
Wadan · Dubai Land Residence Complex
20.9%
27 Oct 2026
49%-27.7behind15 Dec 2027Nov 2030dubairealestateiq.com
The Autograph-I Series
Green Group · Jumeirah Village Circle
4%
23 Apr 2026
32%-27.7behind31 Aug 2028under 10% built: too early to projectdubairealestateiq.com
South Garden D
Wasl · Jabal Ali First
5.7%
7 Sept 2026
33%-27.3behind31 May 2028under 10% built: too early to projectdubairealestateiq.com
77s
77 Shades Of Green · Business Bay
13.7%
10 Sept 2026
41%-27.3behind31 Dec 2028Oct 2036dubairealestateiq.com
Azizi Lina
Azizi Developments · Jabal Ali Industrial Second
2.4%
16 Nov 2026
30%-27.1behind30 Sept 2028under 10% built: too early to projectdubairealestateiq.com
Villa Del Garda Residences
Riviera · Palm Deira
0%
28 Sept 2026
27%-27.1behind4 Mar 2028under 10% built: too early to projectdubairealestateiq.com
Linden Residences
Black Soil · International City Ph 2 & 3
26.8%
4 Sept 2026
54%-27.1behind30 Dec 2027Nov 2030dubairealestateiq.com
The Valley - Farm Grove 2
Emaar Properties · Al Yufrah 1
9.8%
6 Jul 2026
37%-27behind31 Oct 2028under 10% built: too early to projectdubairealestateiq.com
Marina Views
Emaar Properties · Dubai Maritime City
7.1%
5 May 2026
34%-27behind31 Dec 2028under 10% built: too early to projectdubairealestateiq.com
DAMAC Lagoons - Lagoon Views 12
DAMAC Properties · Al Hebiah Fifth
36.5%
17 Jul 2026
64%-27behind30 Jun 2027Jun 2029 – Dec 2029dubairealestateiq.com
Ocean Views
Emaar Properties · Dubai Maritime City
6.2%
21 Apr 2026
33%-26.9behind30 Sept 2028under 10% built: too early to projectdubairealestateiq.com
Longfor International Center
Star Lang · International City Ph 1
1.6%
15 Oct 2026
29%-26.9behind30 Dec 2027under 10% built: too early to projectdubairealestateiq.com
Oasiz 1 by Danube
Danube Properties · Silicon Oasis (Nadd Hessa)
38.2%
12 Nov 2026
65%-26.8behind30 Nov 2027Jan 2030 – May 2030dubairealestateiq.com
The Weave
The Weave · Jumeirah Village Circle
7.6%
13 Aug 2026
34%-26.8behind1 Sept 2028under 10% built: too early to projectdubairealestateiq.com
Golf Acres
Emaar Properties · Madinat Al Mataar
3.5%
23 Jun 2026
30%-26.6behind31 Dec 2028under 10% built: too early to projectdubairealestateiq.com
Samana Business Park
SAMANA Developers · Majan
12.8%
24 Sept 2026
39%-26.6behind30 Sept 2028Apr 2035 – Aug 2035dubairealestateiq.com
Leven Residences
Metrical · Jumeirah Village Triangle
23.3%
6 Aug 2026
50%-26.6behind15 Nov 2027Oct 2030dubairealestateiq.com
Binghatti Flare
Binghatti Developers · Jumeirah Village Triangle
20%
19 Jun 2026
47%-26.5behind14 Jul 2027Oct 2029 – Mar 2030dubairealestateiq.com
The Collective
Bold Living · Madinat Al Mataar
5.7%
20 Aug 2026
32%-26.5behind31 Mar 2028under 10% built: too early to projectdubairealestateiq.com
Rabdan Square
Rabdan · Nad Al Shiba First
1.2%
7 Oct 2026
28%-26.4behind1 Mar 2028under 10% built: too early to projectdubairealestateiq.com
La Vue Parc
Maaia Prime · Nad Al Shiba First
15.4%
1 Jul 2026
42%-26.4behind15 Sept 2027Apr 2031dubairealestateiq.com
Binghatti Skyflame 2
Binghatti Developers · Majan
12.2%
28 Oct 2026
39%-26.3behind31 Dec 2027Feb 2031 – Feb 2032dubairealestateiq.com
The Valley - Vindera
Emaar Properties · Al Yufrah 1
2%
20 Jan 2026
28%-26.3behind31 Dec 2028under 10% built: too early to projectdubairealestateiq.com
Burj Azizi
Azizi Developments · Trade Center First
7.5%
3 Sept 2026
34%-26.3behind30 Aug 2030under 10% built: too early to projectdubairealestateiq.com
Palm Jebel Ali - the Beach and Coral Collection - Frond D
Nakheel · Palm Jabal Ali
2.2%
13 Oct 2026
29%-26.3behind4 Dec 2028under 10% built: too early to projectdubairealestateiq.com
Waada - Rayhan 1
BT Properties · Madinat Al Mataar
15.1%
20 Oct 2026
42%-26.3behind31 Oct 2028Nov 2034dubairealestateiq.com
Sol Levante
SOL Properties · Jumeirah Village Triangle
7.2%
6 Jul 2026
34%-26.3behind15 Sept 2028under 10% built: too early to projectdubairealestateiq.com
Pristine by Zoya
Zoya · Jabal Ali First
58.4%
20 Aug 2026
85%-26.3behind1 Jan 2027Jan 2028dubairealestateiq.com
Montage
Key Mavens · Al Jadaf
40%
15 Oct 2026
66%-26.2behind31 Aug 2027May 2029dubairealestateiq.com
Samana Hills South 2
SAMANA Developers · Dubai Industrial City (Saih Shuaib 2)
12.4%
28 Oct 2026
39%-26.1behind31 Aug 2028Nov 2034 – Dec 2034dubairealestateiq.com
Palm Jebel Ali - Frond M
Nakheel · Palm Jabal Ali
51.3%
10 Nov 2026
77%-26.1behind8 Oct 2027Oct 2029 – Feb 2030dubairealestateiq.com
Palm Jebel Ali - the Beach and Coral Collection
Nakheel · Palm Jabal Ali
2.4%
13 Oct 2026
29%-26.1behind4 Dec 2028under 10% built: too early to projectdubairealestateiq.com
15 Cascade
Iman Developers · Al Hebiah First
5.5%
2 Jul 2026
32%-26.1behind30 Sept 2028under 10% built: too early to projectdubairealestateiq.com
Binghatti Skyblade
Binghatti Developers · Downtown Dubai
17.1%
21 Apr 2026
43%-26behind30 Nov 2027Jul 2029 – Mar 2032dubairealestateiq.com
Palm Jebel Ali - the Beach and Coral Collection - Frond F
Nakheel · Palm Jabal Ali
2.5%
13 Oct 2026
29%-26behind4 Dec 2028under 10% built: too early to projectdubairealestateiq.com
Coastal Haven by Prestige Harbour Real Estate Development
Royal Centurion · Palm Deira
33%
8 Oct 2026
59%-26behind30 Nov 2027Feb 2030dubairealestateiq.com
Stories by Mirfa
Mirfa · Madinat Al Mataar
0.5%
1 Oct 2026
27%-26behind31 Mar 2028under 10% built: too early to projectdubairealestateiq.com
Palm Jebel Ali - the Beach and Coral Collection - Frond E
Nakheel · Palm Jabal Ali
2.6%
13 Oct 2026
29%-25.9behind4 Dec 2028under 10% built: too early to projectdubairealestateiq.com
Wellington Ocean by Ank Motiwala Developments
A N K · Palm Deira
33.1%
22 Oct 2026
59%-25.9behind19 Dec 2027Mar 2030dubairealestateiq.com
The Valley - Farm Grove
Emaar Properties · Al Yufrah 1
10%
15 Jul 2026
36%-25.8behind31 Dec 2028Nov 2038 – Jan 2041dubairealestateiq.com
Palm Jebel Ali - the Beach and Coral Collection - Frond B
Nakheel · Palm Jabal Ali
2.7%
13 Oct 2026
29%-25.8behind4 Dec 2028under 10% built: too early to projectdubairealestateiq.com
Palm Jebel Ali - the Beach and Coral Collection - Frond C
Nakheel · Palm Jabal Ali
2.8%
13 Oct 2026
29%-25.8behind4 Dec 2028under 10% built: too early to projectdubairealestateiq.com
Avana Residences by Deca Real Estate Development
Deca · Jumeirah Village Circle
3%
21 Apr 2026
29%-25.8behind30 Nov 2027under 10% built: too early to projectdubairealestateiq.com
Emerge Residences
N A A S Real Estate Development L.L.C · Nad Al Shiba First
21.1%
2 Sept 2026
47%-25.8behind1 Nov 2027Jul 2030dubairealestateiq.com
Beach Walk Grand by Imtiaz
Imtiaz Developments · Dubai Islands
68%
9 Nov 2026
94%-25.7behind25 Dec 2026Sept 2027 – Sept 2027dubairealestateiq.com
Alder at Park Five
Deyaar Development PJSC · Dubai Production City
6.1%
30 Sept 2026
32%-25.7behind31 Dec 2027under 10% built: too early to projectdubairealestateiq.com
Veona by Gutti
Gutti · Dubai Land Residence Complex
21.7%
14 Oct 2026
47%-25.7behind31 Dec 2027Sept 2030dubairealestateiq.com
Nourelle
Dubai Holding Real Estate · Um Suqaim Third
6.3%
3 Nov 2026
32%-25.6behind1 Mar 2029under 10% built: too early to projectdubairealestateiq.com
Avenew888 - Modo
Avenew · Madinat Al Mataar
21.2%
8 Oct 2026
47%-25.6behind15 Mar 2028Jun 2031dubairealestateiq.com
Floarea Oasis
Mashriq Elite · Dubai Land Residence Complex
12.6%
15 Sept 2026
38%-25.6behind30 Dec 2028Jul 2036dubairealestateiq.com
Beach Walk Grand 2 by Imtiaz
Imtiaz Developments · Dubai Islands
23.5%
14 Sept 2026
49%-25.5behind15 Dec 2027Jul 2030 – Aug 2030dubairealestateiq.com
Sea View Residence by Sama Mayas
Sama Mayas · Palm Deira
12.7%
1 Jun 2026
38%-25.5behind30 Sept 2027Jan 2032dubairealestateiq.com
Aero 1
Bithaus · Madinat Al Mataar
35.6%
29 Sept 2026
61%-25.5behind15 Jul 2027Dec 2028dubairealestateiq.com
Marina Place 2
Emaar Properties · Dubai Maritime City
1.5%
21 Apr 2026
27%-25.4behind31 Dec 2028under 10% built: too early to projectdubairealestateiq.com
Ashwood Estates
Wasl · Dubai Production City
0.1%
1 Jun 2026
25%-25.3behind18 Sept 2028under 10% built: too early to projectdubairealestateiq.com
09 Life Residences
Deniz · Dubai Land Residence Complex
6.8%
26 Aug 2026
32%-25.3behind1 Dec 2027under 10% built: too early to projectdubairealestateiq.com
Marquis Horizon
Marquis · Madinat Al Mataar
0%
10 Nov 2026
25%-25.2behind5 Sept 2028under 10% built: too early to projectdubairealestateiq.com
The Autograph-S Series
Green Group · Jumeirah Village Circle
18.5%
14 Apr 2026
44%-25.2behind31 Dec 2027Feb 2032dubairealestateiq.com

Next page

Method

Time elapsed = (inspection date minus construction start on the register) divided by (registered completion date minus construction start). When no start date is printed, the registration date is used.

Gap = % built at the inspection minus % of time elapsed at the same date, in percentage points. Behind = a gap below -10 points. Registered date passed = the inspection is after the completion date on the register and the project is not at 100%.

Projection, only for 10% to 99% built: the remaining % divided by the observed pace, where the pace is % built per day since the start date, since the registration date and between the last two inspections we hold (when it rose). The range runs from the earliest to the latest of these estimates.

Limits: Construction does not move in a straight line (a slow start, faster structure, slow finishing), so a straight line from an early reading tends to give later dates than the work will need, and a late reading can give earlier ones. The % built is the DLD inspection figure, not ours.

Source: the Dubai Land Department project register as mirrored per project with its inspection history, read by our register job; 985 DLD records, 28 with two or more dated inspections.

Files: /data/n35a/pace.json · /open/n35a-build.py · /registers/changes/