Home / Dubai / Construction pace against the registered date
Construction pace against the registered date
For Dubai projects with DLD inspection readings: % built against the share of time elapsed to the completion date on the register, and the completion range the observed pace points to. A projection, not a promise.
Updated 23 Nov 2026
A projection from the pace on the register, not a promise, and not a finding about the developer.
Show as a table
| Gap (points) | Projects |
|---|---|
| -60 … -50 | 98 |
| -50 … -40 | 119 |
| -40 … -30 | 168 |
| -30 … -20 | 186 |
| -20 … -10 | 140 |
| -10 … 0 | 94 |
| 0 … 10 | 29 |
| 10 … 20 | 13 |
| 20 … 30 | 9 |
| 30 … 40 | 3 |
| 40 … 50 | 1 |
Projects
| Project | % built (inspection) | Time elapsed | Gap (points) | Pace | Registered completion | Projected range | Register |
|---|---|---|---|---|---|---|---|
| Talea OMNIYAT · Dubai Maritime City | 4.7% 2 Nov 2026 | 26% | -21.6 | behind | 30 Jun 2028 | under 10% built: too early to project | dubairealestateiq.com |
| Fiori Nshama · Al Yelayiss 2 | 0% 25 Apr 2026 | 22% | -21.6 | behind | 30 Jun 2028 | under 10% built: too early to project | dubairealestateiq.com |
| Nuvana by Wadan Wadan · Palm Deira | 24.9% 30 Jul 2026 | 46% | -21.5 | behind | 1 Sept 2027 | Jun 2029 | dubairealestateiq.com |
| Holm One Holm Avenue · Al Satwa | 17.7% 22 Oct 2026 | 39% | -21.5 | behind | 30 Mar 2028 | Feb 2031 | dubairealestateiq.com |
| Grand Polo - Montura Emaar Properties · Grand Polo Club, Dubai Investment Park Second | 11.1% 5 Aug 2026 | 33% | -21.4 | behind | 30 Jun 2029 | Dec 2036 – Oct 2037 | dubairealestateiq.com |
| Chapter 01 by Newbury Developments Newbury · International City Ph 2 & 3 | 2.4% 25 Jun 2026 | 24% | -21.4 | behind | 1 Oct 2028 | under 10% built: too early to project | dubairealestateiq.com |
| Prestige Gardens by Prestige One Prestige Gardens · Al Satwa | 0% 17 Sept 2026 | 21% | -21.4 | behind | 30 Sept 2028 | under 10% built: too early to project | dubairealestateiq.com |
| Marina Place 1 Emaar Properties · Dubai Maritime City | 4.2% 3 Apr 2026 | 26% | -21.3 | behind | 31 Dec 2028 | under 10% built: too early to project | dubairealestateiq.com |
| Solaya (1,2,3) La Mer North Property · La Mer | 0% 14 Jul 2026 | 21% | -21.3 | behind | 30 Jun 2029 | under 10% built: too early to project | dubairealestateiq.com |
| Sunvale Prysm · Jabal Ali First | 1.3% 23 Jun 2026 | 23% | -21.3 | behind | 31 May 2028 | under 10% built: too early to project | dubairealestateiq.com |
| The Caden by Prescott Prescott · Bukadra | 0.5% 2 Jun 2026 | 22% | -21.2 | behind | 15 May 2028 | under 10% built: too early to project | dubairealestateiq.com |
| Empire Estates Empire · Arjan | 60% 19 Jun 2026 | 81% | -21.1 | behind | 31 Dec 2026 | Dec 2027 | dubairealestateiq.com |
| Time 3 Time Properties · Dubai Land Residence Complex | 47.1% 24 Aug 2026 | 68% | -21.1 | behind | 1 Aug 2027 | Nov 2028 | dubairealestateiq.com |
| Velos Residence City View Urban · Al Hebiah First | 6.6% 4 Aug 2026 | 28% | -21.1 | behind | 31 Oct 2028 | under 10% built: too early to project | dubairealestateiq.com |
| Art House Private Residences by Viva Viva · Majan | 0% 23 Jun 2026 | 21% | -21.1 | behind | 15 Feb 2028 | under 10% built: too early to project | dubairealestateiq.com |
| Cg Living C G Gulf · Palm Deira | 1.6% 18 May 2026 | 23% | -21.1 | behind | 30 Jun 2028 | under 10% built: too early to project | dubairealestateiq.com |
| The Highgrove Ellington Properties · Mohammed Bin Rashid City | 7% 6 Aug 2026 | 28% | -20.9 | behind | 31 Dec 2028 | under 10% built: too early to project | dubairealestateiq.com |
| ORLA, Dorchester Collection Omniyat · Palm Jumeirah (The Crescent) | 70% 21 Aug 2026 | 91% | -20.8 | behind | 31 Dec 2026 | Feb 2028 – Mar 2028 | dubairealestateiq.com |
| Nanma Lotus Nanma Properties · Madinat Al Mataar | 3.6% 15 Oct 2026 | 24% | -20.8 | behind | 15 Feb 2028 | under 10% built: too early to project | dubairealestateiq.com |
| Xenia Residence N Y X · Jumeirah Village Circle | 51.6% 15 Oct 2026 | 72% | -20.8 | behind | 1 Mar 2027 | Sept 2027 | dubairealestateiq.com |
| Maravea Residences Enzo Prime · Palm Deira | 0% 8 Jul 2026 | 21% | -20.8 | behind | 30 Apr 2028 | under 10% built: too early to project | dubairealestateiq.com |
| Franck Muller Yachting London Gate · Dubai Maritime City | 0% 26 Mar 2026 | 21% | -20.7 | behind | 29 Jul 2028 | under 10% built: too early to project | dubairealestateiq.com |
| Hqa by Arista Arista One · Jabal Ali First | 0% 10 Aug 2026 | 21% | -20.7 | behind | 30 Jun 2028 | under 10% built: too early to project | dubairealestateiq.com |
| DAMAC Riverside - Ivy DAMAC Properties · Dubai Investment Park Second | 38.1% 26 Aug 2026 | 59% | -20.6 | behind | 31 Dec 2027 | Oct 2029 – Jan 2030 | dubairealestateiq.com |
| Rosewell Nshama · Al Yelayiss 2 | 0% 26 Jun 2026 | 21% | -20.6 | behind | 31 Dec 2028 | under 10% built: too early to project | dubairealestateiq.com |
| Le Blanc by Imtiaz Imtiaz Developments · Dubailand Residence Complex | 6% 8 Oct 2026 | 27% | -20.5 | behind | 15 Oct 2028 | under 10% built: too early to project | dubairealestateiq.com |
| Prestige One Residences Prestige Luxe Real Estate Development L.L.C · Dubai Maritime City | 0.1% 23 Sept 2026 | 21% | -20.4 | behind | 31 Dec 2029 | under 10% built: too early to project | dubairealestateiq.com |
| Nad Al Sheba Gardens Phase 11 Shamal · Nad Al Shiba First | 0.1% 20 Aug 2026 | 20% | -20.2 | behind | 1 Jul 2029 | under 10% built: too early to project | dubairealestateiq.com |
| Ocean Cove Emaar Properties · Dubai Maritime City | 17.9% 14 Apr 2026 | 38% | -20.1 | behind | 31 Aug 2028 | Dec 2032 – Apr 2034 | dubairealestateiq.com |
| Golf Verge Emaar Properties · Madinat Al Mataar | 4.2% 22 Jul 2026 | 24% | -20.1 | behind | 31 May 2029 | under 10% built: too early to project | dubairealestateiq.com |
| Voxa Residences Pantheon · Jumeirah Village Triangle | 4.5% 1 Jun 2026 | 25% | -20.1 | behind | 31 Dec 2028 | under 10% built: too early to project | dubairealestateiq.com |
| Elwood Estates Sobha Realty · Al Yufrah 1 | 14.4% 20 Jul 2026 | 34% | -19.9 | behind | 30 Jun 2028 | Aug 2032 – Nov 2033 | dubairealestateiq.com |
| Ellington Sands I Ellington Properties · Dubai Islands (Island A) | 0.4% 5 Jun 2026 | 20% | -19.8 | behind | 31 Dec 2028 | under 10% built: too early to project | dubairealestateiq.com |
| The Bristol Emaar Beachfront Emaar Properties · Dubai Marina | 5.8% 23 Jun 2026 | 26% | -19.8 | behind | 30 Sept 2029 | under 10% built: too early to project | dubairealestateiq.com |
| Ellington Sands II Ellington Properties · Palm Deira | 0.4% 5 Jun 2026 | 20% | -19.8 | behind | 31 Dec 2028 | under 10% built: too early to project | dubairealestateiq.com |
| HQ by Rove IRTH Group · Business Bay | 0.7% 6 Jul 2026 | 21% | -19.8 | behind | 31 Mar 2029 | under 10% built: too early to project | dubairealestateiq.com |
| Alba Tower Century Seven Properties L.L.C · Al Satwa | 30.9% 27 Jul 2026 | 51% | -19.8 | behind | 30 Jun 2028 | Dec 2030 | dubairealestateiq.com |
| Chelsea Residences 2 by DAMAC DAMAC Properties · Dubai Maritime City | 6.5% 11 Nov 2026 | 26% | -19.7 | behind | 31 Dec 2029 | under 10% built: too early to project | dubairealestateiq.com |
| Jumeirah Residences Emirates Towers Dubai Holding Real Estate · Trade Center Second | 4.2% 28 Sept 2026 | 24% | -19.6 | behind | 1 Sept 2030 | under 10% built: too early to project | dubairealestateiq.com |
| Palm Central Private Residences - Frond M Nakheel · Palm Jabal Ali | 0.1% 15 Sept 2026 | 20% | -19.5 | behind | 31 Jul 2029 | under 10% built: too early to project | dubairealestateiq.com |
| Kyomi Residence Anax · International City Ph 2 & 3 | 0% 12 Oct 2026 | 20% | -19.5 | behind | 1 Jan 2028 | under 10% built: too early to project | dubairealestateiq.com |
| DAMAC Hills (2) - Violet 3 DAMAC Properties · Madinat Hind 4 | 36.2% 16 May 2026 | 56% | -19.4 | behind | 30 Jun 2027 | Nov 2028 – Jan 2029 | dubairealestateiq.com |
| Palm Jebel Ali - Frond N Nakheel · Palm Jabal Ali | 58% 10 Nov 2026 | 77% | -19.4 | behind | 8 Oct 2027 | Feb 2029 – May 2029 | dubairealestateiq.com |
| Solen Residence by Jamal Living Mohammad Abuhijleh · Silicon Oasis (Nadd Hessa) | 21.7% 13 Aug 2026 | 41% | -19.4 | behind | 30 Oct 2027 | Sept 2029 | dubairealestateiq.com |
| Interstellar Tower MR8 · Jumeirah Village Triangle | 0% 6 Jul 2026 | 19% | -19.3 | behind | 30 Sept 2028 | under 10% built: too early to project | dubairealestateiq.com |
| Orvessa Residences by Michel Adam Bnw Echjay · Jabal Ali First | 1.5% 10 Sept 2026 | 21% | -19.3 | behind | 30 Sept 2028 | under 10% built: too early to project | dubairealestateiq.com |
| The Valley - Elea Emaar Properties · Al Yufrah 1 | 22% 15 Jul 2026 | 41% | -19.2 | behind | 30 Jun 2028 | May 2031 – May 2032 | dubairealestateiq.com |
| Azurline Residences by Maas Developers M A A S Developers L.L.C · Jumeirah Village Circle | 56.5% 28 Sept 2026 | 76% | -19.2 | behind | 31 Mar 2027 | Dec 2027 | dubairealestateiq.com |
| Amis & Gpd Presents Fleur De Jardin Villas Amis Gpd Developer L.L.C · Majan | 0.6% 1 Sept 2026 | 20% | -19.2 | behind | 9 Oct 2028 | under 10% built: too early to project | dubairealestateiq.com |
| Eaton Square Ellington Properties · Bukadra | 5.4% 20 Jul 2026 | 25% | -19.1 | behind | 30 Jun 2028 | under 10% built: too early to project | dubairealestateiq.com |
| The Mural OMNIYAT · Dubai Maritime City | 16.6% 1 Oct 2026 | 36% | -18.8 | behind | 10 Jul 2028 | Aug 2031 – Feb 2034 | dubairealestateiq.com |
| Verdana Residence Reportage Properties · Dubai Investment Park First | 0% 5 Aug 2026 | 19% | -18.8 | behind | 30 Sept 2028 | under 10% built: too early to project | dubairealestateiq.com |
| Sierra by Iman Iman Developers · Al Hebiah First | 3.7% 10 Aug 2026 | 23% | -18.8 | behind | 30 Jun 2029 | under 10% built: too early to project | dubairealestateiq.com |
| Sol Luxe SOL Properties · Trade Center First | 2% 30 Jun 2026 | 21% | -18.8 | behind | 15 Mar 2029 | under 10% built: too early to project | dubairealestateiq.com |
| Wynwood Horizon Imtiaz Developments · Meydan Horizon, MBR City | 9.6% 16 Sept 2026 | 28% | -18.7 | behind | 30 Oct 2028 | under 10% built: too early to project | dubairealestateiq.com |
| Address the Bay Emaar Properties · Dubai Marina | 70.1% 15 Jul 2026 | 89% | -18.7 | behind | 31 Dec 2026 | Feb 2028 – Apr 2028 | dubairealestateiq.com |
| Enchante by Grid Grid Properties · Arjan | 1.6% 11 Nov 2026 | 20% | -18.7 | behind | 15 Dec 2028 | under 10% built: too early to project | dubairealestateiq.com |
| Sea Cliff by Imtiaz Imtiaz Developments · Dubai Islands | 7.7% 13 Oct 2026 | 26% | -18.6 | behind | 15 Aug 2028 | under 10% built: too early to project | dubairealestateiq.com |
| Golf Meadow Emaar Properties · Madinat Al Mataar | 4.5% 19 Jul 2026 | 23% | -18.6 | behind | 31 Jul 2029 | under 10% built: too early to project | dubairealestateiq.com |
| Rabdan Gardens Rabdan · Al Satwa | 0% 23 Jun 2026 | 19% | -18.5 | behind | 1 Mar 2028 | under 10% built: too early to project | dubairealestateiq.com |
Method
Time elapsed = (inspection date minus construction start on the register) divided by (registered completion date minus construction start). When no start date is printed, the registration date is used.
Gap = % built at the inspection minus % of time elapsed at the same date, in percentage points. Behind = a gap below -10 points. Registered date passed = the inspection is after the completion date on the register and the project is not at 100%.
Projection, only for 10% to 99% built: the remaining % divided by the observed pace, where the pace is % built per day since the start date, since the registration date and between the last two inspections we hold (when it rose). The range runs from the earliest to the latest of these estimates.
Limits: Construction does not move in a straight line (a slow start, faster structure, slow finishing), so a straight line from an early reading tends to give later dates than the work will need, and a late reading can give earlier ones. The % built is the DLD inspection figure, not ours.
Source: the Dubai Land Department project register as mirrored per project with its inspection history, read by our register job; 985 DLD records, 28 with two or more dated inspections.
Files: /data/n35a/pace.json · /open/n35a-build.py · /registers/changes/