Home / Dubai / Construction pace against the registered date

Construction pace against the registered date

For Dubai projects with DLD inspection readings: % built against the share of time elapsed to the completion date on the register, and the completion range the observed pace points to. A projection, not a promise.

Updated 23 Nov 2026

A projection from the pace on the register, not a promise, and not a finding about the developer.

860projects compared (DLD % built and dates on the register)
82.7%more than 10 points behind the time elapsed (95% interval 80 to 85.1%)
-27median gap in points, % built minus % of time elapsed (95% interval -29.1 to -26)
452projects with a projected range (10% to 99% built)
86.7%of them projected after the registered date (95% interval 83.3 to 89.5%)
≤-6098-50119-40168-30186-20140-10940291013209303401
Projects by gap between % built and % of time elapsed, in 10-point bins
Show as a table
Gap (points)Projects
-60 … -5098
-50 … -40119
-40 … -30168
-30 … -20186
-20 … -10140
-10 … 094
0 … 1029
10 … 2013
20 … 309
30 … 403
40 … 501

Projects

711 projects, page 10
Project% built (inspection)Time elapsedGap (points)PaceRegistered completionProjected rangeRegister
Talea
OMNIYAT · Dubai Maritime City
4.7%
2 Nov 2026
26%-21.6behind30 Jun 2028under 10% built: too early to projectdubairealestateiq.com
Fiori
Nshama · Al Yelayiss 2
0%
25 Apr 2026
22%-21.6behind30 Jun 2028under 10% built: too early to projectdubairealestateiq.com
Nuvana by Wadan
Wadan · Palm Deira
24.9%
30 Jul 2026
46%-21.5behind1 Sept 2027Jun 2029dubairealestateiq.com
Holm One
Holm Avenue · Al Satwa
17.7%
22 Oct 2026
39%-21.5behind30 Mar 2028Feb 2031dubairealestateiq.com
Grand Polo - Montura
Emaar Properties · Grand Polo Club, Dubai Investment Park Second
11.1%
5 Aug 2026
33%-21.4behind30 Jun 2029Dec 2036 – Oct 2037dubairealestateiq.com
Chapter 01 by Newbury Developments
Newbury · International City Ph 2 & 3
2.4%
25 Jun 2026
24%-21.4behind1 Oct 2028under 10% built: too early to projectdubairealestateiq.com
Prestige Gardens by Prestige One
Prestige Gardens · Al Satwa
0%
17 Sept 2026
21%-21.4behind30 Sept 2028under 10% built: too early to projectdubairealestateiq.com
Marina Place 1
Emaar Properties · Dubai Maritime City
4.2%
3 Apr 2026
26%-21.3behind31 Dec 2028under 10% built: too early to projectdubairealestateiq.com
Solaya (1,2,3)
La Mer North Property · La Mer
0%
14 Jul 2026
21%-21.3behind30 Jun 2029under 10% built: too early to projectdubairealestateiq.com
Sunvale
Prysm · Jabal Ali First
1.3%
23 Jun 2026
23%-21.3behind31 May 2028under 10% built: too early to projectdubairealestateiq.com
The Caden by Prescott
Prescott · Bukadra
0.5%
2 Jun 2026
22%-21.2behind15 May 2028under 10% built: too early to projectdubairealestateiq.com
Empire Estates
Empire · Arjan
60%
19 Jun 2026
81%-21.1behind31 Dec 2026Dec 2027dubairealestateiq.com
Time 3
Time Properties · Dubai Land Residence Complex
47.1%
24 Aug 2026
68%-21.1behind1 Aug 2027Nov 2028dubairealestateiq.com
Velos Residence
City View Urban · Al Hebiah First
6.6%
4 Aug 2026
28%-21.1behind31 Oct 2028under 10% built: too early to projectdubairealestateiq.com
Art House Private Residences by Viva
Viva · Majan
0%
23 Jun 2026
21%-21.1behind15 Feb 2028under 10% built: too early to projectdubairealestateiq.com
Cg Living
C G Gulf · Palm Deira
1.6%
18 May 2026
23%-21.1behind30 Jun 2028under 10% built: too early to projectdubairealestateiq.com
The Highgrove
Ellington Properties · Mohammed Bin Rashid City
7%
6 Aug 2026
28%-20.9behind31 Dec 2028under 10% built: too early to projectdubairealestateiq.com
ORLA, Dorchester Collection
Omniyat · Palm Jumeirah (The Crescent)
70%
21 Aug 2026
91%-20.8behind31 Dec 2026Feb 2028 – Mar 2028dubairealestateiq.com
Nanma Lotus
Nanma Properties · Madinat Al Mataar
3.6%
15 Oct 2026
24%-20.8behind15 Feb 2028under 10% built: too early to projectdubairealestateiq.com
Xenia Residence
N Y X · Jumeirah Village Circle
51.6%
15 Oct 2026
72%-20.8behind1 Mar 2027Sept 2027dubairealestateiq.com
Maravea Residences
Enzo Prime · Palm Deira
0%
8 Jul 2026
21%-20.8behind30 Apr 2028under 10% built: too early to projectdubairealestateiq.com
Franck Muller Yachting
London Gate · Dubai Maritime City
0%
26 Mar 2026
21%-20.7behind29 Jul 2028under 10% built: too early to projectdubairealestateiq.com
Hqa by Arista
Arista One · Jabal Ali First
0%
10 Aug 2026
21%-20.7behind30 Jun 2028under 10% built: too early to projectdubairealestateiq.com
DAMAC Riverside - Ivy
DAMAC Properties · Dubai Investment Park Second
38.1%
26 Aug 2026
59%-20.6behind31 Dec 2027Oct 2029 – Jan 2030dubairealestateiq.com
Rosewell
Nshama · Al Yelayiss 2
0%
26 Jun 2026
21%-20.6behind31 Dec 2028under 10% built: too early to projectdubairealestateiq.com
Le Blanc by Imtiaz
Imtiaz Developments · Dubailand Residence Complex
6%
8 Oct 2026
27%-20.5behind15 Oct 2028under 10% built: too early to projectdubairealestateiq.com
Prestige One Residences
Prestige Luxe Real Estate Development L.L.C · Dubai Maritime City
0.1%
23 Sept 2026
21%-20.4behind31 Dec 2029under 10% built: too early to projectdubairealestateiq.com
Nad Al Sheba Gardens Phase 11
Shamal · Nad Al Shiba First
0.1%
20 Aug 2026
20%-20.2behind1 Jul 2029under 10% built: too early to projectdubairealestateiq.com
Ocean Cove
Emaar Properties · Dubai Maritime City
17.9%
14 Apr 2026
38%-20.1behind31 Aug 2028Dec 2032 – Apr 2034dubairealestateiq.com
Golf Verge
Emaar Properties · Madinat Al Mataar
4.2%
22 Jul 2026
24%-20.1behind31 May 2029under 10% built: too early to projectdubairealestateiq.com
Voxa Residences
Pantheon · Jumeirah Village Triangle
4.5%
1 Jun 2026
25%-20.1behind31 Dec 2028under 10% built: too early to projectdubairealestateiq.com
Elwood Estates
Sobha Realty · Al Yufrah 1
14.4%
20 Jul 2026
34%-19.9behind30 Jun 2028Aug 2032 – Nov 2033dubairealestateiq.com
Ellington Sands I
Ellington Properties · Dubai Islands (Island A)
0.4%
5 Jun 2026
20%-19.8behind31 Dec 2028under 10% built: too early to projectdubairealestateiq.com
The Bristol Emaar Beachfront
Emaar Properties · Dubai Marina
5.8%
23 Jun 2026
26%-19.8behind30 Sept 2029under 10% built: too early to projectdubairealestateiq.com
Ellington Sands II
Ellington Properties · Palm Deira
0.4%
5 Jun 2026
20%-19.8behind31 Dec 2028under 10% built: too early to projectdubairealestateiq.com
HQ by Rove
IRTH Group · Business Bay
0.7%
6 Jul 2026
21%-19.8behind31 Mar 2029under 10% built: too early to projectdubairealestateiq.com
Alba Tower
Century Seven Properties L.L.C · Al Satwa
30.9%
27 Jul 2026
51%-19.8behind30 Jun 2028Dec 2030dubairealestateiq.com
Chelsea Residences 2 by DAMAC
DAMAC Properties · Dubai Maritime City
6.5%
11 Nov 2026
26%-19.7behind31 Dec 2029under 10% built: too early to projectdubairealestateiq.com
Jumeirah Residences Emirates Towers
Dubai Holding Real Estate · Trade Center Second
4.2%
28 Sept 2026
24%-19.6behind1 Sept 2030under 10% built: too early to projectdubairealestateiq.com
Palm Central Private Residences - Frond M
Nakheel · Palm Jabal Ali
0.1%
15 Sept 2026
20%-19.5behind31 Jul 2029under 10% built: too early to projectdubairealestateiq.com
Kyomi Residence
Anax · International City Ph 2 & 3
0%
12 Oct 2026
20%-19.5behind1 Jan 2028under 10% built: too early to projectdubairealestateiq.com
DAMAC Hills (2) - Violet 3
DAMAC Properties · Madinat Hind 4
36.2%
16 May 2026
56%-19.4behind30 Jun 2027Nov 2028 – Jan 2029dubairealestateiq.com
Palm Jebel Ali - Frond N
Nakheel · Palm Jabal Ali
58%
10 Nov 2026
77%-19.4behind8 Oct 2027Feb 2029 – May 2029dubairealestateiq.com
Solen Residence by Jamal Living
Mohammad Abuhijleh · Silicon Oasis (Nadd Hessa)
21.7%
13 Aug 2026
41%-19.4behind30 Oct 2027Sept 2029dubairealestateiq.com
Interstellar Tower
MR8 · Jumeirah Village Triangle
0%
6 Jul 2026
19%-19.3behind30 Sept 2028under 10% built: too early to projectdubairealestateiq.com
Orvessa Residences by Michel Adam
Bnw Echjay · Jabal Ali First
1.5%
10 Sept 2026
21%-19.3behind30 Sept 2028under 10% built: too early to projectdubairealestateiq.com
The Valley - Elea
Emaar Properties · Al Yufrah 1
22%
15 Jul 2026
41%-19.2behind30 Jun 2028May 2031 – May 2032dubairealestateiq.com
Azurline Residences by Maas Developers
M A A S Developers L.L.C · Jumeirah Village Circle
56.5%
28 Sept 2026
76%-19.2behind31 Mar 2027Dec 2027dubairealestateiq.com
Amis & Gpd Presents Fleur De Jardin Villas
Amis Gpd Developer L.L.C · Majan
0.6%
1 Sept 2026
20%-19.2behind9 Oct 2028under 10% built: too early to projectdubairealestateiq.com
Eaton Square
Ellington Properties · Bukadra
5.4%
20 Jul 2026
25%-19.1behind30 Jun 2028under 10% built: too early to projectdubairealestateiq.com
The Mural
OMNIYAT · Dubai Maritime City
16.6%
1 Oct 2026
36%-18.8behind10 Jul 2028Aug 2031 – Feb 2034dubairealestateiq.com
Verdana Residence
Reportage Properties · Dubai Investment Park First
0%
5 Aug 2026
19%-18.8behind30 Sept 2028under 10% built: too early to projectdubairealestateiq.com
Sierra by Iman
Iman Developers · Al Hebiah First
3.7%
10 Aug 2026
23%-18.8behind30 Jun 2029under 10% built: too early to projectdubairealestateiq.com
Sol Luxe
SOL Properties · Trade Center First
2%
30 Jun 2026
21%-18.8behind15 Mar 2029under 10% built: too early to projectdubairealestateiq.com
Wynwood Horizon
Imtiaz Developments · Meydan Horizon, MBR City
9.6%
16 Sept 2026
28%-18.7behind30 Oct 2028under 10% built: too early to projectdubairealestateiq.com
Address the Bay
Emaar Properties · Dubai Marina
70.1%
15 Jul 2026
89%-18.7behind31 Dec 2026Feb 2028 – Apr 2028dubairealestateiq.com
Enchante by Grid
Grid Properties · Arjan
1.6%
11 Nov 2026
20%-18.7behind15 Dec 2028under 10% built: too early to projectdubairealestateiq.com
Sea Cliff by Imtiaz
Imtiaz Developments · Dubai Islands
7.7%
13 Oct 2026
26%-18.6behind15 Aug 2028under 10% built: too early to projectdubairealestateiq.com
Golf Meadow
Emaar Properties · Madinat Al Mataar
4.5%
19 Jul 2026
23%-18.6behind31 Jul 2029under 10% built: too early to projectdubairealestateiq.com
Rabdan Gardens
Rabdan · Al Satwa
0%
23 Jun 2026
19%-18.5behind1 Mar 2028under 10% built: too early to projectdubairealestateiq.com

Next page

Method

Time elapsed = (inspection date minus construction start on the register) divided by (registered completion date minus construction start). When no start date is printed, the registration date is used.

Gap = % built at the inspection minus % of time elapsed at the same date, in percentage points. Behind = a gap below -10 points. Registered date passed = the inspection is after the completion date on the register and the project is not at 100%.

Projection, only for 10% to 99% built: the remaining % divided by the observed pace, where the pace is % built per day since the start date, since the registration date and between the last two inspections we hold (when it rose). The range runs from the earliest to the latest of these estimates.

Limits: Construction does not move in a straight line (a slow start, faster structure, slow finishing), so a straight line from an early reading tends to give later dates than the work will need, and a late reading can give earlier ones. The % built is the DLD inspection figure, not ours.

Source: the Dubai Land Department project register as mirrored per project with its inspection history, read by our register job; 985 DLD records, 28 with two or more dated inspections.

Files: /data/n35a/pace.json · /open/n35a-build.py · /registers/changes/